HTM 03-01 A: _Hlk37000395 – Specific performance standards
[HTM 03-01 A – PDF page 134]
volume delivered will be related to the air-change rate for the application.
When balancing combined supply/ extract cascade ventilation systems (for example, operating suites, clean room suites), the airflow through the extract terminals in the adjacent corridors may need to be adjusted outside of their original design values in order to achieve the desired room pressure differentials.
Air-conditioning plant
Measuring the air pressure in the main supply duct and using that to set the supply fan speed as a percentage of its rated output and using that to set the extract fan speed as a percentage of the supply fan speed is not a satisfactory, accurate or acceptable way of controlling the desired supply and extract air volumes.
11.44 The location of all control and monitoring sensors should be checked and their accuracy proved.
11.40 The specified flow rate and/or pressure drops will be set for all heater- batteries, cooling coils and humidifiers. The methods described in the CIBSE Commissioning Codes W and R should be followed. On completion their regulating devices will be locked to prevent alteration.
11.45 The control system’s ability to carry out its specified functions will need to be proved. The correct operation of any alarm systems should also be proved.
Control system
11.41 The control system should not be commissioned until both the air distribution system and air-conditioning equipment have been commissioned.
11.46 If the plant is provided with a “users” control panel in addition to the one located in the plantroom, the operation of both should be proved. This will typically apply to operating departments and laboratory systems.
Specific performance standards
11.47 The performance of the system should be measured and compared with information provided by the designer.
11.42 Because of the specialised nature of control systems and the fact that each manufacturer’s system will contain its own algorithms and settings, commissioning should be completed by the supplier, and witnessed and documented by a representative of the client (for example, the healthcare organisation’s appointed validator).
Plant capacity and control
11.48 When setting to work and proving the design, both the manufacturer of the air handling plant and the control specialist should attend site together and jointly commission the system.
11.49 If any doubt exists as to the capacity of the installed system, its ability to achieve the specified inside design conditions with
11.43 In the vast majority of healthcare applications, the fan output should be set to give a constant volume of air. This to be controlled by measuring the pressure drop across the fan using a sensing ring and associated volume controller that will automatically integrate the fan factor to determine and control the pre-set output air volume. The fan output will then in air volume terms remain constant regardless of changes of system resistance. The actual
[HTM 03-01 A – PDF page 135]
11.0 Commissioning systems
the plant operating at winter and summer outside design conditions should be proved. Artificial loads will be required in order to simulate the internal gains/losses and the outside design conditions.
11.55 In the event of a contractual deficiency a Type 1 precision-grade sound level meter should be used and the noise level determined by the procedure given in Health Technical Memorandum 08-01.
Filter challenge
General ventilation filters
11.50 On completion of the plant performance test, recording thermo- hygrographs should be placed in each room/ area served by the plant and also the supply air duct upstream of the fog coil. The plant should be run for 24 hours with all doors closed. During this period the inside conditions should stay within the tolerances specified. Alternatively the BMS may be used to obtain the information required.
Noise levels (general)
11.56 In-situ performance tests will not normally be required for primary and secondary filters and their housings. However, the filters should be visually inspected for grade, tears, orientation and fit within their housing. Filters should be clean and a replacement set available. Bag filters should be installed so that their bags are vertical and spaced so that air can move through them freely.
11.57 Air leakage around a filter housing significantly reduces the filter efficiency. The as-fitted filter housing and access door arrangement should not permit air to bypass.
11.51 The commissioning noise level is that measured with a sound level meter in the unoccupied room, taking account of the external noise together with the noise generated by the ventilation system. Chapter 8 and Table 1 in Chapter 4 give information for many applications.
EPA or HEPA filters (for exhaust protective enclosures and laboratories)
11.58 Pathogenic material may be discharged through damaged or badly installed EPA or HEPA terminal filters. The complete installation should be tested using the method set out in BS EN ISO 14644.
11.52 The noise levels apply at the maximum velocity for which the system is designed to operate. Acoustic commissioning tests should be carried out with all plant and machinery running normally and achieving the design conditions of airflow, temperature and humidity.
The challenge tests may be carried out using either of the following techniques:
11.53 An industrial-grade Type 2 sound level meter will normally be sufficient to check the noise level. Its accuracy should be checked using a calibrated sound source before use.
• a light scanning airborne particle counter (LSAPC) and a natural challenge to detect leaks;
• dispersed oil particle (DOP) to provide the challenge and a photometer to detect leaks.
11.54 The noise level readings are to be taken at typical normal listening position 1.5 m above floor level and at least 1 m from any surface and not on any line of symmetry. In critical rooms the noise should be measured at the centre of the room and at the centre of each quarter. The mean of the five readings should then be calculated.
11.59 In both cases the upstream challenge should be measured. A measurement of particle penetration through a representative section of the EPA filter media is then taken and used as the