Ventilation system commissioning records
11.63 Following commissioning, the main contractor will collate the individual commissioning reports together with the plant user manuals ready for handover.
11.60 With an LSAPC the filter face is sampled at several points to establish the smallest non-penetrating particle size. This will directly relate to the grade of filter under test. The filter face, its seal and housing are then scanned, and if a significant number of particles at or above this size are detected, there is deemed to be a leak at or near the test position.
11.64 The fire dampers will have been tested by a specialist, and a written statement detailing which fire dampers were tested, when and by whom should be provided. If any fire dampers in the system were not tested, they should be listed and appended to the statement.
11.65 The airflow balancing report compiled by the commissioning engineers should be available to the validator. The report should include copies of the equipment calibration certificates.
11.61 With DOP a challenge aerosol of inert particles of the type produced by a dispersed oil particle generator is introduced into the air, upstream of the EPA or HEPA filter. The downstream face of the filter, its mounting seal and housing are then scanned for leakage using a photometer. A leak should be deemed to have occurred if a steady and repeatable reading on the photometer at any point exceeds 0.01% of the upstream reading.
11.62 Should the EPA or HEPA filter fail this test, it will be replaced. Should the filter
[HTM 03-01 A – PDF page 137]
12.0 Acceptance testing: validation
12.0 Acceptance testing: validation
12.1 All new and refurbished ventilation systems should be independently validated prior to acceptance by the client.
12.2 Validation differs from commissioning in that its purpose is to look at the complete installation from air intake to extract discharge and assess its “fitness for purpose as a whole”. This involves examining the fabric of the building being served by the system and inspecting the ventilation equipment fitted as well as measuring the actual ventilation performance. Validation is not a snagging exercise; see the Note after paragraph 12.30.
It is unlikely that the client’s in-house staff will possess the knowledge or equipment necessary to undertake this process. Validation should therefore be carried out by a suitably qualified competent engineer appointed by the client. The validator would be the client’s AE(V) (see Chapter 2 in Part B of Health Technical Memorandum 03-01) or someone of similar standing who is familiar with the ventilation requirements for healthcare facilities. They will be completely independent of the system designers, contractors, suppliers, installers, commissioners and those who will subsequently operate and maintain the system.
12.5 To retain independence, the validator should be appointed and paid directly by the client. The validator will act as the client’s representative to inspect the system, check its performance and recommend acceptance, or not, to the client.
12.3 Validation is a process of proving that the system in its entirety is fit for purpose and achieves the operating performance originally specified. It will normally be a condition of contract that “The system will be acceptable to the client if at the time of validation, it is considered fit for purpose and will only require routine maintenance in order to remain so for its projected life.”
“Client” means the healthcare provider, not a contractor or service provider.
Appointment of validator
12.4 In order to ensure that the complete system operates correctly it will be necessary to validate it as a whole from the air intake through to the extract discharge.