SHTM 03-01 Part A: 12. Acceptance Testing: Validation – UCV terminal control system checks / 12. Acceptance Testing: Validation – UCV theatre microbiological tests

Ventilation for Healthcare - Design and validation (SHTM 03-01 Part A) · PDF pages 155–157 of 227 · Source file: shtm-03-01-part-a-v30-feb-2022.pdf
Unofficial text extract. Tables and figures may be incomplete. Authoritative version: official PDF from NHS National Services Scotland.

[SHTM 03-01 Part A – PDF page 155]

penetration to be no greater than 1% of the challenge at each test position in the inner zone;

penetration to be no greater than 0.1% of the challenge at the centre of the test grid.

If a result is close to or above the given limits, a further reading should be obtained using a longer time base (1 minute) and the penetration should not exceed the given limit.

UCV canopy flow visualisation

The use of smoke to gain an understanding of the overall performance of the canopy may prove useful at this stage in the validation process but cannot be relied on to produce a contractually definitive measure of performance.

UCV canopy noise level

An industrial-grade sound level meter to BS EN 61672 Type 2 fitted with a muff will be used to check the noise level. The instrument should be calibrated using a matched sound source prior to each set of readings.

The noise level readings are to be taken at a typical normal listening position 1.5 m above floor level and at least 1 m from any surface and not on any line of symmetry. Measurements should be taken under the centre of each quadrant and in the centre of the canopy, and the five readings averaged.

The readings should be taken with the UCV canopy at operational speed and repeated with it at set back.

For UCV operating suites, the noise level should not exceed:

operating theatre and spaces without doors that are open to it (for example, the scrub): 53 dB(A);

all other peripheral rooms of the suite: 48 dB(A).

UCV terminal control system checks

Temperature

The readings of temperature taken under the UCV canopy should be within ±1ºC of the readout on the theatre control panel.

Humidity

The readings of humidity taken under the UCV canopy should be within±5%RH of the readout on the theatre control panel.

Direct reading differential pressure gauges

The differential pressure across the terminal filter should be measured to confirm the accuracy of the indicated reading of any gauge.

[SHTM 03-01 Part A – PDF page 156]

Control functions

The operation of all control functions provided on the theatre control panel should be checked for conformity with the design specification (see Appendix 10).

If an auxiliary panel has been fitted, its interlocking with the main theatre control panel control functions will be checked for conformity with the design specification.

Panel indicator lights

The panel indicators should illuminate as appropriate when the control functions are selected, or warning levels are reached (see Appendix 10 for an example “cause and effect” test regime).

BMS interface

The operation, monitoring and alarm functions should be checked for conformity with those set out in the design specification.

UCV theatre microbiological tests

There is little value in performing microbiological sampling in an empty operating theatre supplied with ultra clean ventilation. The foregoing filter challenge tests, air velocity measurements and entrainment test will have proved that the system operates satisfactorily and achieves the contracted level of performance. The EPA filters will remove bacteria-sized particles from the air supplied through the UCV canopy. Therefore, there will be an insignificant number of bacterial and/or fungal cfus present until the theatre is actually used.

Following full validation, in-use microbiological sampling during a surgical procedure will not be required unless specified by the client’s VSG.

UCV operating suite validation report

Following validation, a full report detailing the findings will be produced and sent to the client’s lead project manager. The report should conclude with a clear statement on whether the UCV operating suite as a whole achieved or did not achieve the standard set out in the agreed design specification.

The client’s lead project manager should lodge a copy of the report with:

theatre manager;

infection prevention and control;

estates and facilities.

Pharmacy aseptic preparation facilities

The following regime of inspection and testing should be applied to the validation of new installations. The test regime has been devised to ensure that the system as installed fully achieves the operational requirement for these systems as set out in EUGGMP and the design specification.

[SHTM 03-01 Part A – PDF page 157]

Basic requirement

The validation procedure set out in paragraphs 12.1–12.33 should have been satisfactorily completed prior to attempting to validate the aseptic preparation facility. The suite to be validated should be physically complete with final finishes applied and have been completely cleaned. All ventilation systems serving it should be operating correctly and delivering their design airflow rates.

Aseptic preparation facility validation procedure

Tests to validate the suitability and performance of the aseptic preparation facility should be undertaken in the order that they appear below. Should an item fail to meet the required standard it should be rectified and successfully retested before passing on to the next test.

Summary of test regime

Challenge tests should ensure that:

the supply terminal HEPA filters are sealed in their housings so that no air will bypass them;

the terminal filters are of a uniform quality and undamaged.

Differential pressure measurements should ensure the correct pressure cascade.

Particle counting should be carried out at a specified number of test positions in order to determine the individual cleanroom classification in accordance with ISO EN 14644 and ISO 17141.

Control system checks should ensure that the system operates as specified.

Microbiological sampling should check the air quality.

Test and measuring conditions

While validating the aseptic preparation facility, the conditions in the cleanrooms should be stable and within the given ranges.

Temperature: 19–23ºC dry bulb.

Humidity: 30–70% relative humidity.

Test and measuring equipment

Any test or measuring equipment used should have a certificate to prove that its calibration has been checked within the previous 12 months at a facility using traceable national standards.

Supply terminal EPA or HEPA filter seal leak test

The test will confirm that there is no unfiltered air bypassing the EPA or HEPA filter seal.

Each EPA or HEPA filter seal should be scanned using a light scattering airborne particle counter (LSAPC) to prove that there are no leaks.