13. Information

Records required

There is a requirement under the Building Regulations to provide documentary evidence of the design, commissioning and subsequent performance of ventilation systems as well as recommended maintenance routines (Building Regulations. 2010, Part 8, Paragraph 39).

Electronic records should be in a format that is compatible with the client’s archive and retrieval system.

Handover

The following general information is required at plant handover:

“as fitted” drawings of the plant showing the location of all items and listing the size of ducts, grilles and diffusers together with their factors;

“schematic” drawing of the air distribution system showing design and actual airflows from all outlets together with the design and actual airflows in each duct. The duct centre correction factors should be given and the grille factors;

the location of all volume control dampers should be marked on the “as fitted” and “schematic” drawings;

a floor plan of the area served by the plant showing all doorways, hatches, transfer grilles, pressure relief dampers, pressure stabilisers, supply and extract terminals. The total supply and extract volumes should be shown for each room served by the plant. The volume flow and direction of flow through transfer grilles, pressure relief dampers and pressure stabilisers should also be shown, together with the room pressures in pascals measured with regard to atmospheric pressure. For operating suites the “key” door should be identified;

a fire plan of the area served showing the fire zone and location of all fire and smoke dampers and detectors. An explanation of the ventilation strategy in the event of an in-zone fire, adjacent zone fire or smoke being drawn into the airhandling unit from an outside source should be provided.

wiring diagrams for all electrical equipment associated with the air handling systems including motor control circuit details and any interlocking and safety devices such as emergency stop buttons adjacent to the item of plant;

manufacturer’s operating instructions and “setting to work” guidance for all specialist components incorporated in the systems;

- a schematic of the control system showing the location of all plant sensors;

- control algorithm(s) of the actual plant operation and the set points entered

during commissioning together with the control panel access codes and keys.

Plant design information

The following plant design information is required at plant handover:

[SHTM 03-01 Part A – PDF page 161]

a simple statement of the design intent;

a description of the plant’s intended mode of operation;

winter outside design temperature in ºCdb;

winter outside design humidity in % saturation;

winter room supply air design temperature in ºCdb;

winter room supply air design humidity in % saturation;

winter inside design temperature for each room in ºC;

winter inside design humidity for each room in % saturation;

summer outside design temperature in ºCdb;

summer outside design humidity in% saturation;

summer room supply air design temperature in ºCdb;

summer room supply air design humidity in % saturation;

summer inside design temperature for each room in ºC;

summer inside design humidity for each room in % saturation;

winter psychrometric chart showing the condition of the air between all items of plant and the design outside, supply and room air conditions;

summer psychrometric chart showing the condition of the air between all items of plant and the design outside, supply and room air conditions;

the design mass airflow rate used to size the plant in kg/s;

the design volumetric flow rate in m 3/s.

Individual equipment information

Heater-batteries including energy recovery

The following information concerning heater-batteries is required at plant handover:

the size of the battery, number of passes and fin spacing;

the design flow and return temperatures and flow rate in L/s;

the pressure drop across the water side of the battery in Pa;

the number of phases, supply voltage, current drawn and number of steps if electric;

the maximum rated capacity of the battery and actual design rating in kW;

the design and actual face velocity in m/s;

the pressure drop across the air side of the battery in Pa;

the design on and off coil air temperature and humidity at winter and summer design conditions

Cooling coils

The following information concerning cooling coils is required at plant handover:

[SHTM 03-01 Part A – PDF page 162]

the size of coil, number of passes and fin spacing;

the design flow and return temperatures and flow rate in L/s if chilled water;

the pressure drop across the water side of the coil in Pa;

the supply pressure and mass flow rate if direct expansion;

the maximum rated capacity of the coil and actual design rating in kW;

the contact factor;

the design sensible and latent cooling loads in kW;

the design and actual face velocity in m/s;

the pressure drop across the air side of the coil in Pa;

the design on and off coil air temperature and humidity at summer design conditions.

Humidifiers

The following information concerning humidifiers is required at plant handover:

the size of the humidifier and number of lances;

the supply pressure and mass flow rate of the steam;

the number of phases, supply voltage, current drawn and number of steps if electric;

the maximum rated capacity of the humidifier and actual design rating in L/hour;

the design and actual face velocity in m/s;

the design upstream and downstream air temperature and humidity at winter design conditions

Filters

The following information concerning filters is required at plant handover:

the size of the filter and number in bank;

its grade;

the design and actual face velocity in m/s;

the initial pressure drop across the filter when clean in Pa;

the final pressure drop across the filter when dirty in Pa;

the manufacturer’s name and filter identification code.

Fans

The following Information concerning fans is required at plant handover:

the size of the fan and its type;

the fan curve;

speed and direction of rotation;

[SHTM 03-01 Part A – PDF page 163]

the drive motor frame size;

the number of phases, voltage and maximum design and actual current drawn;

the design and actual delivered air volume in m3/s;

the fan suction pressure at high and low speed in Pa;

the fan delivery pressure at high and low speed in Pa;

Attenuators

The following information concerning attenuators is required at plant handover:

the size of the attenuator and number in bank;

the design and actual face velocity in m/s;

the initial pressure drop across the attenuator in Pa;

the upstream sound level in dB(A); the downstream sound level in dB(A).

System information

The preservation of information and records of ventilation systems and their performance is a legal requirement. It is therefore essential that when new systems are completed, full information as to their purpose, design, layout and actual commissioned performance are handed on to the client. If any derogations were agreed from this standard, they should be noted and the reason for them explained. The system information if electronic (for example, BIM model) should be in a form that is compatible with the client’s IT standard and can be accessed and searched by it.

In new “green field” developments an inventory of the installed ventilation systems should be compiled. In existing developments the client will normally have an inventory of their installed systems, and all new systems should be added to it.

The inventory will be subdivided into the following categories:

local exhaust ventilation systems (LEV) – note these are statutory items;

critical healthcare ventilation systems (CHV).

(These are systems the loss of which would seriously limit the delivery of healthcare – for example, operating suite, SCBU, critical care areas, interventional imaging suite, aseptic preparation facility.)

general ventilation system [supply and extract] (GVS);

general extract systems (GES);

systems installed for smoke clearance in the event of a fire, classed as smoke and heat exhaust ventilation systems;

– (SHEVS) (for example, smoke extract fans in stairwells, automatic smoke clearance dampers in atria).

Note: During the design and contract process, ventilation systems are often given “construction” codes for drawing reference and site identification purposes. It is

[SHTM 03-01 Part A – PDF page 164]

imperative that prior to handover the actual identification codes and labels affixed to the systems conform to the inventory in use at the site or desired by the client. Each system code should be unique and conform to the categorisation format for the client’s inventory given above.

For ease of future reference, a list of design and construction references for drawings and plant, cross-referenced to the client’s building designations and plant inventory codes, should be produced.

For each ventilation system the inventory should contain the following details:

a unique system identification code (for example, LEV 001; CHV 001) as appropriate;

the location of the ventilation fan unit or supply and extract AHU(s);

the location of the fresh air inlet;

the location of the extracted air discharge;

the specific area(s) served by the system;

the date the system was installed;

the date the system was validated and accepted by the client.

Each ventilation system should have a logbook (physical or electronic) that contains the following information:

the unique system identification reference;

purpose of the system;

date of installation;

details of the installed equipment and ductwork layout;

detail of the fire plan and location of fire and smoke dampers;

design performance parameters (for example, airflow rates, air-change rates, pressures);

commissioned date and performance;

record of the system validation and acceptance;

records of the annual inspection and verification;

maintenance records and plant information (for example, fan specifications and filter sizes).

The records should be linked to the inventory and stored in such a way as to be readily available in the event of plant breakdown or other incident.

Every ventilation system should be clearly identified with a permanent label. The label should show in lettering 100 mm high the inventory reference code of the AHU and clearly identify the area that it serves. The label should be mounted with screws or rivets in an easily visible place near the fan of the unit adjacent to the local electrical isolator. The system control panel should have a duplicate label. Any subsystems and the principal branch ducts should be similarly labelled.

[SHTM 03-01 Part A – PDF page 165]

The nature of air and direction of flow should be clearly marked on all ducts using the symbols given in BS 1710.

All airflow test-points should be clearly identified with a permanent label and the design information given (for example, TPS 1 – Anaesthetic supply; 400 × 300; Design 185 L/s).

If two ventilation systems supply a common room or an outlier from another zone, the room identification label should state the relevant ventilation identification codes, for example: Theatres 5&6 Utility; [CHV 012 and CHV 015], as should the labels on their individual AHUs.

Any ventilation system that conveys a hazardous substance or is affected by a hazardous radiation must be clearly marked with the appropriate symbol.

Fire and smoke dampers

A complete schedule of dampers fitted, their location and unique identification code should be provided.

A statement of when they were tested and by whom should be included.

Spares

Unless otherwise agreed with the site maintenance department, spares should be stored on a rack in the entrance of the relevant plantroom and preserved from casual damage or contamination.

The scale of spare fans to be provided should relate to the number of AHUs using fans of the same size. The spare fans should be pre-wired with power and control connectors so that when used they are plug and play.

A complete set of new filters should be handed over.

A complete set of any other consumable item installed in the installation should be handed over.

BIM status

If the installation was modelled using BIM during construction, the BIM model should be brought up to date and all asset tags incorporated prior to handover.

Training for estates staff who will be tasked with keeping the BIM model in date should be given, ideally while the original BIM team is available.

Maintenance routines

Any product or installation-specific maintenance routines should form part of the handover documentation and, if necessary, training.

Information on routine inspection and maintenance is given in Part B of Scottish Health Technical Memorandum 03-01.

[SHTM 03-01 Part A – PDF page 166]

Expected service life

Air handling units (AHUs) have an expected service life of 20 years. Part B of this SHTM states that ventilation systems should be taken out of service, deep cleaned, their controls renewed and recommissioned after 10 years. The handover information will both assist this process and help inform the selection of replacement plant.

Additional end user information

The information itemised above is intended to fulfil the contract requirement and provide a record for the client and their appointed operational management and maintenance teams. There is also a need in some circumstances to provide the end- user with information as to the role that them and their patients from airborne contaminants.

In operating suites and interventional imaging suites of any type, a simplified plan of the suite showing the principal direction of air movement should be displayed at the entrance to the suite. The following bullet points should be appended to the plan:

the air supplied to each room is intended to dilute any airborne contaminants;

the airflow between rooms will ensure that contaminants do not enter;

people are the main source of airborne contaminants; they disperse such contaminants as they move around: the more people, the more movements, the more airborne contaminants;

optimum conditions exist when all doors are closed;

in order to ensure that the system operates correctly and efficiently:

- routine checks should be carried out of the system performance;

- the system should be taken out of use periodically to carry out essential

maintenance.

The VSG should advise if other applications require similar explanatory information.

Staff training

On completion of the project, training in the correct use, operation and routine maintenance of the installed systems should be given as appropriate to the following staff groups:

the end-users;

those who will operate and maintain the installed systems.