10. Installation Standards
General
AHUs, ductwork sections and associated elements of the ventilation system will be delivered to site suitably packaged to protect them from damage and casual contamination. They should remain protected when stored on site awaiting installation.
Ductwork should be installed to the “Advanced Level” as defined in BESA’s (2019) ‘TR/19: Guide to good practice – internal cleanliness of ventilation systems’. Should any doubt exist as to whether the guidance has been observed, the ducts should be cleaned internally to restore them to this standard and be visibly clean before being taken into use.
When the ventilation elements are installed, all open ends have to be sealed to prevent the ingress of construction dust as installation progresses. The access doors and panels of AHUs should be kept closed. All AHU dampers and fire dampers should be covered to prevent casual contamination during the construction phase. This is particularly important for fire dampers mounted in the plantroom floor. The damper blades should be wiped clean before final connection to the distribution ductwork.
The area around the supply air intake should be kept free of vegetation, waste, rubbish, builders’ debris or any other possible source of contamination.
“Builders’ work” ducts of brick or concrete should have a smooth internal finish and be surface sealed to prevent the release of dust before being taken into use. They should be fitted with a drainage system if not self-draining.
Every effort should be made to prevent the internal contamination of the ventilation system during the construction phase as once contaminated, it is extremely difficult to completely remove dust and debris. In particular, extract and recirculation fans should not be run up until the area is at least “builders clean” – that is, the floors swept and wet-mopped – otherwise the energy-recovery device in the AHU could become contaminated and its efficiency significantly reduced.
AHUs
Units should have a working life of up to 20 years; it can be anticipated that over this period there will be a need to access every element within the unit for deep cleaning. It is also quite possible that during the life of the unit, the main fan and all control valves will need replacement. Heater and cooling coils may also need to be repaired or replaced. Suitably positioned service connection joints and adequate spacing should permit these items to be isolated and withdrawn without the need to drain down entire systems or dismantle other installed plant.
Care should be taken during installation to ensure that electrical and mechanical services are not installed in positions that will reduce or impede access. Mounting all control valves and fan controllers on a frame positioned adjacent to the unit is the
[SHTM 03-01 Part A – PDF page 125]
preferred option. This approach has the advantage that the frame and its components can be built and tested “off-site”.
In order to reduce the effects of galvanic corrosion, black iron fittings should not be used in the pipework installation. Rolled jointed stainless-steel pipework is preferred.
Vibration from a remote plantroom can be transmitted by the structure of the building, and may be regenerated and sometimes magnified many times. Pipe and ductwork should incorporate anti-vibration couplings, pipe hangers and supports, preferably in two planes at right angles, as close to the vibration source as possible.
The service connection points for pipework and electrical conduits will have been made during construction of the unit. The unit will then have been leak-tested in the factory prior to delivery to site. If there is a need to drill through the AHU casing or panels (for example, to mount a sensor), the hole should be as small as practicable and sealed to prevent air leakage.
It is essential that the AHU/ductwork is mounted far enough from the floor to permit the correct installation of drainage systems for cooling coils, humidifiers and heat recovery systems. If the AHU is located on a roof, it will require a clearance of 600 mm to provide access to maintain the building structure below. Sufficient height for the installation of drainage pipework and traps should always be allowed. Easy access for maintenance of drainage systems and their associated pipework should be provided. It should be possible to fully withdraw the drainage tray if it is of the removable type.
AHUs should be positioned so that all parts are easily and safely accessible for routine inspection and service. If a unit is located against a wall or backs onto another unit, access to all parts should be available from the front. Units greater than 1 m wide should preferably have access from both sides or access doors large enough to permit the full and safe entry of maintenance personnel.
Air filters, cooling-coil drainage trays and drift eliminators are all items that should be changed, inspected or withdrawn on a regular basis. The installation of the AHU should permit this without the need for tools or to dismantle other plant or systems.
Access to air intakes and discharges, AHUs and items in the distribution system such as filters or auxiliary trimmer batteries located in a plantroom or plant area should be via fixed ladders, hook ladders, pulpit style steps or other moveable access platforms. The installation of distribution ductwork and other electrical or mechanical services should provide sufficient clearance to allow access equipment to be moved into position.
Distribution systems
Where ductwork penetrates a roof, it should be protected by an upstand to prevent water penetration. Where it penetrates an outside wall, the method of installation should prevent water tracking along the ductwork into the building or its wall cavity.
The installation of all services in service ducts and above ceilings should be coordinated so that cable trays, medical gas and other pipework do not obstruct or
[SHTM 03-01 Part A – PDF page 126]
prevent access to the ductwork cleaning doors, dampers and any auxiliary plant elements. The use of BIM should highlight clashes at the design stage.
Plant elements such as VAV boxes, trimmer heaters or cooling coils, humidifier lances or branch filters that are located outside of plant spaces should be accessible for routine inspection and have a cleaning access door on both sides. They cannot be installed above any of the following areas:
operating theatres;
preparation rooms or sterile pack stores;
anaesthetic rooms or recovery areas;
rooms containing imaging equipment;
pharmacy cleanrooms;
containment laboratories;
patient bedrooms and isolation rooms.
Rectangular ductwork sections should be joined by bolted or clipped gasketed flanges. Circular and flat-oval slip-joints should be mastic-sealed and held with blind rivets, not screws. The mastic used should not support biological growth. The ductwork installation will be leak-tested prior to acceptance.
Volume control dampers (VCD) should be oriented so that their adjusting handles or knobs are located at the lower vertical edge or bottom of the damper when mounted above ceilings. The means of adjusting the damper will be within sight and reach from a designated ceiling void access hatch once the ceiling is complete. Volume control dampers mounted in any location should have the control adjuster mounted to allow easy access for the commissioning team and for future access when a post- cleaning rebalance is undertaken.
Access to VCDs or local auxiliary fans mounted above ceilings should be via low- leakage access hatches mounted in the ceiling or hatches integral to a light fitting.
Note: Obtaining access by removing a light fitting is not acceptable.
Where ducts are drilled to provide test holes or to mount sensors, the swarf should be removed, and the hole deburred before the fan is started.
Note: Care should be taken to prevent the inadvertent drilling of attenuators.
Flexible ductwork may only be used if there is no other way of connecting an air terminal to a duct. The flexible duct should be not more than 0.5 m in length, be as fully extended as possible and never used in lieu of a bend. The fire rating of the flexible duct should be no less than that of the fixed duct that it is connected to (see also paragraphs 9.131 and 9.160).
Fire and smoke dampers must be installed strictly in accordance with their manufacturer’s instructions. There will be a rectangular access hatch (saddle mounted for circular ducts) and test switch adjacent to the damper so that a single person can trigger the damper and directly observe its operation during the annual
[SHTM 03-01 Part A – PDF page 127]
test (see photograph). When pressure stabilisers incorporate a fire damper, the test switch is to be located in an easily accessible position on the less clean side of the pressure stabiliser.
Figure 10 Fire damper with test switch and inspection hatch
Point of use
Items of equipment that require access for inspection and cleaning should not be accepted if they are installed in locations that prevent easy access.
Items of equipment that require access for inspection and cleaning such as fan coil units will not be accepted if they are installed directly above medical or diagnostic equipment.
Note: A common problem occurs because installation layout drawings show fan coil or similar units on the room plan. These are often only “indicative” of the fact that there will be a unit in the room but are taken as the desired position by those carrying out the installation. As an example, the installation drawing for an interventional imaging room shows a fan coil unit in the centre of the ceiling. If it is installed in this position it will be directly above the scanner once that is installed. The fan coil unit will then not be accessible for routine inspection and maintenance, and should it leak water, it will put the scanner out of action.
[SHTM 03-01 Part A – PDF page 128]
The installed position of ceiling terminals in storerooms (for example, a theatre’s bulk sterile pack store) should coordinate with the siting of the storage racking. The airflow at the terminals should be routinely measured, so the racking and its contents should not obstruct access to the terminal when using a calibrated hood. The same problem can occur in recovery rooms and ward areas where bed curtain rails and bed hoist tracks can prevent the measurement of airflow from ceiling terminals.
Low-level extract grilles should be of the pull off face type for ease of cleaning.
See pictures of low level extract installations in Appendix 9.
Service penetrations
Where services penetrate the fabric of the building, they should be sealed to prevent any uncontrolled air leakage between rooms and service spaces or voids. Situations where this occurs will be:
service spaces behind IPS panels at wash basins and scrub troughs;
cased in wall-mounted medical gas pipeline units and ceiling-mounted pendants;
electrical trunking and bedhead rail systems;
boxed-in main and local drainage pipework;
ceiling-mounted operating lights, examination lights and other pendant- supported items.
The sealing should be at the point that the service penetrates the wall, ceiling or floor and not at the access panels or covering shrouds as these will need to be removed from time to time. Sealing of the penetrations should be done at first-fix stage as access will become progressively more difficult once final covers and finishes are applied. In certain applications, permeability testing will be carried out at first-fix stage to ensure that this has been done.
Note: The “clean zone” is not the same as the overall size of the canopy, and it is vital to consult the UCV canopy supplier in order to get the position and size of the zone correct, as mistakes are expensive to rectify.