SHTM 03-01 Part A: 11. Commissioning Systems
[SHTM 03-01 Part A – PDF page 129]
11. Commissioning Systems
General
Commissioning is the process of advancing a system from physical completion to an operating condition. It will normally be carried out by specialist commissioning contractors working in conjunction with equipment installers. Commissioning of the ventilation system will normally be the responsibility of the main or mechanical contractor who should coordinate the process.
Commissioning is often subdivided into sections (for example, air handling unit, automatic controls, air side balance, building fabric and fittings). Each section may be commissioned by its specialist installer, and they are often accepted in isolation.
Commissioning is an essential process for ventilation systems. It is therefore important that adequate provision for the process be made at the design stage of the project. Procedures for commissioning air-handling systems are given in CIBSE Commissioning Codes and BSRIA BG 49 – Commissioning Air Systems.
The duct design process should take into account the requirements of system balancing. The position and number of regulating dampers included in the design should be sufficient for this purpose.
Location of dampers and test holes
Balancing/commissioning dampers will be required in each branch of the distribution ductwork. In a critical system such as an operating suite, the branch to each room and each location where it is required to carry out a proportional balance should have a balancing damper.
Test holes for the measurement of airflow will be required at carefully selected points in main and all branch ducts. The number and spacing of holes are given in the BSRIA BG 49/2015 Commissioning Air Systems. Their positions should be identified at the design stage.
The test positions need to be accessible for commissioning to take place. They may also be required for subsequent annual verification of the system performance, so they should not be covered by permanent lagging.
The measurement point should be in a straight length of duct as far away as possible from any upstream bends, dampers or other elements that could cause disturbance to the airflow. The actual location should be:
at least 1.5 duct diameters upstream of sources of turbulence such as dampers and bends;
if this is not possible, ten diameters downstream of dampers, bends or tees, and five diameters downstream of eccentric reducers;
where there is enough space round the duct to insert the pitot tube and take readings;
where the duct has a constant cross- sectional area.
[SHTM 03-01 Part A – PDF page 130]
Test holes for measuring total airflow from a fan should be located either four diameters upstream or ten diameters downstream of the fan. Provision should also be made for measuring the fan’s speed of rotation.
Note: Plug and EC fans are supplied with a measuring ring so their output can be read directly. This needs to be connected to an external pressure tapping or electronic fan control unit.
Information to be provided
It is essential that the designer should pass on the system-design intent fully to the commissioning engineer by providing:
relevant parts of the specification;
schematic drawings indicating data listed in Table 11;
equipment schedules;
controller and regulator schedule;
fan performance curves;
wiring diagrams for electrical equipment, including interlock details
Table 11: Information to be provided on schematic drawings
Items in system Information to be provided
Fans Fan total pressure Volume flow rate at normal and set back speed Maximum motor current
Plant items Type and identification numbers from equipment schedules Fluid and air volume flow rates Fluid and air side pressure losses Dry bulb temperatures Wet bulb temperatures Humidity
Dampers, including motorised and fire dampers
Identification numbers from equipment schedules Location Identification number Volume flow rate
Main and branch ducts Dimensions Volume flow rates and velocities Identification numbers from equipment schedules
Test holes and access panels Location and size of duct Identification number Design airflow rate
Room supply and extract terminals Location Identification number Grille or diffuser factor Volume flow rate and neck velocity Operating static pressure
Pressure cascade Room differential pressures Airflow direction between rooms Pressure stabiliser and transfer grille locations
Internal environment conditions Design room conditions and adjustable range Specific room air velocity if specified Noise level
Controllers Set points
[SHTM 03-01 Part A – PDF page 131]
Notes: Fan total pressure is the difference between the total pressure (static pressure + velocity pressure) at the fan outlet and the total pressure at the fan inlet. Where volume flow rates are variable, maximum and minimum values should be provided.
Commissioning personnel
It is unlikely that all the required commissioning skills will be possessed by one individual; a commissioning team is therefore usually needed. The objective of commissioning is to ensure that the necessary performance and safety requirements are met.
During the commissioning process a great deal of information will be generated which will form an invaluable future source of reference about the plant. It is essential to ensure that it is collected together in the form of a commissioning manual and handed over to the client on completion of the contract together with the “as fitted” drawings.
In order to be successful the commissioning process will need to start before practical completion, as many parts of the system will become progressively less accessible. The correct installation of those parts should be witnessed and leak rate tests carried out as construction proceeds. Failure to establish responsibility for commissioning early enough will delay the completion of the project or lead to unsatisfactory plant performance (see CIBSE Commissioning Code M).
Commissioning brief
The commissioning team will require a detailed brief from the system designer. This should include:
a “user” brief comprising a description of the installation and its intended mode of operation;
the precise design requirements with regard to the scheme of air movement, room static pressures, supply and extract airflow rates and acceptable tolerances;
full details of the design conditions both inside and out, for winter and summer, together with the control strategy;
equipment manufacturers’ type test data, commissioning, operation and maintenance recommendations;
drawings showing the layout of the system, positions of airflow measurement test points, dampers, regulating devices and filters within the duct runs, together with sizes of ducts and terminal fittings. It will save time if these drawings are annotated with the design volumes and static pressures required at each branch and outlet point;
wiring diagrams for all electrical equipment associated with the air- handling systems, including motor control circuit details and any interlocking and safety devices.
CIBSE Commissioning Code A – ‘Air distribution’ or BSRIA BG 49 – ‘Commissioning air systems’ provide full guidance on the information that will be required by the commissioning team.
[SHTM 03-01 Part A – PDF page 132]
Designers should specify the type of measuring instruments and test procedures. They should include in the contract documents instructions on verifying the accuracy of test instruments, which should be supported by reference to relevant calibration certificates.
The system, on completion, should be operated by the contractor as a whole and subject to performance tests in accordance with the contract requirements. These will include independent validation of the system performance on behalf of the client.
The commissioning process should be carried out in the order in which it appears in this guidance document. That is to say, the static checks and visual inspections itemised in paragraphs 11.20–11.26 should be followed by the dynamic tests described in paragraphs 11.27–11.46, the performance tests listed in paragraphs 11.47–11.64 and finally the handover procedures set out in paragraphs 11.63–11.65.
Once the system is shown to meet the design intent, the handover documentation should be completed. In the event of performance not being acceptable, the matter should be dealt with in accordance with the contract arrangements.
Pre-commissioning checks
The pre-commissioning checks consist of visual inspection, manual operation of equipment, static measurements and functional tests of individual components. They should be carried out prior to setting the system to work and undertaking the dynamic commissioning process set out in paragraph 11.27 onwards.
Note: Before commencing commissioning, it is essential that builders’ work in the area served by the system is complete. The doors and windows should be fitted, floor finishes applied, walls and ceilings completed and their final finish applied. Fans should not be run until the area is clean (see paragraph 10.6).
Standard of installation
During the installation of the system the following will be witnessed:
that the plant and installations have been provided and installed in accordance with the design specification and drawings;
that only approved sealants have been used in the installation;
that all components function correctly;
that the satisfactory sealing of access doors and viewing ports has been carried out;
that the AHU airtightness test as per BS EN 1886 has been carried out;
that air-pressure tests and air-leakage tests on ventilation ducting have been carried out in accordance with the methods set out in the BESA DW143 – ‘Ductwork leakage testing’ but the leakage rate to be not greater than 3% (it is usual to carry out these tests a section at a time as the ductwork is installed and before its insulation is applied. The results will be recorded in the commissioning manual);
that gaps around doors and hatches are as specified in the design;
[SHTM 03-01 Part A – PDF page 133]
that the permeability tests are carried out as per paragraph 12.17;
that the correct operation of pressure stabilisers, control dampers, isolating and non-return dampers have been checked;
that test holes have been provided in their specified locations and are sealed with suitable grommets;
that control dampers are secured and their quadrants fitted correctly;
that any interlocks are operative and in accordance with specification;
that the electric circuits are completed, tested and energised;
that electric motors have been checked for correct direction of rotation both at full speed and set back;
that cooling and heating media are available at correct temperatures and pressures and in specified quantities
that the air-conditioning plant components and controls function correctly;
that the air-conditioning plant interlocks and safety controls function correctly;
that the plant is physically complete, insulation is applied and all ducts and pipework are identified as specified;
that all service penetrations of the fabric of the area are sealed at the point of penetration (see also paragraph 10.30);
that the building housing the ventilation plant is generally in a fit condition for commissioning and performance tests to commence, that is, windows, doors, partitions, ceilings, etc. are completed, surfaces sealed and their final finish applied;
that the areas containing the ventilation plant and those being served by it are clean;
that access to all parts of the system is safe and satisfactory.
Certification of equipment
The following test certificates should be assembled by the commissioning team and be available for inspection at any time during the contract period. They will form part of the handover information and should be placed in the commissioning manual:
type test performance certificates for fans;
pressure test certificates for:
- heater-batteries;
- cooling coils;
- humidifier (if appropriate);
type-test certificates for attenuators;
type-test certificates for primary and secondary filters;
individual test certificates for EPA or HEPA air filters.
[SHTM 03-01 Part A – PDF page 134]
Equipment tests
Prior to setting the system to work the following will be witnessed and proving tests should be carried out as detailed:
Filters
The quality of filter housing and in particular, the seals, is a critical factor in maintaining the efficacy of the filtration system by ensuring that air does not bypass the filter elements. Therefore, the following checks should be made:
filter seals should be fitted and in good condition;
filters should be installed correctly with respect to airflow;
bag filters should be installed so that the bags are vertical and their pockets free;
all filters should be checked to ensure they are free of visible damage;
EPA or HEPA filters should be scanned with an LSAPC to prove that they and their housings achieve the specified filter efficiency;
the differential pressure indicators should be checked for accuracy and that they are marked with the initial and final filter resistance.
Drainage arrangements
The drain should conform in all respects to the standard set out in paragraph 9.105 onwards. In addition, the following should be proved:
that the drain tray is easily removable or completely accessible;
that the drift eliminator (if fitted) is removable without the use of tools;
that a borosilicate glass trap is fitted and is easily removable;
that the trap discharge point to drain has a clear air-gap of at least 15 mm;
that the pipework is supported so that the air-break cannot be reduced;
that the drain system from each drain tray is independent up to the air- break.
The operation of the drainage system is then proved by introducing water into the duct at the drain tray and observing that it completely drains out. This check is to be repeated both at normal speed and set back once the fans have been commissioned. At this time the clear trap can be marked to indicate the normal water level with the fan running.
Fire dampers
The following will be witnessed and proving tests should be carried out as detailed:
the operation of all fire and smoke dampers (fire dampers fitted with a thermally actuated “memory metal” mechanism should be proved using a hot air heat source);
the access provided to enable the dampers to be visually inspected and/ or reset should be sufficient for the purpose;
indication should be provided of the dampers’ position (open/tripped);
[SHTM 03-01 Part A – PDF page 135]
indication of the fire dampers’ location should be provided both on the ductwork and at a visible point on the building fabric if the ductwork is concealed.
Dynamic commissioning
Air-handling and distribution system
Before commencing the dynamic commissioning all rubbish should have been removed and the floors swept and wet- mopped (see paragraph 10.6). Any IPS panels should be in position, access hatches closed, light fittings in place and ceiling tiles clipped down as necessary.
The fan drive, direction of rotation, speed and current drawn should be set in accordance with their manufacturer’s instructions. In the vast majority of healthcare applications, the fan output should be set to give a constant volume of air. This to be controlled by measuring the pressure drop across the fan using a sensing ring and associated volume controller that will automatically integrate the fan ‘K’ factor to determine and control the pre-set output air volume. The fan output will then in air volume terms remain constant regardless of changes of system resistance. The actual volume delivered will be related to the air-change rate for the application.
After the installation has been checked to ensure that it is in a satisfactory and safe condition for start-up, it should be set to work and regulated to enable the plant to meet its design specification. The proportional balancing method described in the CIBSE Commissioning Code A should be followed. The airflow rates will be set within the tolerances laid down in the design brief. This will normally be the design airflow rate +10%; –0%.
Note: Plug fans are fitted with a measuring ring so that the design volume flow can be set when first started. It can then be reset as the airflow balance progresses. This method will result in the correct airflow with the least total system resistance once balancing is completed.
Air commissioning measuring equipment standards
All test and measuring equipment used will have a certificate to prove that its calibration has been checked within the previous 12 months at a facility using traceable national standards.
System performance should be measured at the main and branch duct supply and extract test points using a pitot and manometer or a thermal anemometer.
Supply and extract air volumes at the room terminals should be measured using a calibrated hood with back pressure compensation. If a hood correction factor is applied, it should be determined by a direct comparison with a duct measurement immediately adjacent to a terminal and not a general comparison between air at the main supply duct and the total as measured at the terminals. For multi-directional terminals a correction cross will be fitted in the measuring hood.
Note: Measurements taken with a “home- made” hood or cone will not be accepted.
[SHTM 03-01 Part A – PDF page 136]
Measurements at extract grille faces should, where possible, be taken using a calibrated hood. Alternatively, they may be measured with a rotating vane anemometer fitted with a hood, or as a last resort, scanned using a rotating vane anemometer and a free area factor applied. The grille face free area and factor used should be stated in the commissioning report.
Order of commissioning
When combined supply and extract systems are to be balanced and the area that they serve is to be at or above atmospheric pressure, the supply should be balanced first with the extract fan switched off, and then the extract balanced with the supply fan(s) on. The supply balance should then be rechecked.
For combined systems where the area that they serve is to be below atmospheric pressure, the extract should be balanced first with the supply fan switched off and then the supply balanced with the extract fan on. The extract should then be rechecked.
On completion of the balance, all volume airflows in supply and extract ducts and from grilles and diffusers will be measured and recorded. The true air- change rate can then be calculated from the data obtained.
Note: For accuracy the room dimensions should be actually measured on site rather than deriving them from design drawings.
All supply and extract duct volume control dampers should be locked and their position marked and the fan motor settings noted and recorded.
All grille and diffuser volume control registers should be locked to prevent alteration and their final position marked.
Room air distribution
The pressure relief dampers and pressure stabilisers will be set to achieve the specified room differential pressures and locked. The grille direction control vanes and diffuser cones will be set to give the specified air movement pattern. Visualisation techniques may need to be employed to prove the required airflow pattern is being achieved and detect any adverse coanda effects (see paragraph 9.162).
Note: When balancing combined supply/ extract cascade ventilation systems (for example, operating suites, cleanroom suites), the airflow through the extract terminals in the adjacent corridors may need to be adjusted outside of their original design values in order to achieve the desired room pressure differentials.
Air-conditioning plant
The specified flow rate and/or pressure drops will be set for all heater- batteries, cooling coils and humidifiers. The methods described in the CIBSE Commissioning Codes W and R should be followed. On completion their regulating devices will be locked to prevent alteration.
Control system
[SHTM 03-01 Part A – PDF page 137]
The control system should not be commissioned until both the air distribution system and air-conditioning equipment have been commissioned.
Because of the specialised nature of control systems and the fact that each manufacturer’s system will contain its own algorithms and settings, commissioning should be completed by the supplier, and witnessed and documented by a representative of the client (for example, the healthcare organisation’s appointed validator).
In the vast majority of healthcare applications, the fan output should be set to give a constant volume of air. This to be controlled by measuring the pressure drop across the fan using a sensing ring and associated volume controller that will automatically integrate the fan factor to determine and control the pre-set output air volume. The fan output will then in air volume terms remain constant regardless of changes of system resistance. The actual volume delivered will be related to the air-change rate for the application.
Note: Measuring the air pressure in the main supply duct and using that to set the supply fan speed as a percentage of its rated output and using that to set the extract fan speed as a percentage of the supply fan speed is not a satisfactory, accurate or acceptable way of controlling the desired supply and extract air volumes.
The location of all control and monitoring sensors should be checked and their accuracy proved.
The control system’s ability to carry out its specified functions will need to be proved. The correct operation of any alarm systems should also be proved.
If the plant is provided with a “users” control panel in addition to the one located in the plantroom, the operation of both should be proved. This will typically apply to operating departments and laboratory systems.
Specific performance standards
The performance of the system should be measured and compared with information provided by the designer.
Plant capacity and control
When setting to work and proving the design, both the manufacturer of the air handling plant and the control specialist should attend site together and jointly commission the system.
If any doubt exists as to the capacity of the installed system, its ability to achieve the specified inside design conditions with the plant operating at winter and summer outside design conditions should be proved. Artificial loads will be required in order to simulate the internal gains/losses and the outside design conditions.
On completion of the plant performance test, recording thermo- hygrographs should be placed in each room/ area served by the plant and also the supply air duct upstream of the fog coil. The plant should be run for 24 hours with all doors closed.
[SHTM 03-01 Part A – PDF page 138]
During this period the inside conditions should stay within the tolerances specified. Alternatively, the BMS may be used to obtain the information required.
Noise levels (general)
The commissioning noise level is that measured with a sound level meter in the unoccupied room, taking account of the external noise together with the noise generated by the ventilation system. Chapter 8 and Table 1 in Chapter 4 give information for many applications.
The noise levels apply at the maximum velocity for which the system is designed to operate. Acoustic commissioning tests should be carried out with all plant and machinery running normally and achieving the design conditions of airflow, temperature and humidity.
An industrial-grade Type 2 sound level meter will normally be sufficient to check the noise level. Its accuracy should be checked using a calibrated sound source before use.
The noise level readings are to be taken at typical normal listening position 1.5 m above floor level and at least 1 m from any surface and not on any line of symmetry. In critical rooms the noise should be measured at the centre of the room and at the centre of each quarter. The mean of the five readings should then be calculated
In the event of a contractual deficiency a Type 1 precision-grade sound level meter should be used and the noise level determined by the procedure given in Scottish Health Technical Memorandum 08-01.
Filter challenge
General ventilation filters
In-situ performance tests will not normally be required for primary and secondary filters and their housings. However, the filters should be visually inspected for grade, tears, orientation and fit within their housing. Filters should be clean and a replacement set available. Bag filters should be installed so that their bags are vertical and spaced so that air can move through them freely.
Air leakage around a filter housing significantly reduces the filter efficiency. The as- fitted filter housing and access door arrangement should not permit air to bypass.
EPA or HEPA filters (for exhaust protective enclosures and laboratories)
Pathogenic material may be discharged through damaged or badly installed EPA or HEPA terminal filters. The complete installation should be tested using the method set out in BS EN ISO 14644 and ISO 17141.
The challenge tests may be carried out using either of the following techniques:
a light scanning airborne particle counter (LSAPC) and a natural challenge to detect leaks;
dispersed oil particle (DOP) to provide the challenge and a photometer to detect leaks.
[SHTM 03-01 Part A – PDF page 139]
In both cases the upstream challenge should be measured. A measurement of particle penetration through a representative section of the EPA filter media is then taken and used as the reference background level. These two readings enable the range of the detecting instrument to be set.
With an LSAPC the filter face is sampled at several points to establish the smallest non-penetrating particle size. This will directly relate to the grade of filter under test. The filter face, its seal and housing are then scanned, and if a significant number of particles at or above this size are detected, there is deemed to be a leak at or near the test position.
With DOP a challenge aerosol of inert particles of the type produced by a dispersed oil particle generator is introduced into the air, upstream of the EPA or HEPA filter. The downstream face of the filter, its mounting seal and housing are then scanned for leakage using a photometer. A leak should be deemed to have occurred if a steady and repeatable reading on the photometer at any point exceeds 0.01% of the upstream reading.
Should the EPA or HEPA filter fail this test, it will be replaced. Should the filter mounting seal or housing fail this test, it may be repaired and the test repeated.
Ventilation system commissioning records
Following commissioning, the main contractor will collate the individual commissioning reports together with the plant user manuals ready for handover.
The fire dampers will have been tested by a specialist, and a written statement detailing which fire dampers were tested, when and by whom should be provided. If any fire dampers in the system were not tested, they should be listed and appended to the statement.
The airflow balancing report compiled by the commissioning engineers should be available to the validator. The report should include copies of the equipment calibration certificates.