HTM 03-01 A: _Hlk37000395 – General
[HTM 03-01 A – PDF page 127]
11.0 Commissioning systems
11.0 Commissioning systems
Location of dampers and test holes
General
11.5 Balancing/commissioning dampers will be required in each branch of the distribution ductwork. In a critical system such as an operating suite, the branch to each room and each location where it is required to carry out a proportional balance should have a balancing damper.
11.1 Commissioning is the process of advancing a system from physical completion to an operating condition. It will normally be carried out by specialist commissioning contractors working in conjunction with equipment installers. Commissioning of the ventilation system will normally be the responsibility of the main or mechanical contractor who should coordinate the process.
11.6 Test holes for the measurement of airflow will be required at carefully selected points in main and all branch ducts. The number and spacing of holes are given in the BSRIA BG 49/2015 Commissioning Air Systems. Their positions should be identified at the design stage.
11.2 Commissioning is often subdivided into sections (for example, air handling unit, automatic controls, air side balance, building fabric and fittings). Each section may be commissioned by its specialist installer, and they are often accepted in isolation.
11.7 The test positions need to be accessible for commissioning to take place. They may also be required for subsequent annual verification of the system performance, so they should not be covered by permanent lagging.
11.3 Commissioning is an essential process for ventilation systems. It is therefore important that adequate provision for the process be made at the design stage of the project. Procedures for commissioning air-handling systems are given in CIBSE Commissioning Codes and BSRIA BG 49 – Commissioning Air Systems.
11.8 The measurement point should be in a straight length of duct as far away as possible from any upstream bends, dampers or other elements that could cause disturbance to the airflow. The actual location should be:
• at least 1.5 duct diameters upstream of sources of turbulence such as dampers and bends;
11.4 The duct design process should take into account the requirements of system balancing. The position and number of regulating dampers included in the design should be sufficient for this purpose.
[HTM 03-01 A – PDF page 128]
Table 11 Information to be provided on schematic
drawings
Items in system Information to be provided
• if this is not possible, ten diameters downstream of dampers, bends or tees, and five diameters downstream of eccentric reducers;
Fans Fan total pressure Volume flow rate at normal and set back speed Maximum motor current
• where there is enough space round the duct to insert the pitot tube and take readings;
• where the duct has a constant cross- sectional area.
Plant items Type and identification numbers from equipment schedules Fluid and air volume flow rates Fluid and air side pressure losses Dry bulb temperatures Wet bulb temperatures Humidity
Dampers, including motorised and fire dampers
Identification numbers from equipment schedules Location Identification number Volume flow rate
Test holes for measuring total airflow from a fan should be located either four diameters upstream or ten diameters downstream of the fan. Provision should also be made for measuring the fan’s speed of rotation.
Main and branch ducts
Dimensions Volume flow rates and velocities Identification numbers from equipment schedules
Test holes and access panels
Location and size of duct Identification number Design airflow rate
Room supply and extract terminals
Plug and EC fans are supplied with a measuring ring so their output can be read directly. This needs to be connected to an external pressure tapping or electronic fan control unit.
Location Identification number Grille or diffuser factor Volume flow rate and neck velocity Operating static pressure
Information to be provided
Pressure cascade Room differential pressures Airflow direction between rooms Pressure stabiliser and transfer grille locations
11.9 It is essential that the designer should pass on the system-design intent fully to the commissioning engineer by providing:
Internal environment conditions
Design room conditions and adjustable range Specific room air velocity if specified Noise level
• relevant parts of the specification;
Controllers Set points
• schematic drawings indicating data listed in Table 11;
Notes:
• equipment schedules;
• controller and regulator schedule;
• fan performance curves;
1. Fan total pressure is the difference between the total pressure (static pressure + velocity pressure) at the fan outlet and the total pressure at the fan inlet.
• wiring diagrams for electrical equipment, including interlock details.
2. Where volume flow rates are variable, maximum and minimum values should be provided.
[HTM 03-01 A – PDF page 129]
11.0 Commissioning systems
Commissioning personnel
summer, together with the control strategy;
• equipment manufacturers’ type test data, commissioning, operation and maintenance recommendations;
11.10 It is unlikely that all the required commissioning skills will be possessed by one individual; a commissioning team is therefore usually needed. The objective of commissioning is to ensure that the necessary performance and safety requirements are met.
• drawings showing the layout of the system, positions of airflow measurement test points, dampers, regulating devices and filters within the duct runs, together with sizes of ducts and terminal fittings. It will save time if these drawings are annotated with the design volumes and static pressures required at each branch and outlet point;
11.11 During the commissioning process a great deal of information will be generated which will form an invaluable future source of reference about the plant. It is essential to ensure that it is collected together in the form of a commissioning manual and handed over to the client on completion of the contract together with the “as fitted” drawings.
• wiring diagrams for all electrical equipment associated with the air- handling systems, including motor control circuit details and any interlocking and safety devices.
11.14 CIBSE Commissioning Code A – ‘Air distribution’ or BSRIA BG 49 – ‘Commissioning air systems’ provide full guidance on the information that will be required by the commissioning team.
11.12 In order to be successful the commissioning process will need to start before practical completion, as many parts of the system will become progressively less accessible. The correct installation of those parts should be witnessed and leak rate tests carried out as construction proceeds. Failure to establish responsibility for commissioning early enough will delay the completion of the project or lead to unsatisfactory plant performance (see CIBSE Commissioning Code M).
Commissioning brief
11.15 Designers should specify the type of measuring instruments and test procedures. They should include in the contract documents instructions on verifying the accuracy of test instruments, which should be supported by reference to relevant calibration certificates.
11.13 The commissioning team will require a detailed brief from the system designer. This should include:
• a “user” brief comprising a description of the installation and its intended mode of operation;
11.16 The system, on completion, should be operated by the contractor as a whole and subject to performance tests in accordance with the contract requirements. These will include independent validation of the system performance on behalf of the client.
• the precise design requirements with regard to the scheme of air movement, room static pressures, supply and extract airflow rates and acceptable tolerances;
• full details of the design conditions both inside and out, for winter and
11.17 The commissioning process should be carried out in the order in which it appears in this guidance document. That is to say, the static checks and visual inspections itemised in paragraphs 11.20–11.26 should be followed by the dynamic tests described