HTM 03-01 A: _Hlk37000395 – Ultra-clean ventilation system
[HTM 03-01 A – PDF page 68]
be taken out of use without detriment to operating conditions in the other.
that 60% saturation at 20ºC is not exceeded during the design summer outside conditions.
When not in use the humidity may be allowed to fall below 35% but should not be allowed to rise above 70%.
An AHU provided under paragraph 8.72 may be shared between two conventional operating suites, but not between a conventional and a UCV suite.
8.73 The AHU supply and extract fans should be interlocked so that the supply starts up first and shuts down last, thus preventing reverse airflows. If the extract plant fails when the theatre is in use, it may continue to be used but a warning should show on the BMS and theatre control panel. If the supply fails when the theatre is in use the extract should shut down to prevent reverse airflows and an alarm should sound and show on the theatre control panel.
Fire aspects
8.70 The automatic control of ventilation in operating suites needs to be simple and robust. Over-reliance on complex room pressure and flow relationships linked to automatic fan speed control are unnecessary and in the long term have been shown to be unreliable. Complex software algorithms that can only be accessed and interpreted by off-site specialists should not be used. Whichever control strategy is chosen, it is important that on-site staff have the facility to override the control system and keep the ventilation operating at least until the surgical procedure is complete (see also Chapter 9).
Operating suite air handling unit
8.71 Each conventional operating theatre suite should have its own dedicated AHU to the standard set out in Chapter 9. To ensure operational flexibility and permit routine maintenance, an air handling unit should not be shared between suites.
8.74 When considering the overall airflow movement, careful thought needs to be given to the operation of the ventilation system to limit smoke spread in the event of a fire. However, this is a highly staffed department with a low fire risk/load status and these factors need to be recognised when developing the fire strategy. Operating departments typically comprise a series of linked rooms with multiple exits. Over-compartmentation can lead to difficulties in establishing clean airflow paths and room air dilution rates. This will lead to an increased risk of healthcare- acquired infections. Staff areas within the department should be treated as a subcompartment.
Ultra-clean ventilation system
General requirements
8.75 The design philosophy of a conventionally ventilated operating suite is based on the need to dilute contaminants
8.72 In retrofit installations, site conditions may preclude individual AHUs for each suite. In these circumstances, subject to VSG approval, an AHU may be shared between not more than two operating suites providing each suite has its own control of temperature. An accessible airflow measurement test point should be provided in the supply branch duct to each theatre suite so that the primary air volume to each can be determined. In addition, the branch supply and extract should be capable of being physically isolated and the main airflow rate reduced so that either suite can
[HTM 03-01 A – PDF page 69]
8.0 Specific healthcare department requirements
providing operating conditions to at least a “conventional” theatre standard throughout the suite with the UCV in “low speed” mode. It should also be remembered that suitable levels of ventilation will always be required in the peripheral rooms.
8.77 UCV systems can be designed and built from first principles or a range of bespoke modular units of varying shapes and sizes are available, with each manufacturer having a slightly different approach to UCV design. Notwithstanding any variation in their design philosophy, all UCV systems will be required to completely achieve the performance standard set out in Chapter 12.
and control both the condition and movement of air in an operating suite. Ultra-clean ventilation (UCV) is a means of significantly increasing the dilution effect by providing a large volume of clean filtered air to the zone in which an operation is performed, and sterile items are exposed. Air is discharged above the operating zone and while not truly laminar, its downward displacement purges the clean zone of contaminants and particles generated by the activities within it. The airflow in and around the clean zone also serves to prevent particles originating outside the zone from entering it. The resulting reduction in contaminants has been shown to significantly reduce post- operative sepsis following certain orthopaedic procedures.
8.78 As with conventional theatres, each UCV operating suite should have its own dedicated AHU to the standard set out in Chapter 9. To ensure operational flexibility and permit routine maintenance, an AHU should not be shared between suites.
The number of microorganisms that are present in the air at the wound site and exposed surgical items is dependent on the operating team, their procedural discipline, choice of clothing and the type of UCV system. Ultra-clean air is defined as that containing not more than 10 colony forming units per cubic metre of air (10 cfu/m3) present at the wound site during a surgical procedure. In practice levels of only 1 cfu/m3 are often attained.
8.79 In retrofit installations, site conditions may preclude individual AHUs for each suite. In these circumstances, subject to VSG approval, an AHU may be shared between not more than two UCV operating suites providing each suite has its own control of temperature. An accessible airflow measurement test point should be provided in the supply branch duct to each theatre so that the primary air volume to each UCV canopy can be determined. In addition, the branch supply and extract should be capable of being physically isolated and the main airflow rate reduced so that either suite can be taken out of use without detriment to operating conditions in the other.
8.76 UCV systems are very successful in reducing contaminants at the wound site so it is often considered that there is no need for complex air movement control schemes in the rest of the suite. However, when designing the ventilation scheme, it should be noted that the users may switch the UCV terminal to “low speed” when non- orthopaedic surgery is taking place. This is because the high airflow rates can cause increased moisture evaporation of exposed tissue which may be detrimental to the surgical outcome. In recognition of this, the ventilation scheme should be capable of
An AHU provided under paragraph 8.79 may be shared between two UCV operating suites, but not between a conventional and a UCV suite.
[HTM 03-01 A – PDF page 70]
8.80 An inherent feature of a UCV system is its large airflow so it is essential to recirculate the air supplied to the operating theatre and/or to recover its energy in order to optimise operating costs.
8.83 If the client requires a “lay up” preparation room, a pressure stabiliser will be required between the preparation room and theatre. It should be fitted with a baffle on the theatre side to prevent air transfer interfering with the airflow distribution under the UCV canopy.
8.84 Separate scrub-up or disposal facilities are not necessary for air cleanliness, although operational policy may prefer such a provision. A separate anaesthetic room should however be provided.
Types of UCV system
Remote plant systems
8.81 The primary fresh air volume supplied to a UCV operating suite will be the same as for a conventional suite and it should be dispersed to the rooms in the suite in the same manner. The UCV canopy will typically incorporate recirculation fans. In order to prevent these fans “robbing” the air supply to the rooms, the primary air supply to the UCV theatre suite should be split into two ducts each with a volume control damper – one duct to feed the UCV canopy and the other for the anaesthetic and preparation rooms.
8.85 In a remote plant system, all the air- conditioning equipment is located outside of the operating theatre, except for the unidirectional airflow terminal, terminal filter, air diffuser and the return air grilles (see Figure 1).
8.86 This arrangement has the following advantages:
8.82 “Laying up” instruments in the clean zone is preferable microbiologically and considered best practice by the Royal College of Orthopaedic Surgeons, so an SPS preparation room should be provided. A transfer grille will be needed in the door between the theatre and preparation room.
Figure 1 UCV remote plant system
with eliminator
Attenuator Auxiliary cooling coil
Recirculation
fan
Drain
Primary conditioned supply air from main
air handling unit
Return air
filter
Terminal filters with diffuser screen
UCV canopy
Return air grille
Operating theatre
Alternative
return air grille location
[HTM 03-01 A – PDF page 71]
8.0 Specific healthcare department requirements
• The recirculation fans are out of the theatre, thus reducing noise. Multiple recirculation fans may be replaced by a single fan unit.
air filters, final filter and air diffuser. Primary air is supplied by a remote air- conditioning unit at the volume and to the standard required for a conventional operating suite. The UCV-canopy return-air fans may be within the unit or mounted independently of it in the ceiling void or wall space (see Figure 2).
• Casual heat gains from recirculation fan(s), canopy lights, equipment and people within the theatre can be removed by a cooling coil in the return air stream. This will prevent heat build-up in the theatre.
8.88 Modular units have the following advantages:
• As they are produced in a modular form, installation is generally more straightforward.
• The return air filters can be changed without needing access to the theatre, making routine maintenance more feasible.
• They can be used to upgrade an existing conventional operating suite to a UCV suite without the need to change the AHU.
• All the UCV elements are in one place, making maintenance simpler.
• The opportunity exists to locate the EPA filter in the primary supply duct rather than the theatre terminal. This will reduce the number of filters required and allow them to be changed without entering the theatre.
Modular systems
8.87 Vertical-flow modular units comprise a ceiling-mounted canopy containing return
8.89 UCV systems can be designed and built from first principles, or a range of bespoke modular units of varying shapes and sizes are available, with each manufacturer
Figure 2 UCV modular system
Primary conditioned supply air from main
air handling unit
Recirculation
fan
Return air filter
Terminal filters with diffuser screen
UCV canopy
and grille
Operating theatre
Alternative
return air filter and grille location
[HTM 03-01 A – PDF page 72]
having a slightly different approach to UCV design. Whichever system is used, in order for the UCV terminal to produce the desired airflow within its footprint without entraining non-filtered air, the physical outside edge of the UCV canopy unit should not be less than 1 m from the operating theatre wall.
Notwithstanding any variation in their design philosophy, all UCV systems will be required to completely achieve the performance standard set out in Chapter 12.
a 1.4 m circular or rectangular terminal may be provided. For major orthopaedic procedures, a minimum size of 2.8 m × 2.8 m will be required. This is the area projected on the floor under the supply air terminal within the full walls, partial walls or air curtain. Any air outside this zone cannot be guaranteed to be ultra-clean although given the dilution factor, the level of microbiological contamination will be much lower than the general level in a conventional operating theatre. Having a contrasting coloured area on the floor delineating the extent of the “clean zone” will assist staff and is therefore essential.
Vertical flow UCV systems
The entire “clean zone” footprint of the UCV canopy will be designated by a contrasting coloured inlay in the floor covering. A line marked on, or cut into, the floor covering is not sufficient and will not be accepted at validation.
8.90 Vertical flow systems are effective at reducing infection risks (Lidwell et al., 1982). Some systems have no walls and use auxiliary fans to create an air curtain around the clean zone. Partial wall systems have side screens that terminate 2 m above floor level and full wall UCV have side screens that terminate 1 m above floor level.
8.91 Full wall systems provide a physical barrier between the operating team and other theatre occupants and guide the air down to the operating table level. They can therefore work at a lower air velocity.
8.94 When upgrading an existing conventional theatre to an ultra-clean standard the only solution may be the installation of a modular system. In these units, the heat gains from the return air fans may warrant the inclusion of supplementary cooling within the module. However, issues of cooling-coil drainage, condensate removal and maintenance access within the space constraints of the module may make this option impracticable. The additional cooling load should then be catered for by conditioning the primary air to compensate.
8.92 Siting the return air grilles around the periphery of the theatre at low level will help control short-circuiting and give an improved airflow path. In any event there should be an “air out” path on each face or in each corner of the theatre. These may be provided by combination of pressure stabilisers and passive or active low-level extract grilles. Failure to provide “air out” paths on all faces of the theatre may result in the surplus air causing entrainment into the clean zone.
8.93 Vertical systems should have a clean zone large enough to encompass the operating site and all instrument trays likely to be needed for the procedures to be undertaken. Where the surgical site is small,
8.95 If an existing AHU is to be retained, it may require modification to ensure that it achieves the standards set out in Chapter 9 of this document (see also paragraph 4.73). The fan may need re-rating to accommodate the change in system resistance. The cooling coil may also need to be upgraded to cater for the increased load resulting from the return air fans and terminal lights. Failure to make adequate
[HTM 03-01 A – PDF page 73]
8.0 Specific healthcare department requirements
provision for this may make the theatre unusable during prolonged warm spells.
for replacement without the need to disturb the fabric of the operating suite.
UCV filters
8.99 The AHU primary and secondary filters should be to the standards and in the location set out in Chapter 9.
8.100 Terminal filters should be provided within the UCV canopy or in the air supply to it. Efficiency particulate air (EPA) filters grade E10 as specified in BS EN 1822 will be required as a minimum. There is no aerobiological benefit in fitting filters of a higher grade than this.
8.96 A factor affecting the airflow pattern is the supply/room air temperature difference. When the supply air temperature is significantly above room temperature, buoyancy effects will reduce the volume of air reaching the operating zone. This can occur at start-up in a large theatre where the temperature when not in use has dropped below 18ºC. If it is anticipated at design stage that this will be a regular occurrence, a system incorporating full walls should be used. Demountable extensions that convert a partial wall to a full wall unit are available.
8.101 In some modular UCV units their manufacturers state that the terminal filter is used as a pressure equaliser to balance airflow so a grade higher than E10 is fitted. The increased resistance may affect the velocity of air reaching the operating level and there will be penalties in terms of installed fan power, energy consumption and higher noise levels.
8.97 Convection up-currents from the surgical team and operating lamp tend to counter the movement of clean air towards the operating site, hence the air velocity reaching the operating level is critical. The minimum velocity given below has been selected to take account of these factors and is greater than the theoretical minimum value. For all vertical UCV systems the design discharge velocities will be as follows:
• Air velocity 2 m above floor level:
– no side wall system = 0.38 m/s average;
8.102 The final filters should be installed in a leak-proof housing in a manner which allows the terminal unit, filters and their seals to be validated. The UCV canopy and its terminal filters will be scanned with a light scattering airborne particle counter (LSAPC) during validation to prove the effectiveness of the complete installation.
– partial wall system = 0.38 m/s average;
– full wall system = 0.30 m/s average.
• Air velocity 1 m above floor level:
– all systems = 0.2 m/s minimum within the inner operating zone.
Chapter 12 gives details of the method of measurement.
8.103 Where UCV units are constructed in sections, a means of measuring the pressure drop across the terminal filters in each section should be provided. The pressure test points should be located outside of the partial wall, capped to prevent air leakage and accessible within the theatre without the need to open the unit inspection panels. Alternatively, direct-reading non- electronic pressure gauges (of the minihelic type) may be fitted.
8.98 Variable speed recirculation fans with differential pressure control may be the most suitable solution for maintaining consistent performance and energy saving. The recirculation fans should be accessible
8.104 The UCV system will require a return air filter to capture the relatively coarse particles which would otherwise
[HTM 03-01 A – PDF page 74]
the lowest point of the central light stem, luminaire, monitor, camera, their associated articulation arms and any other ceiling- hung equipment should never be less than 2 m above floor level.
significantly reduce the life of the final filter. This should be at least an ISO 16890 Coarse 60%. In remote recirculation systems there may be advantages in fitting a higher- grade return air filter as it will reduce the load on the terminal EPA filters and extend their life.
Noise level
8.105 If sound-attenuating material is used to line any portion of the inside of the UCV unit it should be non-particle shedding and non-combustible.
8.106 The maximum noise level in an operating theatre fitted with a UCV terminal of any type should not exceed 53 dB(A). Chapter 12 gives details of the method of measurement.
Lighting and operating lights
The traditional means of light support is a central column that passes through the UCV canopy and is rigidly fixed to the building structure. The position of the support therefore prevents air being supplied at the centre of the canopy. Separate supports displaced from the centre of the clean zone would lead to improved airflow. This approach was advocated in the 1994 version of this guidance but at the time of writing no UK manufacturer has chosen to adopt this solution. Alternatively, equipping the operating team with battery- powered headset lamps may remove the need for traditional operating lamps and their supports.
8.107 The position of the UCV light fittings and style of partial walls, where fitted, should neither adversely disturb the airflow nor result in significant spatial variations in illuminance levels.
Controls and instrumentation
8.110 The functions of the supply AHU and extract ventilation should be continuously monitored by a BMS control unit and interlocked with the UCV terminal control and monitoring functions. The room temperature sensor should be located in the re-circulated air return path. The controls and instrumentation for the main plant are set out in Chapter 9.
8.108 In vertical units, specialised task lighting should be provided by toroidal, cruciform or small multiple dome-shaped luminaires as they have good aerodynamic properties. The ideal luminaire will have a minimal effect on the airflow regardless of where it is positioned. Large diameter saucer-shaped luminaires should not be used in vertical flow systems as they will occlude the airflow in the critical central zone. It is important to consider the suitability of existing luminaires when retrofitting UCV systems.
8.111 UCV systems will additionally require a low speed facility that can reduce the air supplied through the UCV canopy to a volume that equates to not less than 22 ac/h of the operating theatre gross volume or that required for door protection, whichever is greater, whilst still leaving the supply AHU operating at full speed. In this operational mode the theatre may be used as a conventional operating suite. A means of switching between
8.109 In vertical UCV installations the distance between the UCV canopy diffuser screen and the floor should be between 2.75 m and 3 m. This will allow space for the operating lamps and their articulation arms, and ensure that air at the correct velocity arrives at the operating level. When parked,
[HTM 03-01 A – PDF page 75]
8.0 Specific healthcare department requirements
in “Set back” (legend: “Theatre not to be used in this condition”).
conventional and UCV mode will be provided on the theatre control panel and its function clearly labelled (see the Specialised Ventilation for Healthcare Society’s (2017) SVHSoc.01 – ‘Operating theatres: energy control strategies and the surgeon’s panel’ for further details).
• An amber indicator light that will illuminate when the UCV canopy is at low speed and the supply AHU is running at full speed (legend: “Conventional theatre mode”).
• A green indicator light that will illuminate when both the supply AHU and UCV canopy are operating at full speed (legend: “UCV theatre mode”).
• A blue indicator light that will illuminate when the UCV canopy airflow, as detected by a differential pressure sensor, falls below 80% of the design flow rate (legend: “UCV requires service”).
UCV theatre ventilation may be completely switched off when the theatre is not in use, but the room temperature should not be allowed to drop below 18ºC (see paragraph 8.96). The AHU and UCV control should be interlocked so that when the AHU goes to “Set back” the UCV also goes to “Set back”, and if the AHU goes “Off”, the UCV terminal fans also switch “Off”. There is no aerobiological benefit in keeping the UCV terminal fans running when the theatre is not in use, it results in wasted energy.
8.112 The following indicators should be incorporated in the theatre control panel and their functions clearly labelled. In retrofit installations an auxiliary panel for the UCV may be the most practical option. If fitted it should be mounted adjacent to the theatre panel and their control functions interlocked.
In touch screen panels the red indicator should be a band across the screen with the statement “Theatre ventilation not operational. Do not use” The amber indicator may be moving arrows representing airflow with the legend “Conventional Theatre mode”. The green indicator may be moving arrows representing airflow with the legend “UCV Theatre mode”. The blue indicator may be a band across the UCV terminal mimic stating “UCV requires servicing”.
• A readout sufficiently large (25 mm) to be clearly visible from the operating table that shows the temperature of the air at the UCV canopy.
• A readout sufficiently large (25 mm) to be clearly visible from the operating table that shows the relative humidity of the air at the UCV canopy.
8.113 When a system is designed to have partial walls with full wall extensions, a volume control facility may be incorporated to allow the system to be run with reduced velocity when the demountable full walls are in place. It would be the responsibility of the user to ensure correct operation of the system. To assist the user, an explanatory notice should be included on the theatre control panel.
• A red indicator light that will illuminate when either the supply AHU or the UCV canopy fails, or either or both are switched off or the AHU is
8.114 The UCV unit manufacturer’s control box should be located in an accessible position preferably in the operating department adjacent to the operating