HTM 03-01 A: _Hlk37000395 – Pre-commissioning checks
[HTM 03-01 A – PDF page 130]
• that the satisfactory sealing of access doors and viewing ports has been carried out;
in paragraphs 11.27–11.46, the performance tests listed in paragraphs 11.47–11.64 and finally the handover procedures set out in paragraphs 11.63–11.65.
• that the AHU airtightness test as per BS EN 1886 has been carried out;
11.18 Once the system is shown to meet the design intent, the handover documentation should be completed. In the event of performance not being acceptable, the matter should be dealt with in accordance with the contract arrangements.
Pre-commissioning checks
• that air-pressure tests and air-leakage tests on ventilation ducting have been carried out in accordance with the methods set out in the BESA DW143 – ‘Ductwork leakage testing’ but the leakage rate to be not greater than 3% (it is usual to carry out these tests a section at a time as the ductwork is installed and before its insulation is applied. The results will be recorded in the commissioning manual);
• that gaps around doors and hatches are as specified in the design;
11.19 The pre-commissioning checks consist of visual inspection, manual operation of equipment, static measurements and functional tests of individual components. They should be carried out prior to setting the system to work and undertaking the dynamic commissioning process set out in paragraph 11.27 onwards.
• that the permeability tests are carried out as per paragraph 12.17;
• that the correct operation of pressure stabilisers, control dampers, isolating and non-return dampers have been checked;
• that test holes have been provided in their specified locations and are sealed with suitable grommets;
Before commencing commissioning, it is essential that builders’ work in the area served by the system is complete. The doors and windows should be fitted, floor finishes applied, walls and ceilings completed and their final finish applied. Fans should not be run until the area is clean (see paragraph 10.6).
• that control dampers are secured and their quadrants fitted correctly;
• that any interlocks are operative and in accordance with specification;
Standard of installation
• that the electric circuits are completed, tested and energised;
11.20 During the installation of the system the following will be witnessed:
• that electric motors have been checked for correct direction of rotation both at full speed and set back;
• that the plant and installations have been provided and installed in accordance with the design specification and drawings;
• that only approved sealants have been used in the installation;
• that cooling and heating media are available at correct temperatures and pressures and in specified quantities;
• that all components function correctly;
• that the air-conditioning plant components and controls function correctly;
[HTM 03-01 A – PDF page 131]
11.0 Commissioning systems
e. individual test certificates for EPA or
HEPA air filters.
• that the air-conditioning plant interlocks and safety controls function correctly;
Equipment tests
• that the plant is physically complete, insulation is applied and all ducts and pipework are identified as specified;
11.22 Prior to setting the system to work the following will be witnessed and proving tests should be carried out as detailed:
Filters
• that all service penetrations of the fabric of the area are sealed at the point of penetration (see also paragraph 10.30);
11.23 The quality of filter housing and in particular, the seals, is a critical factor in maintaining the efficacy of the filtration system by ensuring that air does not bypass the filter elements. Therefore, the following checks should be made:
a. Filter seals should be fitted and in
• that the building housing the ventilation plant is generally in a fit condition for commissioning and performance tests to commence, that is, windows, doors, partitions, ceilings, etc are completed, surfaces sealed and their final finish applied;
good condition.
b. Filters should be installed correctly
with respect to airflow.
• that the areas containing the ventilation plant and those being served by it are clean;
c. Bag filters should be installed so
• that access to all parts of the system is safe and satisfactory.
that the bags are vertical and their pockets free.
d. All filters should be checked to
Certification of equipment
ensure they are free of visible damage.
e. EPA or HEPA filters should be
scanned with an LSAPC to prove that they and their housings achieve the specified filter efficiency.
11.21 The following test certificates should be assembled by the commissioning team and be available for inspection at any time during the contract period. They will form part of the handover information and should be placed in the commissioning manual:
f. The differential pressure indicators
a. type test performance certificates for
fans;
should be checked for accuracy and that they are marked with the initial and final filter resistance.
b. pressure test certificates for:
Drainage arrangements
i. heater-batteries;
ii. cooling coils;
iii. humidifier (if appropriate);
11.24 The drain should conform in all respects to the standard set out in paragraph 9.105 onwards. In addition, the following should be proved:
c. type-test certificates for attenuators;
d. type-test certificates for primary and
• that the drain tray is easily removable or completely accessible;
secondary filters;
• that the drift eliminator (if fitted) is removable without the use of tools;