HTM 03-01 A: _Hlk37000395 – UCV terminal control system checks / _Hlk37000395 – UCV theatre microbiological tests

Specialised ventilation for healthcare premises Part A: The concept, design, specification, installation and acceptance testing of healthcare ventilation systems · PDF pages 150–152 of 213 · Source file: HTM0301-PartA-accessible-F6.pdf
Unofficial text extract. Tables and figures may be incomplete. Authoritative version: official PDF from NHS England.

[HTM 03-01 A – PDF page 150]

symmetry. Measurements should be taken under the centre of each quadrant and in the centre of the canopy, and the five readings averaged.

For this test the challenge source distribution head will be placed at the test position that yielded the greatest penetration at the periphery of the canopy footprint.

Analysis and interpretation

12.115 The readings should be taken with the UCV canopy at operational speed and repeated with it at set back.

12.110 The following standard is to be achieved:

12.116 For UCV operating suites, the noise level should not exceed:

a. Penetration to be no greater than

10% of the challenge at each test position in the outer zone.

• operating theatre and spaces without doors that are open to it (for example, the scrub): 53 dB(A);

b. Penetration to be no greater than

• all other peripheral rooms of the suite: 48 dB(A).

1% of the challenge at each test position in the inner zone.

c. Penetration to be no greater than

0.1% of the challenge at the centre of the test grid.

UCV terminal control system checks

Temperature

12.111 If a result is close to or above the given limits, a further reading should be obtained using a longer time base (1 minute) and the penetration should not exceed the given limit.

12.117 The readings of temperature taken under the UCV canopy should be within ±1ºC of the readout on the theatre control panel.

UCV canopy flow visualisation

Humidity

12.118 The readings of humidity taken under the UCV canopy should be within ±5%RH of the readout on the theatre control panel.

12.112 The use of smoke to gain an understanding of the overall performance of the canopy may prove useful at this stage in the validation process but cannot be relied on to produce a contractually definitive measure of performance.

UCV canopy noise level

Direct reading differential pressure gauges

12.119 The differential pressure across the terminal filter should be measured to confirm the accuracy of the indicated reading of any gauge.

12.113 An industrial-grade sound level meter to BS EN 61672 Type 2 fitted with a muff will be used to check the noise level. The instrument should be calibrated using a matched sound source prior to each set of readings.

Control functions

12.120 The operation of all control functions provided on the theatre control panel should be checked for conformity

12.114 The noise level readings are to be taken at a typical normal listening position 1.5 m above floor level and at least 1 m from any surface and not on any line of

[HTM 03-01 A – PDF page 151]

12.0 Acceptance testing: validation

with the design specification (see Appendix 10).

UCV operating suite validation report

12.121 If an auxiliary panel has been fitted, its interlocking with the main theatre control panel control functions will be checked for conformity with the design specification.

Panel indicator lights

12.126 Following validation, a full report detailing the findings will be produced and sent to the client’s lead project manager. The report should conclude with a clear statement on whether the UCV operating suite as a whole achieved or did not achieve the standard set out in the agreed design specification.

12.127 The client’s lead project manager should lodge a copy of the report with:

• theatre manager;

12.122 The panel indicators should illuminate as appropriate when the control functions are selected, or warning levels are reached (see Appendix 10 for an example “cause and effect” test regime).

• infection prevention and control;

BMS interface

• estates and facilities.

12.123 The operation, monitoring and alarm functions should be checked for conformity with those set out in the design specification.

Pharmacy aseptic preparation facilities

UCV theatre microbiological tests

12.128 The following regime of inspection and testing should be applied to the validation of new installations. The test regime has been devised to ensure that the system as installed fully achieves the operational requirement for these systems as set out in EUGGMP and the design specification.

Basic requirement

12.124 There is little value in performing microbiological sampling in an empty operating theatre supplied with ultra clean ventilation. The foregoing filter challenge tests, air velocity measurements and entrainment test will have proved that the system operates satisfactorily and achieves the contracted level of performance. The EPA filters will remove bacteria-sized particles from the air supplied through the UCV canopy. Therefore, there will be an insignificant number of bacterial and/or fungal cfus present until the theatre is actually used.

12.129 The validation procedure set out in paragraphs 12.1–12.33 should have been satisfactorily completed prior to attempting to validate the aseptic preparation facility. The suite to be validated should be physically complete with final finishes applied and have been completely cleaned. All ventilation systems serving it should be operating correctly and delivering their design airflow rates.

12.125 Following full validation, in-use microbiological sampling during a surgical procedure will not be required unless specified by the client’s VSG.

[HTM 03-01 A – PDF page 152]

Test and measuring equipment

Aseptic preparation facility validation procedure

12.137 Any test or measuring equipment used should have a certificate to prove that its calibration has been checked within the previous 12 months at a facility using traceable national standards.

12.130 Tests to validate the suitability and performance of the aseptic preparation facility should be undertaken in the order that they appear below. Should an item fail to meet the required standard it should be rectified and successfully retested before passing on to the next test.

Supply terminal EPA or HEPA filter seal leak test

Summary of test regime

12.131 Challenge tests should ensure that:

12.138 The test will confirm that there is no unfiltered air bypassing the EPA or HEPA filter seal.

• the supply terminal HEPA filters are sealed in their housings so that no air will bypass them;

12.139 Each EPA or HEPA filter seal should be scanned using a light scattering airborne particle counter (LSAPC) to prove that there are no leaks.

• the terminal filters are of a uniform quality and undamaged.

12.132 Differential pressure measurements should ensure the correct pressure cascade.

12.140 A spot reading will be taken at the face of the filter to determine the background particle level. A leak is defined as a significant and repeatable rise above the background level.

Terminal (EPA or HEPA) filter media leak test

12.133 Particle counting should be carried out at a specified number of test positions in order to determine the individual clean room classification in accordance with ISO EN 14644.

12.134 Control system checks should ensure that the system operates as specified.

12.141 The test will confirm that the terminal filters have not sustained damage while being installed.

12.135 Microbiological sampling should check the air quality.

12.142 The face of each terminal filter should be scanned using an LSAPC to prove that there are no leaks.

Test and measuring conditions

12.143 A leak is defined as a significant and repeatable rise above the background level.

Clean room particle count

12.136 While validating the aseptic preparation facility, the conditions in the clean rooms should be stable and within the given ranges.

Temperature: 19–23ºC dry bulb.

Humidity: 30–70% relative humidity.

12.144 The test will confirm the number and size of particles present and therefore the classification of the clean room in terms of ISO 14644 or EUGGMP as specified in the project brief.