HTM 03-01 A: _Hlk37000395 – Dynamic commissioning
[HTM 03-01 A – PDF page 132]
Dynamic commissioning
• that a borosilicate glass trap is fitted and is easily removable;
Air-handling and distribution system
• that the trap discharge point to drain has a clear air-gap of at least 15 mm;
• that the pipework is supported so that the air-break cannot be reduced;
• that the drain system from each drain tray is independent up to the air- break.
11.27 Before commencing the dynamic commissioning all rubbish should have been removed and the floors swept and wet- mopped (see paragraph 10.6). Any IPS panels should be in position, access hatches closed, light fittings in place and ceiling tiles clipped down as necessary.
11.25 The operation of the drainage system is then proved by introducing water into the duct at the drain tray and observing that it completely drains out. This check is to be repeated both at normal speed and set back once the fans have been commissioned. At this time the clear trap can be marked to indicate the normal water level with the fan running.
Fire dampers
11.26 The following will be witnessed and proving tests should be carried out as detailed:
11.28 The fan drive, direction of rotation, speed and current drawn should be set in accordance with their manufacturer’s instructions. In the vast majority of healthcare applications, the fan output should be set to give a constant volume of air. This to be controlled by measuring the pressure drop across the fan using a sensing ring and associated volume controller that will automatically integrate the fan ‘K’ factor to determine and control the pre-set output air volume. The fan output will then in air volume terms remain constant regardless of changes of system resistance. The actual volume delivered will be related to the air-change rate for the application.
• The operation of all fire and smoke dampers (fire dampers fitted with a thermally actuated “memory metal” mechanism should be proved using a hot air heat source).
• The access provided to enable the dampers to be visually inspected and/ or reset should be sufficient for the purpose.
• Indication should be provided of the dampers’ position (open/tripped).
11.29 After the installation has been checked to ensure that it is in a satisfactory and safe condition for start-up, it should be set to work and regulated to enable the plant to meet its design specification. The proportional balancing method described in the CIBSE Commissioning Code A should be followed. The airflow rates will be set within the tolerances laid down in the design brief. This will normally be the design airflow rate +10%; –0%.
• Indication of the fire dampers’ location should be provided both on the ductwork and at a visible point on the building fabric if the ductwork is concealed.
Plug fans are fitted with a measuring ring so that the design volume flow can be set when first started. It can then be reset as the airflow balance progresses. This method will result in the correct airflow with the least total system resistance once balancing is completed.
[HTM 03-01 A – PDF page 133]
11.0 Commissioning systems
Air commissioning measuring equipment standards
off, and then the extract balanced with the supply fan(s) on. The supply balance should then be rechecked.
11.30 All test and measuring equipment used will have a certificate to prove that its calibration has been checked within the previous 12 months at a facility using traceable national standards.
11.35 For combined systems where the area that they serve is to be below atmospheric pressure, the extract should be balanced first with the supply fan switched off and then the supply balanced with the extract fan on. The extract should then be rechecked.
11.31 System performance should be measured at the main and branch duct supply and extract test points using a pitot and manometer or a thermal anemometer.
11.36 On completion of the balance, all volume airflows in supply and extract ducts and from grilles and diffusers will be measured and recorded. The true air- change rate can then be calculated from the data obtained.
For accuracy the room dimensions should be actually measured on site rather than deriving them from design drawings.
11.32 Supply and extract air volumes at the room terminals should be measured using a calibrated hood with back pressure compensation. If a hood correction factor is applied, it should be determined by a direct comparison with a duct measurement immediately adjacent to a terminal and not a general comparison between air at the main supply duct and the total as measured at the terminals. For multi-directional terminals a correction cross will be fitted in the measuring hood.
11.37 All supply and extract duct volume control dampers should be locked and their position marked and the fan motor settings noted and recorded.
Measurements taken with a “home- made” hood or cone will not be accepted.
11.38 All grille and diffuser volume control registers should be locked to prevent alteration and their final position marked.
Room air distribution
11.33 Measurements at extract grille faces should, where possible, be taken using a calibrated hood. Alternatively they may be measured with a rotating vane anemometer fitted with a hood, or as a last resort, scanned using a rotating vane anemometer and a free area factor applied. The grille face free area and factor used should be stated in the commissioning report.
Order of commissioning
11.39 The pressure relief dampers and pressure stabilisers will be set to achieve the specified room differential pressures and locked. The grille direction control vanes and diffuser cones will be set to give the specified air movement pattern. Visualisation techniques may need to be employed to prove the required airflow pattern is being achieved and detect any adverse coanda effects (see paragraph 9.162).
11.34 When combined supply and extract systems are to be balanced and the area that they serve is to be at or above atmospheric pressure, the supply should be balanced first with the extract fan switched