HTM 03-01 A: _Hlk37000395 – Design proposal review / _Hlk37000395 – Permeability testing
[HTM 03-01 A – PDF page 138]
Design proposal review
12.10 The contract arrangement should give the validator the right to visit the site as often as they deem necessary during the contract period.
First fix inspection
12.6 It is essential that whoever has been appointed to carry out the final validation acceptance of the system should be involved in the initial client’s brief and design specification, preferably prior to the project being put out to tender. They will then be fully aware of the client’s requirements and any limiting factors.
12.11 The validator should carry out a physical walk-around inspection of the installation at a point in the project when the AHU is “on site” and the main and branch ductwork is for the main part installed, but prior to the ductwork being concealed behind wall panelling or ceilings.
12.12 If possible, the following airtightness tests should be witnessed during the inspection:
While it is beneficial to involve the client’s validator in the design process, it should be remembered that the appointed designer carries the “design risk” and advice from the validator will not obviate this.
• AHU installation leakage (BS EN 1886);
• supply and extract duct leakage (BESA DW/143);
• initial permeability test (see paragraph 12.17).
12.7 It is important that the validator understands the complete project and not just the obvious ventilation aspects. Decisions about the type of ceilings, doors, access hatches, fire compartmentation, floor markings, room functions, their adjacency and the proposed workflow patterns all have a direct effect on the likelihood of being able to achieve the desired ventilation performance. It is not sufficient to consider the ventilation in isolation.
12.13 The quality of the installation, compliance of the AHU, suitability of the basic installation, location and future accessibility of commissioning dampers, location and compliance for testing of fire dampers, etc, can all be assessed during the visit.
12.8 During this process any derogations proposed by the contractor/supplier should be clearly defined, agreed and documented with the client (for example, through the VSG). All parties will then be clear as to what will be the acceptable standard of installation and performance when finally validated.
12.14 When validating large projects that have many AHUs, it is worthwhile to visit the AHU manufacturer to inspect a specimen unit and agree its compliance before all remaining units are built and transported to site. At that time the leakage and deflection tests can be demonstrated by the AHU supplier in their factory.
12.15 Once units are delivered to site, it is useful to get all mechanical and electrical services connected to a specimen AHU. The location of pipework joints, drain points, anti-vibration couplings, isolating and control valves can all be agreed, as can the route of cable ways and control wiring. The
12.9 The ventilation designer(s) should provide the validator with system information listed in Table 11. The information should be in the form of an annotated drawing for each ventilation system to be validated. They should also provide any other design or specification information that will assist the validation process.
[HTM 03-01 A – PDF page 139]
12.0 Acceptance testing: validation
object will be to create an agreed “exemplar unit”. If all other AHUs are installed in an identical fashion, they will normally be considered compliant at the time of final validation.
Any leaks discovered during the test are to be sealed at the point of penetration of the building fabric envelope and NOT at the gaps around IPS panels, ceiling hatches or bedhead trunking covers, etc (see also paragraph 10.30).
12.16 On completion of the first fix visit the validator should provide the client with a short report identifying items that are not compliant with the specification.
Follow-on inspections
Permeability testing
12.17 The following areas will require permeability testing:
• isolation suites of any type;
• operating suites of any type;
12.20 Dependent on the size and complexity of the installation, a second and further inspection visits may be required. The validator should attend site as frequently as necessary in order to try to eliminate any installation issues as the project develops and while trades are still in attendance, rather than having to resolve them at the time of final acceptance.
• pharmacy aseptic preparation facilities;
• IAP cleanrooms in sterile services departments;
Final acceptance inspection: validation
• category 3 and 4 containment facilities;
• any other area specified within the contract.
12.21 The commissioning of a ventilation system will normally be carried out by the suppliers of the various elements. The final acceptance validation will check that all of the elements work as a whole to achieve the project aim.
The methodology for permeability testing is set out in BSRIA document BTS 3 – ‘Air permeability testing of isolation facilities’.
12.22 The following regime of inspection and testing should be applied to the validation of all new and refurbished ventilation systems. It may also be applied to systems that have undergone significant changes such as the replacement of a fan or other major component.
Basic requirements
12.18 An initial permeability test should be witnessed at first-fix stage when the envelope of the suite is physically complete but before wall, ceiling and floor finishes are applied. The objective will be to find and eliminate any construction leaks (for example, between a floor slab and curtain wall) before they become covered up during the fit-out stage (see paragraph 10.30).
12.19 A full permeability test in accordance with the methodology given in BSRIA BTS 3 will be carried out at practical completion to ensure that all service penetrations have been adequately sealed.
12.23 The area served by the ventilation system to be validated should be physically complete with final finishes applied. The doors should fully close against the design pressure differential with IPS panels fitted and any access hatches closed. All ventilation plant serving it should be
[HTM 03-01 A – PDF page 140]
operating correctly and have been commissioned in accordance with the project contract.
12.27 Any test or measuring equipment used should have a certificate to prove that it has been calibrated within the previous 12 months at a facility using traceable national standards.
12.28 In the case of a noise meter, its “matched sound source” should have a certificate to prove that it has been calibrated within the previous 12 months at a facility using traceable national standards. The noise meter should be calibrated to the sound source on each occasion that it is used.
In projects on existing sites, the area of the building being built/refurbished is often sealed off from the “in use” part to prevent dust penetration. At final validation the seals need to be at least temporarily breached in order to be able to determine the ventilation performance in “normal” conditions. If this is not possible, validation will be conditional on a final “actual” performance check when the seal is removed at the time of handover.
12.29 The validator has the right to either witness readings taken by the commissioning team or to independently take such readings and measurements as they deem fit in order to satisfy themselves as to the actual performance of the system.
12.24 The area served should be free of any rubbish, debris, obvious dust and have been wet-mopped before the validation is undertaken.
Validation process
12.30 The validation process should follow the sequence given below. Any failures discovered during the process should be rectified before continuing. The validator should check the following:
• the location of the air intake and discharge and their position relative to each other and other intakes and discharges;
There is no need to clean the area to the point that the validator needs to gown up in order to enter it. A certain amount of disturbance to hatch seals, ceilings, panels, etc will be inevitable during the validation process, so the area will require a final “clinical” clean prior to being taken into use.
• inspection and cleaning access to the vermin mesh and as necessary throughout the installation;
• the security, suitability of and access to the AHU location;
12.25 The validation process should be a continuation of the earlier site inspections and will in many cases be carried out in parallel with the commissioning process.
• sufficient space and access arrangements for service and maintenance;
12.26 Unless stated elsewhere in the design specification, the conditions in the principal space served by the ventilation system being validated should be stable and within the given ranges.
Temperature: 18–22ºC dry bulb.
• that the AHU is uniquely identified (see paragraph 13.17) and complies with the minimum standards set out in Chapter 9;
Humidity: 30–70% Relative humidity.
[HTM 03-01 A – PDF page 141]
12.0 Acceptance testing: validation
ventilation system is in an operational state;
• that the AHU and distribution system have been leak-tested and comply with the design;
• that any user controls fitted operate correctly (for examples of “cause and effect testing”, see Appendix 10);
• that the AHU and supply ductwork system are clean and free of visible dust;
• that the temperature and humidity in the space being ventilated are accurately indicated on the user panel and that they can be adjusted within the specified limits, if applicable;
• that all fire and smoke dampers have been inspected and tested for correct installation and operation. A certificate to that effect, signed and dated by the inspector and tester, will be available for inspection;
• that the estates control functions operate correctly and the plant condition is clearly shown both on the plant control panel and at the BMS/ BEMS interface;
• that the area served by the ventilation system is complete and free from significant defects that could invalidate the validation process;
• that the fire cause and effect strategy has been demonstrated and operates correctly. This may be carried out by others, in which case a statement signed and dated by the person carrying out the test will form part of the handover information;
• that the supply and extract airflow rates are in accordance with the design +10%; –0% and the system terminals are in balance. Note that the total supply and extract air volumes measured at the AHU should equate to those measured at the terminals. A discrepancy in the totals would indicate a leak in the system which should be resolved before proceeding further;
• that any additional tests called for in the project specification have been carried out and witnessed by the validator or the client’s appointed expert.
• that the air-change rate calculated from the measured airflow and room dimensions accords with the design specification;
• that the room differential pressure regime is in accordance with the design and that if pressure stabilisers are fitted, they operate correctly and silently;
Validation is not a “snagging” inspection. The main contractor has presented the installation as being complete, fully commissioned, achieving the specified level of performance and ready for handover. The validator’s role is to check on behalf of the client that the contractor is correct in that assertion.
• the air velocity at a specific location(s) if required in the application specification;
• that the noise level does not exceed the design value;
• that the system indicators correctly and clearly show whether or not the
If the validator discovers that there are a significant number of snags and non-compliances, the validation should be terminated. It is the contractor’s responsibility to snag the project, carry out remedial works and re-present the installation for acceptance. The validator will then need to repeat the validation
[HTM 03-01 A – PDF page 142]
process. The client is entitled to deduct any resulting additional validation fees incurred from the contractor.
operating suite. The test regime has been devised to ensure that the system as installed fully achieves the operational requirement for these systems as set out in Chapter 8.
UCV canopy validation procedure
12.36 The validation procedure set out in paragraph 12.30 onwards should have been satisfactorily completed prior to attempting to validate the UCV canopy. The operating suite to be validated should be physically complete with final finishes applied. All ventilation systems serving it should be operating correctly and delivering their design airflow rates.
12.31 It is vitally important to complete the validation process before the system is accepted by the client. Due to the nature of the ventilation installation and the intensity of use in the healthcare setting, it will not be possible to correct any faults or non- compliances once the system has been accepted and taken into use. There are also medico-legal aspects around taking a non- compliant system into use. Pre-announced handover or occupancy dates are not a reason for the validator or client to accept a non-compliant installation.
Validation report
12.37 Tests to validate the suitability and performance of a UCV canopy should be undertaken in the order that they appear below. If an item fails to meet the required standard it should be rectified and successfully retested before passing on to the next test.
Summary of test regime
12.32 Following validation, a full report detailing the findings will be produced and sent to the client’s lead project manager. The report should conclude with a clear statement on whether the system achieved or did not achieve the standard set out in the agreed design specification.
12.38 Leakage tests should ensure that:
12.33 The client’s lead project manager should lodge a copy of the validation report with:
• the UCV canopy is correctly assembled and sealed so that no air will bypass the filters;
• head of the user department;
• infection prevention and control;
• the canopy terminal filters are correctly sealed in their housings;
• estates and facilities.
• the canopy terminal filters are of a uniform quality and undamaged.
Additional specialist tests
12.39 Air velocity measurements should ensure that:
12.34 Certain critical areas will require additional testing and validation in addition to the process given above.
• a sufficient quantity of air is being delivered by the canopy;
UCV theatres
• the airflow has sufficient velocity to reach the operating site plane.
12.40 An entrainment test should ensure that contaminants arising outside of the UCV canopy footprint are not drawn into it.
12.35 The following regime of inspection and testing should be applied to the validation of new installations designed to provide ultra-clean conditions in an
[HTM 03-01 A – PDF page 143]
12.0 Acceptance testing: validation
12.41 Visualisation techniques should gain an understanding of the overall system performance.
The noise meter should be calibrated to the sound source on each occasion that it is used.
Test grid – vertical flow canopies
12.42 Noise measurement should ensure that working conditions are satisfactory.
12.43 Control system “cause and effect” checks should ensure that the system operates and indicates as specified (for example, see Appendix 10).
12.50 A test grid should be constructed on the floor within the UCV canopy footprint as projected by the inside dimensions of the side walls or boundary air curtain. A suitably marked test sheet will provide a consistent standard of test grid.
12.44 The successful completion of the test regime will ensure that the system will be effective if used correctly.
Test and measuring background conditions
The entire clean zone footprint of the UCV canopy will be designated by a contrasting coloured inlay in the floor covering. A line marked on or cut into the floor covering is not sufficient and will not be accepted.
12.51 The test grid should comprise test squares of 280 mm × 280 mm dimension.
12.45 The entire theatre suite should be clean and free from debris and visible dust. It should be in a condition that if the validation is successful the suite will only require a final clinical clean before being taken into use (see paragraph 12.24).
12.46 All doors should remain closed when readings and scans are being taken.
12.52 The test grid should be aligned along the centre lines of the canopy footprint with its centre under the centre point of the canopy.
12.47 The conditions in the operating theatre should be stable and within the given ranges.
12.53 Any test square with 80% of its area within the UCV footprint should be used as a test position.
Temperature: 18–22ºC dry bulb.
Humidity: 30–70% Relative humidity.
Test and measuring equipment
12.54 An inner zone will be designated that is not less than 36% of the total footprint. It will be made up of a number of test squares distributed symmetrically about the canopy footprint centre line. Regardless of the size or shape of the canopy footprint, the inner zone will comprise a minimum grid of 6 × 6 test squares.
12.48 Any test or measuring equipment used should have a certificate to prove that it has been calibrated within the previous 12 months at a facility using traceable national standards.
12.55 Unless specified otherwise, a test position should be in the geometric centre of a test square.
12.56 Test position 1 will be the left-most test square in the row nearest to the operating theatre wall that houses the
12.49 In the case of a noise meter, its “matched sound source” should have a certificate to prove that it has been calibrated within the previous 12 months at a facility using traceable national standards.