SHTM 03-01 Part A: 4. The Design and Specification Process
[SHTM 03-01 Part A – PDF page 24]
4. The Design and Specification Process
Project brief
The ventilation aspects of a contract will normally form part of a wider project to provide, upgrade or replace a healthcare facility. It is important that the ventilation designer closely liaises with the architect, as the layout of the facility and the adjacency of spaces within it will have a major impact on the ability of the ventilation system to achieve the client’s requirements. All new major projects are required to use building information modelling (BIM) in order to ensure a coordinated design and provide information for the subsequent operation and possible future development of the facility.
The Building Services Research and Information Association (BSRIA) has produced an approach to project delivery known as “Soft landings” (BSRIA, 2018). It aims to ensure that the client’s success criterion is kept in focus during the inception and briefing, design, construction, pre-handover, initial aftercare and extended aftercare phases of a project. It is strongly recommended that the client and project contractor adopt this approach.
Basis of design
This SHTM assumes that designers will be familiar with current CIBSE guidance and will use it as the basis for specifying and designing ventilation systems. However, the actual guidance contained in this SHTM may differ from the CIBSE guidance due to healthcare-specific issues and will take precedence over the CIBSE guidance where there are conflicts.
Note: Scottish Health Technical Memorandum 03- 01 Parts A and B need to be read and considered in their entirety when specifying and designing ventilation systems to ensure that the end result will comply with the client’s needs.
Ventilation Safety Group (VSG)
The management of the ventilation systems of a healthcare provider should be overseen by a Ventilation Safety Group (VSG). The VSG should have clearly defined roles and responsibilities, be part of a healthcare organisation’s governance structure and report to the “Designated Person” at Board level. It should be led and chaired by a person who has appropriate management responsibility, knowledge, competence and experience (for example, the Designated Person). (See Chapter 2 in Part B of Health Technical Memorandum 03-01 for further information.)
The VSG should be a multidisciplinary group and should typically comprise:
an Authorising Engineer/independent adviser for ventilation (AE(V));
an Infection Prevention and Control person;
the Authorised Person(s) for ventilation services (AP(V));
estates (operations and projects) staff;
[SHTM 03-01 Part A – PDF page 25]
clinicians and specialist departments (for example, theatres, critical care areas, pharmacy, medical microbiology, nursing, decontamination);
personnel from the finance department with accountability for capital and revenue evaluation;
other stakeholders as appropriate;
coopted expertise (for example, ventilation designers, consultants and suppliers).
The VSG remit should be to assess all aspects of ventilation safety and resilience required for the safe development and operation of healthcare premises. It should inform the following areas:
the design process for new healthcare premises;
the design process for modifications to existing premises;
the commissioning and validation process;
operational management and maintenance;
annual verification and performance testing;
prioritising the plant replacement programme;
decommissioning and removal of redundant equipment.
Note: Where estates and facilities provider services are part of a contract (including PFI), it is essential that these providers participate fully in all those aspects of estate and facilities management that can affect patients. This includes responding to specific requests from the VSG, which may be in addition to relevant guidance and documentation.
It is important that decisions affecting the resilience, safety and integrity of the ventilation systems and associated equipment are not taken without the agreement of the VSG. The VSG should ensure that appropriate expertise and competence is available when making such decisions.
Whenever significant building work is undertaken; the VSG should consider its effects on the existing ventilation system air intakes. These may need to be protected from airborne dust during construction by the fitting of temporary additional filtration. There will also be a need to identify any risks to construction personnel who may be working in the vicinity of extract air discharges.
When construction or alteration work is undertaken inside an occupied building, its effects on the occupiers should be considered. The VSG should be consulted, and they may require that the area be sealed off from the occupied parts of the building and that a temporary extract be provided to maintain the worksite at a negative pressure to prevent the spread of dust into the rest of the building.
[SHTM 03-01 Part A – PDF page 26]
Derogations and alternative design strategies
Any derogations or alternative design strategies from this guidance should be subject to the scrutiny and agreement in writing by the VSG. The reason for the derogation or alternative design strategy and limits to its application should be recorded.
Designers proposing a derogation or alternative design strategy should be able to supply a body of evidence that their proposal will provide a degree of safety no less than if the guidance in this document had been followed.
Definition of clinical areas and critical systems
Healthcare ventilation may serve clinical or non-clinical areas of the estate:
clinical areas are defined as spaces within the building where surgical or medical treatment is administered to patients. This includes patient bedrooms;
non-clinical areas are defined as spaces where patients may be present but are not under direct treatment. It also includes staff and healthcare services areas.
Certain clinical and non-clinical areas within a healthcare establishment are considered critical to its ability to provide healthcare. Typically, ventilation systems serving the following are considered critical:
operating suites of any type including rooms used for image-guided surgical procedures and their recovery areas;
airborne isolation facilities, both source and protective;
critical care areas and neonatal units;
invasive treatment, endoscopy and bronchoscopy rooms;
containment level 3 laboratory;
pharmacy aseptic preparation facility;
inspection, assembly and packing (IAP) room in a central decontamination unit;
MRI, CAT and other types of emerging imaging technologies that require particularly stable environmental conditions to remain within calibration;
any system classified as an LEV system under the COSHH Regulations;
any other system that clearly meets the definition that “a loss of service from such a system would seriously degrade the ability of the premises to deliver optimal healthcare”.
Note: If any doubt exists about whether a system falls within this definition, the VSG should be consulted regarding the risk to patient safety and business continuity.
Resilience and diversity
When planning the ventilation of healthcare facilities, it is important at the outset to consider how the service will be delivered if the installed ventilation system fails or the area served has to close due to the effects of fire, flood or an outbreak of
[SHTM 03-01 Part A – PDF page 27]
infection. The loss of power, primary heating or cooling medium, or an integrated control system can cause the loss of ventilation to an area, so subsystem resilience is an important consideration.
Resilience in critical healthcare areas can be provided by splitting the ventilation load between two or more AHUs and/or employing a design that allows two or more AHUs to feed a common plenum with isolation dampers on individual branches to each critical zone. (Note that it is not proposed that duplicate back-up units be provided.) As an example, a large critical care area (CCA) level 2 or 3 could be split into two sections with an AHU for each. A small CCA cannot easily be split, so a decant area with a suitable level of ventilation should be pre-designated.
Diversity can be achieved by having several facilities each served by its own AHU. As an example, in an operating department, if each theatre suite is fed from its own dedicated AHU, the loss of one suite, while inconvenient, will not shut the department. The same scenario applies to isolation rooms if several of them are each independently ventilated (see Health Building Note 04-01 for further information).
Note: Providing twin ventilation fans in an AHU delays the time at which the system needs to be completely shut down in the event of a fan failure. It does not in itself provide resilience in terms of delivering healthcare (see Chapter 9 for further guidance).
New build facilities
New build healthcare facilities must be fully compliant with the requirements of all legislation in force at a date agreed when signing the contract. They should comply with the guidance contained in the current SHTM unless a derogation has been agreed with the VSG (see paragraphs 4.10 and 4.11).
Assessment of service requirements: selection of design criteria
External design conditions
The most accurate data that is available for the summer and winter conditions at the site should be used. The Meteorological Office supplies data for the United Kingdom; data is also available from CIBSE and other sources. It is essential that the designer agrees with the client as to which source of data is used and the design risk associated with the chosen external design conditions.
Note: It is essential to design to future climate projection to ensure design temperatures are maintained even in the event of prolonged heatwave conditions. CIBSE (2014) publishes design summer year weather files morphed to reflect future climate change.
Local adjustments for height above sea level, exposure factor, or other local climate peculiarities should be made as appropriate.
Internal design conditions
The design conditions selected within patient areas should strike a balance between the comfort requirements of staff and patients, who often have very different levels of clothing and activity.
[SHTM 03-01 Part A – PDF page 28]
Recommendations for the operative temperature and humidity of individual spaces are given in Activity Data A-Sheets (see Chapter 8 for specific requirements). Particular departmental requirements are given in the respective SHPN/HBN and room data sheets. However, the determination of the room environment must be driven by the patient cohort plus the range of procedures envisaged for that room.
Minimum fresh air requirements
In general areas and wards within healthcare premises, odour control is the main reason for providing ventilation. In the absence of other guidance, 10 L/s/person should be taken as the minimum ventilation requirement. Healthcare ventilation systems will normally be “full fresh air” either by natural, mixed mode or mechanical means, with energy recovery from the extracted air.
In non-clinical areas recirculated air systems may be considered. At least 20% of the recirculated air should be fresh. Additional filtration will be required to remove airborne particulate contamination and, if necessary, odours. This will affect running and maintenance costs and, given the high ErP rating of heat recovery devices, it will be necessary to prove that recirculating the air will be more energy- efficient overall.
Note: Ultra clean ventilated (UCV) operating theatres use air recirculation. The fresh air requirements of this specific application are given in Chapters 8 and 9.
Smoking is generally not permitted in healthcare premises, so no allowance need be made. Reference should be made to local national policy guidance.
In treatment and support areas the overriding requirement may be due to airborne infection control, hazard containment, the stability of specialist equipment or relate to a specific department’s function. Each case should be considered independently in order to determine the overriding minimum requirement for ventilation (see Chapter 8 for specific guidance).
Limiting supply air conditions
For most applications in healthcare buildings, it is the temperature differential between the supply and room air, rather than the actual temperature of the supply air, which is the critical factor. The maximum recommended supply-to-room air temperature differential is:
summer cooling: 7 K
winter heating: 10 K
Room air humidity should be kept below 70% in order to minimise risks associated with condensation and mould growth. There is no lower limit in unoccupied spaces.
Some types of diagnostic imaging technologies require close control of both temperature and humidity as well as the rate of change of conditions to ensure clarity of the image and accuracy of the data generated. The manufacturer’s guidance should be followed.
[SHTM 03-01 Part A – PDF page 29]
Air purity
In healthcare premises, the standard of filtration will depend on the activities within the occupied spaces. Except for special areas (for example, manufacturing pharmacies), the requirement for aerobiological needs is not stringent and filtration is only required to:
maintain hygienic conditions for the health and welfare of occupants, or for processes such as centralised food preparation facilities;
protect finishes, fabrics and furnishings – to reduce redecoration costs;
protect equipment either within the supply air system – to prevent blocking of coils – or in the space itself to prevent dust accumulation
Given that almost all viable particles will originate from the occupants of a space and not from the incoming air, dilution is the more important factor aerobiologically. Therefore, for general areas an ISO ePM 2.5 ≥55% filter may be suitable. More critical areas would require an ISO ePM1 ≥50% filter. Efficiency or high-efficiency (EPA or HEPA) filters will only normally be required in ultra-clean systems, designated “cleanrooms” (see Chapter 9 for specific information) or for some immune-suppressed patient areas
In some inner-city areas the local airborne particulate level may be particularly high. In those special cases filters to ISO ePM1 ≥50% may be required to achieve the required indoor air quality. (See Defra’s website and the Specialised Ventilation for Healthcare Society’s (2018) SVHSoc.02 – ‘Change in air filter test and classification standards’.)
Humidity control requirements
Close control of humidification was originally required for some healthcare applications (for example, operating theatres) in order to control the risk associated with the use of flammable anaesthetic gases. The use of such gases has now ceased.
Providing humidification is expensive in terms of plant, running costs and maintenance, and therefore its use should be restricted to where it is necessary for physiological or operational reasons (see Chapter 8 and associated SHPNs/HBNs).
In general terms the humidity within an occupied building or space will naturally float between 30% and 70% RH (relative humidity). Humidity should not be allowed to rise above 70% at any time but there is no need to maintain a background minimum level when the building or space is unoccupied.
Maximum noise levels
Noise will be generated in an air distribution system by the fan, ductwork fittings, dampers and grilles. The specified maximum noise level will depend on the activities within the occupied spaces.
Attenuation should be incorporated into the ductwork system or plant arrangement as necessary to reduce noise from fans and plant items in order to achieve the acceptable limits within the rooms at the design airflows.
[SHTM 03-01 Part A – PDF page 30]
Plant room noise level from fans when starting up or running should not be greater than 80 dB(A), and should be reduced where the plant is near to departments sensitive to noise.
Attention should be given to the reduction of tonal components. High tonal components from air diffusers etc. can seriously disturb concentration over longer periods even when the overall noise level is low. Broadband noise causes less annoyance.
The values recommended in Table 1 are for the total noise environment of space. In general, there will be noise transmitted into the space and noise generated within the space. The designer requires knowledge of the total hospital layout and operational policies, to assign acceptance magnitudes to all the possible noise sources, in order to arrive at the correct rating.
In Table 1 the overall noise level takes account of all internal and external noise sources. The noise level is the level measured with a sound-level meter in the unoccupied room, taking account of the external noise together with the noise generated by the ventilation system. The ventilation plant design noise level is that generated by the plant alone with no other noise source being considered. The levels suggested make recognised allowance for the ingress of environmental noise which will have to be considered in the overall design, that is, in specifying the attenuation of walls, partitions, ceilings, etc.
Table 1: Interior Noise Level
Area Room: overall noise level –
Ventilation design value –
dB(A)
48
Operating department all rooms including preparation, anaesthetic, scrub and utility, interventional and diagnostic imaging departments – all rooms
dB(A) Operating department all rooms including preparation, anaesthetic, scrub and utility, interventional and diagnostic imaging departments – all rooms
UCV operating theatre and adjacent open- plan scrub only 53 –
Treatment rooms Consulting rooms Sleeping areas/rooms Recovery rooms
35 Treatment rooms Consulting rooms Sleeping areas/rooms Recovery rooms Sanitary facilities 45 40 Aseptic preparation facility 45 40 Industrial areas 50 45 Circulation waiting areas 50 45 Plantrooms 85 80
The recommended criterion is measured as the “A” weighted sound pressure level expressed in decibels, which should not be exceeded for more than 10% of the time. See Scottish Health Technical Memorandum 08-01 – ‘Acoustics’ for further information.
The designer should also consider noise escaping to the external environment and this should not be unacceptable to occupants of adjacent buildings.
[SHTM 03-01 Part A – PDF page 31]
Calculation of building loads
Air infiltration
Air infiltration occurs due to a complex combination of wind pressure, thermal effects, location relative to other features and the construction standard of the building. The infiltration rate is governed by the size and number of doors and other openings in the building envelope and the complexity of internal air paths.
CIBSE guide TM52 provides information and formulae for the calculation of air infiltration in buildings. In all cases the requirements of the appropriate section of the current Building Regulations Part L (airtightness minimum requirements) must be met.
Summertime temperatures
To prevent overheating and avoid the future need for portable room air- conditioners, thermal modelling should be undertaken to ensure that internal temperatures in all areas do not exceed CIBSE Guide A guidance. Thermal modelling should be carried out whether the space is ventilated by natural, mixed mode or mechanical means. The modelling should be undertaken by a competent software user and take into account not only absolute values but also the time component.
Where thermal modelling indicates internal temperatures will exceed the recommended levels defined in CIBSE Guide A, additional measures should be explored to achieve compliance such as reducing solar and casual gains, improving building fabric performance, etc.
Peak heating load
Peak heating local calculations are necessary on all mechanical supply systems to establish the size of heater-batteries and subsequently the central plant. Note that with the introduction of the requirement to fit energy recovery set out in EU 1253, the heater-battery size will be reduced. If the energy-recovery value is ignored, the heater-battery and its control valve will be oversized and the system when put to use will be unstable and liable to hunt.
Where ventilation systems provide tempered air to spaces which have supplementary low pressure hot water (LPHW) to offset the building fabric losses, the AHU heating load should be calculated based on the external winter design temperature, the design internal air temperature, and the calculated total air volume (including a suitable allowance for leakage).
Where the ventilation system is the only means of heating a space, an increase in load equivalent to the calculated fabric heat losses from the space should be added to the ventilation load. A check of supply temperature difference should be made. If it exceeds that recommended in paragraph 4.26 the ventilation supply volume should be increased to suit.
Peak cooling load
In addition to the base data of airflow rates and temperatures, when calculating cooling loads, the designer should take into account:
solar cooling loads;
[SHTM 03-01 Part A – PDF page 32]
surface conduction cooling loads;
internal gain cooling loads;
air infiltration cooling loads;
cooling loads due to high limit humidity control;
method of control of internal conditions;
fluctuations in internal temperatures.
Allowances must be made for all medical equipment in every space. Where the final item has not yet been selected, a unit that is reflective of the needs must be agreed with the stakeholders. A record must be included in the design documentation as to the unit which has been included in the design and the impact on all MEP systems of this unit. The stakeholders must have access to this data to ensure the compatibility of equipment and MEP systems can be checked against final medical equipment selections.
When the peak internal loads have been assessed and a suitable allowance made for non-coincidence, the supply temperature can be calculated.
Once the lowest required supply temperature of the air handling unit has been established, and an allowance made for temperature rise through the fan and ductwork (usually 1 K for low pressure systems), the off-plant enthalpy can be established from a psychrometric chart or table.
The cooling loads for all plant on the chilled water system should be calculated at each of the individual peak times in order to accurately establish the required (diversified) capacity of the chiller.
Note: Note that as with heating, the introduction of the requirement to fit energy recovery set out in EU 1253 means that the cooling-coil size will be reduced. If the energy-recovery value is ignored, the cooling coil and its control valve will be oversized and the system when put to use will be unstable and liable to hunt.
Annual energy consumption
The annual energy consumption of simple heating-only ventilation systems is simple to calculate, based on supply to external air temperature rise, and frequency of occurrence of external temperature data (see CIBSE Guide A).
Minimum air volumes are usually fixed by the room loads or fresh air requirements; however, the designer may increase airflow to some rooms or zones in order to balance loads, as detailed in paragraphs 4.63–4.68
The method of zoning and control can significantly influence energy consumption.
The nature of air-conditioning operation, that is, cooling and reheating for humidity or zonal temperature control, makes prediction of energy consumption very complex. It is imperative that these calculations are performed to ensure optimum energy efficiency.
The concept of load and plant operation charts is outlined in the CIBSE Guide TM52. The method requires the designer to establish the minimum and maximum loads on
[SHTM 03-01 Part A – PDF page 33]
all zones across the range of external temperatures between winter and summer design conditions. The total coil loads can be calculated taking account of the external air temperature and humidity plus the supply air conditions.
When all temperatures/enthalpies for all zones are plotted on the plant operation chart, set points and resetting schedules can be established. From this information, the outputs of individual heaters, coolers and humidifiers can be established at any given external condition. When those loads are computed against annual frequency of occurrence of external conditions as given in CIBSE Guide TM52, the annual energy consumption of individual elements, and thus the air-conditioning system, can be established.
In order to prevent surface condensation occurring, it is necessary to provide enough ventilation to maintain the maximum and ambient dew-point temperature below the lowest surface temperature, the coldest usually being the glazing.
Where this would require excessive ventilation levels, the designer should consider removal of the moisture at the source of the evaporation via an exhaust hood or similar device.
In intermittently heated buildings, it is necessary to consider the condensation risk at night set-back conditions as well as during normal operation. Calculation methods for this assessment are given in CIBSE Guide A.
Calculation of plant requirements
Air supply volumes
The minimum air supply volume for a room is determined by the greatest of:
the minimum fresh air requirement;
the air required to achieve the room differential pressure and provide open door protection at the key door;
the minimum supply volume for the room load as determined by the maximum heating or cooling supply temperature differential;
the desired air-change rate;
the make-up air for a local extract (for example, cooker hood or LEV system).
Plant sizing
Once the design airflow has been established, the cross-sectional area of the air- handling unit can be calculated based on values given in Commission Regulation EU 1253/2014.
The fan duty should be calculated by adding the resistances of all elements that contribute to the pressure drop of the index circuit.
In order to establish the length of the AHU, it will be necessary to refer to manufacturers’ literature, ensuring all necessary access panels and components are included as detailed in Chapter 9.
[SHTM 03-01 Part A – PDF page 34]
The designer should ensure that an allowance has been made for “dirty filter” conditions and confirm whether the fan pressure quoted is the total or static pressure.
Upon completion of the resistance calculation exercise, the designer should make allowances for calculation and construction tolerances as indicated below:
Total pressure loss margin:
for leakage and balancing requirement =+5%
for uncertainties in calculation = +5%
Combined total pressure loss margin =+10%.
Note: All installed ductwork whether new or reused should be subject to a leakage test on site prior to the application of any insulation. The leakage test should be to BESA DW144 but with a permissible leakage rate of not greater than 3%.
Refurbishment of existing facilities and fitting out shell schemes
When refurbishing existing facilities or fitting out “shell” schemes, every effort should be made to achieve full compliance with this SHTM and current Scottish Health Planning Notes (SHPNs). It is important that use of the space is revisited at this stage. Patient cohort, forms of treatment and all other stakeholder requirements must be compared to the capabilities of any existing system/plant and adjustments made to suit.
The physical constraints of the building may mean that some derogation in terms of layout and room dimensions are unavoidable, but it is vital that the infection control aspects, clean airflow paths, cascade of air from clean to less clean areas and fire and smoke requirements are not compromised and that the complete facility will be fit for purpose. The VSG should be consulted and agree in writing to any derogations.
A new AHU fully compliant with current standards will normally be required. The existing AHU should only be retained if it is not more than 10 years old and is (or can be made) fully compliant with current standards.
Note: The application of the ErP regulations may mean that new plant could be physically larger than that previously installed. If the replacement plant cannot be accommodated in the existing plant space, the plantroom may need to be expanded or a new plant space created. It may be that reconsidering how the ventilation load is determined, whether it can be shared, which type of AHU configuration will fulfill the design need, etc., will provide a satisfactory solution rather than just specifying like- for-like replacement plant.
The most commonly used original standard operating theatre design solutions from previous versions of this HTM have been revised and updated (see Appendix 7). They have been retained in this guidance as they will remain applicable to older theatre suites that are being refurbished within their original footprint. They may also be applicable where a pre-built “shell” is being fitted out.
[SHTM 03-01 Part A – PDF page 35]
Change of use of existing facilities
When a change of use of existing facilities is contemplated, the ventilation requirement should be completely revised to suit the new use (see paragraphs 4.63 and 4.69). All requirements must be agreed with the Ventilation Safety Group.
A new AHU fully compliant with current standards will normally be required. The existing AHU should only be retained if it is not more than 10 years old and is (or can be made) fully compliant with current standards.
If the ventilation load is to be increased or reduced and the existing system is retained, its output should be adjusted to suit. This will necessitate a recalculation of the heater and cooler loads and resizing of the control valves to match the new loads. It may also necessitate a change in fan size. Failure to carry out this exercise will carry an energy penalty and loss of control function.
The area/zone fire strategy should be reassessed to suit the new layout and purpose.
Computer-aided design (CAD) and building information modelling (BIM)
The design of new ventilation systems should be created using a CAD package, and the information generated should be incorporated into the BIM for the project. The client should have access to the BIM model as the project progresses; it will be transferred over to the client on completion (see paragraph 13.28 onwards)