Standard layout 5 – (ex HTM 2025 Plan 1b): single-corridor conventional operating suite with “lay-up” prep
Note
This layout and data is for historical purposes only. The information is to be used for the evaluation of existing systems, the fitting out of existing shell schemes or rebalancing of such systems following cleaning.
Room Size Air-change rate (ac/h) Nominal pressure (Pa) Flow rate (m3/s)
Theatre
≥22 # See Notes below
Anaesthetic
Design 15
Commissioned ≥10
~ Supply and extract to achieve the air change rate
Lay-up prep ≥22 0.35*
Existing theatre suite rooms to be measured on site
Scrub – –
Utility >20 –5 0.40
Notes:
# Total airflow related to volume of theatre to give ≥22 ac/h or door protection value = primary theatre supply + 0.28 m3/s from
the Lay-up Prep pressure stabiliser
* See the “designers’ notes” in Appendices 4 and 5.
The utility layout design figures will remain the same if a hatch is fitted instead of a door onto the service corridor.
The extracts within the theatre and scrub may be either passive and fitted with pressure stabilisers or active and connected to the extract system. They should where possible be located at low level and positioned to promote the active ventilation and scouring of all areas of the space (see paragraph 8.92). Air transfer from theatre to anaesthetic room may be by pressure stabiliser or transfer grilles (see paragraphs A8.51 and A8.52 in Appendix 8). The anaesthetic room extract will be at low level (see Appendix 9).
Corridor
KEY TO SYMBOLS
–5
Supply volume (m3/s)
~ >20
Anaesthetic
Exit bay Utility
Extract volume (m3/s)
~
0.40
Nominal room pressure (Pa)
0.35
Air change rate (ac/h)
Prep (lay up)
Pressure stabiliser
≥22
Operating theatre
LLE
≥22
Optional low-level active extract or pressure stabiliser. May be added during refurbishment to assist air distribution in theatre
Transfer grille
Scrub
LLE
[HTM 03-01 A – PDF page 175]
Appendix 7: Operating suite design logic
Standard layout 6 – (ex HTM 2025 Plan 1a): single-corridor UCV operating suite with SPS prep
Note
This layout and data is for historical purposes only. The information is to be used for the evaluation of existing systems, the fitting out of existing shell schemes or rebalancing of such systems following cleaning.
If difficulties are experienced with entrainment around the periphery of the UCV, adding a low-level active or passive extract in the location indicated will usually resolve the problem.
Room Size Air-change rate (ac/h) Nominal pressure (Pa) Flow rate (m3/s)
Theatre
≥22 # See Notes below
Anaesthetic
Design 15
Commissioned ≥10
~ Supply and extract to achieve the air change rate
Existing theatre suite to be measured on site
Sterile pack store prep 0.1
Scrub – –
Utility – –5 0.4
Notes:
# Theatre total airflow related to volume of theatre to give ≥22 ac/h or door protection value
The utility layout design figures will remain the same if a hatch is fitted instead of a door onto the service corridor.
The extracts within the theatre and scrub may be either passive and fitted with pressure stabilisers or active and connected to the extract system. They should where possible be located at low level and positioned to promote the active ventilation and scouring of all areas of the space (see paragraph 8.92). Air transfer from theatre to anaesthetic room may be by pressure stabiliser or transfer grilles (see paragraphs A8.51 and A8.52 in Appendix 8). The anaesthetic room extract will be at low level (see Appendix 9).
Corridor
KEY TO SYMBOLS
–5
Supply volume (m3/s)
~ >20
Anaesthetic
Exit bay Utility
Extract volume (m3/s)
~
0.40
Nominal room pressure (Pa)
UCV operating theatre
0.10
Air change rate (ac/h)
Prep (SPS)
Pressure stabiliser
UCV primary airflow rate (m/s)
LLE
Optional low-level active extract or pressure stabiliser. May be added during refurbishment to assist air distribution in theatre and overcome entrainment problems with the UCV terminal
≥22
Scrub
Transfer grille
LLE
[HTM 03-01 A – PDF page 176]
Standard layout 7 – (ex HTM 2025 Plan 5b): two-corridor conventional operating suite with “lay-up” prep
Note
This layout and data is for historical purposes only. The information is to be used for the evaluation of existing systems, the fitting out of existing shell schemes or rebalancing of such systems following cleaning.
Room Size Air-change rate (ac/h) Nominal pressure (Pa) Flow rate (m3/s)
Theatre
≥22 # See Notes below
Anaesthetic
Design 15
Commissioned ≥10
~ Supply and extract to achieve the air change rate
Existing theatre suite to be measured on site
Lay-up prep ≥22 0.35*
Scrub – –
Utility – 0.1
Notes:
# Theatre total airflow related to volume of theatre to give ≥22 ac/h or door protection = primary theatre supply + 0.28 m3/s from
Lay-up Prep pressure stabiliser
* See the “designers’ notes” in Appendices 4 and 5
The utility design figures will remain the same if a hatch is fitted instead of a door onto the service corridor. Alternatively if the operating department has a central waste processing station, the utility room may be omitted and replaced with a hatch between the theatre and service corridor.
The extracts within the theatre and scrub may be either passive and fitted with pressure stabilisers or active and connected to the extract system. They should where possible be located at low level and positioned to promote the active ventilation and scouring of all areas of the space (see paragraph 8.92). Air transfer from theatre to anaesthetic room may be by pressure stabiliser or transfer grilles (see paragraphs A8.51 and A8.52 in Appendix 8). The anaesthetic room extract will be at low level (see Appendix 9).
Corridor
KEY TO SYMBOLS
Supply volume (m3/s)
~
Scrub Exit bay Anaesthetic
Extract volume (m3/s)
~
Nominal room pressure (Pa)
Air change rate (ac/h)
0.35
Pressure stabiliser
Prep (lay up)
Operating theatre
LLE
≥22 ≥22
Optional low-level active extract or pressure stabiliser. May be added during refurbishment to assist air distribution in theatre
Utility
Transfer grille
0.10
LLE
Service corridor
[HTM 03-01 A – PDF page 177]
Appendix 7: Operating suite design logic
Standard layout 8 – (ex HTM 2025 Plan 5a): two-corridor UCV operating suite with SPS prep
Note
This layout and data is for historical purposes only. The information is to be used for the evaluation of existing systems, the fitting out of existing shell schemes or rebalancing of such systems following cleaning.
If difficulties are experienced with entrainment around the periphery of the UCV, adding a low-level active or passive extract in the location indicated will usually resolve the problem.
Room Size Air-change rate (ac/h) Nominal pressure (Pa) Flow rate (m3/s)
Theatre
≥22 # See Notes below
Anaesthetic
Design 15
Commissioned ≥10
~ Supply and extract to achieve the air change rate
Existing theatre suite to be measured on site
Sterile pack store prep 0.1
Scrub – –
Utility – 0.1
Notes:
# Primary fresh supply air for the UCV canopy is related to volume of theatre to give ≥22 ac/h or door protection
The utility design figures will remain the same if a hatch is fitted instead of a door onto the service corridor. Alternatively if the operating department has a central waste processing station, the utility room may be omitted and replaced with a hatch between the theatre and service corridor.
The extracts within the theatre and scrub may be either passive and fitted with pressure stabilisers or active and connected to the extract system. They should where possible be located at low level and positioned to promote the active ventilation and scouring of all areas of the space (see paragraph 8.92). Air transfer from theatre to anaesthetic room may be by pressure stabiliser or transfer grilles (see paragraphs A8.51 and A8.52 in Appendix 8). The anaesthetic room extract will be at low level (see Appendix 9).
Corridor
KEY TO SYMBOLS
Supply volume (m3/s)
~
Scrub Exit bay Anaesthetic
Extract volume (m3/s)
~
Nominal room pressure (Pa)
UCV operating theatre
Air change rate (ac/h)
0.10
Pressure stabiliser
Prep (SPS)
UCV primary air flow rate (m/s)
LLE
Utility
Optional low-level active extract or pressure stabiliser. May be added during refurbishment to assist air distribution in theatre and overcome entrainment problems with the UCV terminal
0.10
≥22
Transfer grille
LLE
Service corridor