Home › Scotland (NHS Scotland Assure / HFS) › SHTM 03-01 Part A › 12. Acceptance Testing: Validation – Appointment of validator / 12. Acceptance Testing: Validation – First fix inspection

SHTM 03-01 Part A: 12. Acceptance Testing: Validation – Appointment of validator / 12. Acceptance Testing: Validation – First fix inspection

Ventilation for Healthcare - Design and validation (SHTM 03-01 Part A) · PDF pages 140–141 of 227 · Source file: shtm-03-01-part-a-v30-feb-2022.pdf
Unofficial text extract. Tables and figures may be incomplete. Authoritative version: official PDF from NHS National Services Scotland.

[SHTM 03-01 Part A – PDF page 140]

12. Acceptance Testing: Validation

All new and refurbished ventilation systems should be independently validated prior to acceptance by the client.

Validation differs from commissioning in that its purpose is to look at the complete installation from air intake to extract discharge and assess its “fitness for purpose as a whole”. This involves examining the fabric of the building being served by the system and inspecting the ventilation equipment fitted as well as measuring the actual ventilation performance. Validation is not a snagging exercise; see the Note after paragraph 12.30.

Validation is a process of proving that the system in its entirety is fit for purpose and achieves the operating performance originally specified. It will normally be a condition of contract that “The system will be acceptable to the client if at the time of validation, it is considered fit for purpose and will only require routine maintenance in order to remain so for its projected life.”

Appointment of validator

In order to ensure that the complete system operates correctly it will be necessary to validate it as a whole from the air intake through to the extract discharge. It is unlikely that the client’s in-house staff will possess the knowledge or equipment necessary to undertake this process. Validation should therefore be carried out by a suitably qualified competent engineer appointed by the client. The validator would be the client’s AE(V) (see Chapter 2 in Part B of Scottish Health Technical Memorandum 03-01) or someone of similar standing who is familiar with the ventilation requirements for healthcare facilities. They will be completely independent of the system designers, contractors, suppliers, installers, commissioners and those who will subsequently operate and maintain the system.

To retain independence, the validator should be appointed and paid directly by the client. The validator will act as the client’s representative to inspect the system, check its performance and recommend acceptance, or not, to the client.

Note: “Client” means the healthcare provider, not a contractor or service provider.

Design proposal review

It is essential that whoever has been appointed to carry out the final validation acceptance of the system should be involved in the initial client’s brief and design specification, preferably prior to the project being put out to tender. They will then be fully aware of the client’s requirements and any limiting factors.

Note: While it is beneficial to involve the client’s validator in the design process, it should be remembered that the appointed designer carries the “design risk” and advice from the validator will not obviate this.

It is important that the validator understands the complete project and not just the obvious ventilation aspects. Decisions about the type of ceilings, doors, access

[SHTM 03-01 Part A – PDF page 141]

hatches, fire compartmentation, floor markings, room functions, their adjacency and the proposed workflow patterns all have a direct effect on the likelihood of being able to achieve the desired ventilation performance. It is not sufficient to consider the ventilation in isolation.

During this process any derogations proposed by the contractor/supplier should be clearly defined, agreed and documented with the client (for example, through the VSG). All parties will then be clear as to what will be the acceptable standard of installation and performance when finally validated.

The ventilation designer(s) should provide the validator with system information listed in Table 11. The information should be in the form of an annotated drawing for each ventilation system to be validated. They should also provide any other design or specification information that will assist the validation process.

The contract arrangement should give the validator the right to visit the site as often as they deem necessary during the contract period.

First fix inspection

The validator should carry out a physical walk-around inspection of the installation at a point in the project when the AHU is “on site” and the main and branch ductwork is for the main part installed, but prior to the ductwork being concealed behind wall panelling or ceilings.

If possible, the following airtightness tests should be witnessed during the inspection:

AHU installation leakage (BS EN 1886);

supply and extract duct leakage (BESA DW/143);

initial permeability test (see paragraph 12.17).

The quality of the installation, compliance of the AHU, suitability of the basic installation, location and future accessibility of commissioning dampers, location and compliance for testing of fire dampers, etc., can all be assessed during the visit.

When validating large projects that have many AHUs, it is worthwhile to visit the AHU manufacturer to inspect a specimen unit and agree its compliance before all remaining units are built and transported to site. At that time the leakage and deflection tests can be demonstrated by the AHU supplier in their factory.

Once units are delivered to site, it is useful to get all mechanical and electrical services connected to a specimen AHU. The location of pipework joints, drain points, anti-vibration couplings, isolating and control valves can all be agreed, as can the route of cable ways and control wiring. The object will be to create an agreed “exemplar unit”. If all other AHUs are installed in an identical fashion, they will normally be considered compliant at the time of final validation.

On completion of the first fix visit the validator should provide the client with a short report identifying items that are not compliant with the specification.