Vertical flow UCV canopy air velocity tests
Test setup
The canopy face diffuser screen should be in place for these tests.
12,71 Take spot readings to establish that the room is within the specified temperature and humidity test conditions.
Set out the test grid as described previously.
Swing the operating lamp arms and any other stem arms so that they align to present the least resistance to airflow, are perpendicular to the front edge of the test sheet and face the back edge. Any lamp and equipment heads should as far as practicable be outside of the UCV canopy footprint (see photographs).
Test instrument
The measuring instrument should be a thermal anemometer with a digital readout. The instrument resolution should be at least 0.01 m/s, have a tolerance of ±0.015 m/s or 3% and be calibrated down to 0.15 m/s or lower. An alternative instrument may be used providing it is of no lesser specification.
Test method
The instrument should be mounted on a test stand and set to take a mean reading over a 10-second sample interval.
The test instrument should record readings automatically for later download or be connected to a printer.
The test stand should be positioned on each test point in turn and the reading taken when the instrument has stabilised.
When taking a reading, the test person should not stand within the same quadrant as the test instrument.
Readings are to be taken at the test positions with the instrument probe facing the wall housing the theatre control panel commencing at the first test position. Readings are taken either working along the rows from left to right or for all test positions in one quadrant at a time.
When all test positions under one half of the canopy have been covered, readings of temperature and humidity are taken at the specified height in the centre of the canopy. The readouts from the theatre control panel should be recorded at this time.
Having completed one half of the test grid, the operating lamp arms and any other stem arms should be swung round through 180º and the test stand reversed so that the wall housing the theatre control panel is behind the test person. Readings are recommenced starting at the right of the test row and working from right to left or a quadrant at a time, as above.
[SHTM 03-01 Part A – PDF page 150]
UCV canopy high level discharge velocity test
Measurements of air velocity are to be taken at every test position 2 m above floor level and the results averaged. The average of the total readings taken is to be not less than:
0.38 m/s for a canopy with no side walls or side walls that terminate at 2 m above floor level.
0.30 m/s for a canopy with side walls that terminate 1 m above floor level.
For UCV canopies that are an assembly of two or four units, each fed by a recirculation fan, the average air velocity for each unit should not exceed ±6% of the measured average velocity for the canopy.
Figure 12: UCV 2m air velocity test set-up
UCV canopy low level air velocity test
Measurements of air velocity are to be taken at each of the inner zone test positions 1 m above floor level.
The measured velocity at every test position in the inner clean zone should be not less than 0.20 m/s.
Figure 13: UCV 1m air velocity test set-up
UCV canopy entrainment test
Rationale for the entrainment test
The performance of a UCV canopy may be compromised by room air being drawn into the ultra clean airflow, a phenomenon known as entrainment. Significant levels of entrainment could lead to microbial contamination of items left exposed on instrument trolleys laid out beneath the canopy.
[SHTM 03-01 Part A – PDF page 151]
UCV canopies having permanently fitted side walls that terminate 1 m above floor level do not need to be tested, as the walls physically prevent entrainment.
Principle of the test
A source of particles is produced outside of the UCV canopy footprint and is used to challenge the system. A sample probe and detector are placed within the ultra clean airflow and used to determine the percentage penetration of the test particles at predefined locations under the UCV canopy footprint. The source and sample probe are moved in tandem around the UCV canopy and pairs of readings taken at the detector, from which the percentage penetration at specified locations is calculated. The degree of penetration should be below specified maximum limits if entrainment is to be declared not significant.
Test setup
The challenge will be provided by using non-EPA-filtered air emerging from the preparation room via the pressure stabiliser or transfer grille and ducted to the specified release position.
The canopy face diffuser screen should be in place for these tests.
The test is performed without any theatre equipment in place beneath or closely adjacent to the UCV canopy. All doors in the theatre suite should be closed and remain so for the duration of the test.
The operating lights and support booms should be moved to a central position beneath the canopy and raised to 2 m above floor level, so as not to interfere with the peripheral airflows (see photograph).
Spot readings are taken at the centre of the canopy, 1 m from floor level, to establish that the room is within the specified temperature and humidity limits (see paragraph 12.47).
The test grid is set out as described previously (see paragraph 12.50).
Test equipment
The source unit will be a fan/blower or other method that ducts non-EPA- filtered air (see paragraph 12.89) and expels it via a delivery head mounted on a test stand or clamped to the UCV canopy sidewall at the specified release position to provide the particle challenge. The challenge air will be delivered vertically downwards from a position 2 m above floor level alongside the outside edge of the side wall or in line with the downward air curtain if the canopy does not have side walls. The challenge airflow velocity should be the same as the measured average velocity at the 2 m level for the canopy under test.
[SHTM 03-01 Part A – PDF page 152]
Figure 14 UCV entrainment test setup
The detector will be an LSAPC capable of sampling a minimum of 28.3 L of air (1 ft3) per minute and providing readings for particle sizes from to 5 µm to 0.3 µm. Measuring instruments should be compliant with the requirements of BS EN ISO 14644 or ISO 17141 to reflect the type of test. An alternative instrument may be used providing it is of no lesser specification
The sampling head will be an isokinetic fishtail scanning probe mounted horizontally on a test stand 1 m above floor level and connected to the LSAPC by a hose no longer than 2 m
Test positions and orientation of source and detector sampling probe
The test positions will be at the centre of each test square, as defined for the velocity test (see paragraph 12.50).
For rectangular UCV canopies, measurements of penetration are to be taken at the four corner test squares of the test grid and at intermediate positions along the line of test squares between the corners. The number of intermediate test positions will be
[SHTM 03-01 Part A – PDF page 153]
as equally spaced as possible around the periphery, with not fewer than three and not more than five complete test squares between test positions.
A further series of measurements are to be obtained around the periphery of the inner zone (defined in paragraph 12.54). Measurements of penetration are to be taken at the four corner test squares of the inner zone of the test grid and if necessary at intermediate positions along the line of test squares between the corners as equally spaced as possible, with not fewer than three and not more than five complete test squares between test positions.
The centre of the challenge particle source delivery head is aligned with the centre of the designated test square, with its longer edge against the outer edge of the side wall or air curtain and delivering the challenge 2 m above floor level. The air containing challenge particles is directed vertically downward. Where there is physical interference due to obstructions such as gas pendants, the source will be moved to the next available non-obstructed test square location nearest to the stipulated test position. The sampling probe will then also be moved to remain opposite the source.
In the case of non-rectangular canopies, an interpretation of the above strategy should be adopted that will yield a no less searching examination of the unit’s ability to control entrainment.
Test method
A measurement of particle penetration through a representative section of the EPA filter media is to be taken. The smallest non-penetrating particle size will be used as the reference background level and set in the detector instrument. The detector instrument should be set to take a reading over a 15-second sample interval and record the number of particles at the non-penetrating particle size determined above.
An initial sample of air at the source delivery head should be taken to check that there are sufficient particles of the considered size present. The challenge will be considered suitable if:
the particles are within the size range 5 to 0.3 µm and thus capable of remaining airborne for a substantial time;
the particles should not be able to penetrate the canopy EPA filters in sufficient numbers to cause a background count that is more than 0.1% of the challenge count;
the number of particles present will enable a minimum of three logarithm (1000- fold) range of counts to be recorded between the source and background readings. A concentration of approximately 105 particles per cubic metre of source air has been shown to be adequate.
Note: The same equipment should be used to measure both the challenge source and penetration so as not to bias results through particle losses within the test equipment.
The sampling probe of the detector instrument is mounted on a test stand with its orifice facing outwards horizontally from the centre of the UCV canopy, 1 m above floor level. The sampling probe will be orientated at right angles to the partial wall
[SHTM 03-01 Part A – PDF page 154]
when sampling along the sides of the test grid but will be set to bisect the angle when measuring at the corner test positions. (See Figure 15 for test locations and see photograph of entrainment test equipment in Figure 13.)
The test will commence at the first test position; this being designated the left-most corner of the test grid when facing the wall housing the theatre control panel. The penetration will also be measured at the corresponding test point on the inner zone commencing at the corner nearest to the first test position.
When these tests have been completed, the source distribution head and sampling probe will be moved to the next test positions, working around the test grid in a clockwise direction.
The test stands will be positioned on each test point in turn and a pair of readings (challenge, then penetration) taken when the instrument has stabilised.
When taking a reading, the test person should stay within the UCV canopy footprint but on the side opposite the sampling probe.
A single measurement will be taken at the geometrical centre of the UCV canopy footprint. The centre measurement will be taken with the sampling probe mounted vertically 1 m above floor level
Figure 15: Entrainment test locations for a 2.8 m ×2.8 m UCV terminal
Note: Test grid layout is as for Figure 11. Entrainment test set-up and guidance is given in paragraphs12.86 onwards.
For this test the challenge source distribution head will be placed at the test position that yielded the greatest penetration at the periphery of the canopy footprint.
Analysis and interpretation
The following standard is to be achieved:
penetration to be no greater than 10% of the challenge at each test position in the outer zone;