#SectionPDF pages
1Front matter / Contents1–5
2Executive Summary6–8
3Acknowledgements9–11
41. Introduction12–15
52. The User Requirements16–19
63. Legal Requirements – Applicable Legislation20–23
74. The Design and Specification Process24–35
85. Ventilation Strategies36–44
96. Energy Control Strategies45–47
107. Environmental Control48–51
118. Specific Healthcare Department Requirements – General considerations52–56
128. Specific Healthcare Department Requirements – Operating department57–65
138. Specific Healthcare Department Requirements – Ultra-clean ventilation system66–73
148. Specific Healthcare Department Requirements – Barn and semi-barn theatres / 8. Specific Healthcare Department Requirements – Hybrid theatres74–75
158. Specific Healthcare Department Requirements – Neutral pressure theatres for infectious patients / 8. Specific Healthcare Department Requirements – Interventional imaging suites76–77
168. Specific Healthcare Department Requirements – Other application-specific design guidance78–81
178. Specific Healthcare Department Requirements – Hydrotherapy: general requirements82–87
189. Equipment Selection Factors – General requirements88–92
199. Equipment Selection Factors – Supply AHUs and associated extract units (pages 93–100)93–100
209. Equipment Selection Factors – Supply AHUs and associated extract units (pages 101–108)101–108
219. Equipment Selection Factors – Supply AHUs and associated extract units (pages 109–113)109–113
229. Equipment Selection Factors – Distributed air-conditioning elements / 9. Equipment Selection Factors – AHUs: automatic control114–120
239. Equipment Selection Factors – Local exhaust ventilation (LEV)121–123
2410. Installation Standards124–128
2511. Commissioning Systems129–139
2612. Acceptance Testing: Validation – Appointment of validator / 12. Acceptance Testing: Validation – First fix inspection140–141
2712. Acceptance Testing: Validation – Permeability testing142–146
2812. Acceptance Testing: Validation – UCV canopy leakage tests147–148
2912. Acceptance Testing: Validation – Vertical flow UCV canopy air velocity tests / 12. Acceptance Testing: Validation – UCV canopy entrainment test149–154
3012. Acceptance Testing: Validation – UCV terminal control system checks / 12. Acceptance Testing: Validation – UCV theatre microbiological tests155–157
3112. Acceptance Testing: Validation – Radiopharmacy aseptic preparation facilities / 12. Acceptance Testing: Validation – Containment level 3 laboratories158–159
3213. Information160–166
33Appendix 1: Typical AHU Plant Layouts167–168
34Appendix 2: Summary of design conditions169–170
35Appendix 3: Hierarchy of cleanliness / Appendix 4: Leakage flows in m3/s through closed door gaps171–172
36Appendix 5: Recommended airflow rates in m3/s through a doorway between rooms of different cleanliness to control cross-contamination / Appendix 6: Typical approximate pressures in an operating suite when a given door is open173–174
37Appendix 7: Operating suite design logic175–186
38Appendix 8: Design of air- movement control schemes for operating theatres – General / Appendix 8: Design of air- movement control schemes for operating theatres – Peripheral room type187–188
39Appendix 8: Design of air- movement control schemes for operating theatres – Air-movement control in peripheral rooms189–192
40Appendix 8: Design of air- movement control schemes for operating theatres – Transfer grilles / Appendix 8: Design of air- movement control schemes for operating theatres – Pressure-relief dampers193–194
41Appendix 8: Design of air- movement control schemes for operating theatres – Room temperature estimation / Appendix 8: Design of air- movement control schemes for operating theatres – Relief of excess air from operating theatre when all doors are closed195–199
42Appendix 8: Design of air- movement control schemes for operating theatres – Calculation sheet for flow rates200–213
43Appendix 9: Design of air- movement control scheme for anaesthetic room214–215
44Appendix 10: Example cause-and- effect check-sheets216–218
45Appendix 11: References219–224
46Appendix 12: Abbreviations used in this document225–227