HTM 03-01 A: _Hlk37000395 – Derogations and alternative design strategies / _Hlk37000395 – Resilience and diversity

Specialised ventilation for healthcare premises Part A: The concept, design, specification, installation and acceptance testing of healthcare ventilation systems · PDF pages 30–36 of 213 · Source file: HTM0301-PartA-accessible-F6.pdf
Unofficial text extract. Tables and figures may be incomplete. Authoritative version: official PDF from NHS England.

[HTM 03-01 A – PDF page 30]

negative pressure to prevent the spread of dust into the rest of the building.

but are not under direct treatment. It also includes staff and healthcare services areas.

Derogations and alternative design strategies

4.13 Certain clinical and non-clinical areas within a healthcare establishment are considered critical to its ability to provide healthcare. Typically, ventilation systems serving the following are considered critical:

• operating suites of any type including rooms used for image-guided surgical procedures and their recovery areas;

4.10 Any derogations or alternative design strategies from this guidance should be subject to the scrutiny and agreement in writing by the VSG. The reason for the derogation or alternative design strategy and limits to its application should be recorded.

• airborne isolation facilities, both source and protective;

• critical care areas and neonatal units;

• invasive treatment, endoscopy and bronchoscopy rooms;

4.11 Designers proposing a derogation or alternative design strategy should be able to supply a body of evidence that their proposal will provide a degree of safety no less than if the guidance in this document had been followed.

• containment level 3 laboratory;

• pharmacy aseptic preparation facility;

• inspection, assembly and packing (IAP) room in a sterile services department;

• MRI, CAT and other types of emerging imaging technologies that require particularly stable environmental conditions to remain within calibration;

• any system classified as an LEV system under the COSHH Regulations;

The foregoing guidance is not intended to prevent the use of new technology or stifle design innovation but rather to ensure that what is being proposed will result in a facility that is fit for purpose when used. It will not be enough to state that the derogation or alternative design strategy proposed has been used elsewhere. There should be evidence that what is being proposed has been successful elsewhere.

• any other system that clearly meets the definition that “a loss of service from such a system would seriously degrade the ability of the premises to deliver optimal healthcare”.

Definition of clinical areas and critical systems

4.12 Healthcare ventilation may serve clinical or non-clinical areas of the estate:

If any doubt exists about whether a system falls within this definition, the VSG should be consulted regarding the risk to patient safety and business continuity.

• Clinical areas are defined as spaces within the building where surgical or medical treatment is administered to patients. This includes patient bedrooms.

• Non-clinical areas are defined as spaces where patients may be present

[HTM 03-01 A – PDF page 31]

4.0 The design and specification process

Resilience and diversity

New build facilities

4.17 New build healthcare facilities must be fully compliant with the requirements of all legislation in force at a date agreed when signing the contract. They should comply with the guidance contained in the current HTM unless a derogation has been agreed with the VSG (see paragraphs 4.10 and 4.11).

Assessment of service requirements: selection of design criteria

4.14 When planning the ventilation of healthcare facilities, it is important at the outset to consider how the service will be delivered if the installed ventilation system fails or the area served has to close due to the effects of fire, flood or an outbreak of infection. The loss of power, primary heating or cooling medium, or an integrated contol system can cause the loss of ventilation to an area, so subsystem resilience is an important consideration.

External design conditions

4.18 The most accurate data that is available for the summer and winter conditions at the site should be used. The Meteorological Office supplies data for the United Kingdom; data is also available from CIBSE and other sources. It is essential that the designer agrees with the client as to which source of data is used and the design risk associated with the chosen external design conditions.

4.15 Resilience in critical healthcare areas can be provided by splitting the ventilation load between two or more AHUs and/or employing a design that allows two or more AHUs to feed a common plenum with isolation dampers on individual branches to each critical zone. (Note that it is not proposed that duplicate back-up units be provided.) As an example, a large critical care area (CCA) level 2 or 3 could be split into two sections with an AHU for each. A small CCA cannot easily be split, so a decant area with a suitable level of ventilation should be pre-designated.

It is essential to design to future climate projection to ensure design temperatures are maintained even in the event of prolonged heatwave conditions. CIBSE (2014) publishes design summer year weather files morphed to reflect future climate change.

4.19 Local adjustments for height above sea level, exposure factor, or other local climate peculiarities should be made as appropriate.

4.16 Diversity can be achieved by having several facilities each served by its own AHU. As an example, in an operating department, if each theatre suite is fed from its own dedicated AHU, the loss of one suite, while inconvenient, will not shut the department. The same scenario applies to isolation rooms if several of them are each independently ventilated (see Health Building Note 04-01 for further information).

Internal design conditions

4.20 The design conditions selected within patient areas should strike a balance between the comfort requirements of staff and patients, who often have very different levels of clothing and activity.

4.21 Recommendations for the operative temperature and humidity of individual

Providing twin ventilation fans in an AHU delays the time at which the system needs to be completely shut down in the event of a fan failure. It does not in itself provide resilience in terms of delivering healthcare (see Chapter 9 for further guidance).

[HTM 03-01 A – PDF page 32]

determine the overriding minimum requirement for ventilation (see Chapter 8 for specific guidance).

spaces are given in Activity Data A-Sheets (see Chapter 8 for specific requirements). Particular departmental requirements are given in the respective HBN and room data sheets.

Limiting supply air conditions

Minimum fresh air requirements

4.26 For most applications in healthcare buildings, it is the temperature differential between the supply and room air, rather than the actual temperature of the supply air, which is the critical factor. The maximum recommended supply-to-room air temperature differential is:

• summer cooling: 7 K

• winter heating: 10 K.

4.22 In general areas and wards within healthcare premises, odour control is the main reason for providing ventilation. In the absence of other guidance, 10 L/s/person should be taken as the minimum ventilation requirement. Healthcare ventilation systems will normally be “full fresh air” either by natural, mixed mode or mechanical means, with energy recovery from the extracted air.

4.27 Room air humidity should be kept below 70% in order to minimise risks associated with condensation and mould growth. There is no lower limit in unoccupied spaces.

4.23 In non-clinical areas recirculated air systems may be considered. At least 20% of the recirculated air should be fresh. Additional filtration will be required to remove airborne particulate contamination and, if necessary, odours. This will affect running and maintenance costs and, given the high ErP rating of heat recovery devices, it will be necessary to prove that recirculating the air will be more energy- efficient overall.

4.28 Some types of diagnostic imaging technologies require close control of both temperature and humidity as well as the rate of change of conditions to ensure clarity of the image and accuracy of the data generated. The manufacturer’s guidance should be followed.

Air purity

Ultra clean ventilated (UCV) operating theatres use air recirculation. The fresh air requirements of this specific application are given in Chapters 8 and 9.

4.29 In healthcare premises, the standard of filtration will depend on the activities within the occupied spaces. Except for special areas (for example, manufacturing pharmacies), the requirement for aerobiological needs is not stringent and filtration is only required to:

4.24 Smoking is generally not permitted in healthcare premises, so no allowance need be made. Reference should be made to local national policy guidance.

• maintain hygienic conditions for the health and welfare of occupants, or for processes such as centralised food preparation facilities;

• protect finishes, fabrics and furnishings – to reduce redecoration costs;

4.25 In treatment and support areas the overriding requirement may be due to airborne infection control, hazard containment, the stability of specialist equipment or relate to a specific department’s function. Each case should be considered independently in order to

• protect equipment either within the supply air system – to prevent

[HTM 03-01 A – PDF page 33]

4.0 The design and specification process

Maximum noise levels

blocking of coils – or in the space itself to prevent dust accumulation.

4.35 Noise will be generated in an air distribution system by the fan, ductwork fittings, dampers and grilles. The specified maximum noise level will depend on the activities within the occupied spaces.

4.36 Attenuation should be incorporated into the ductwork system or plant arrangement as necessary to reduce noise from fans and plant items in order to achieve the acceptable limits within the rooms at the design airflows.

4.30 Given that almost all viable particles will originate from the occupants of a space and not from the incoming air, dilution is the more important factor aerobiologically. Therefore, for general areas an ISO ePM 2.5 ≥55% filter may be suitable. More critical areas would require an ISO ePM1 ≥50% filter. Efficiency or high-efficiency (EPA or HEPA) filters will only normally be required in ultra-clean systems and designated “clean rooms” (see Chapter 9 for specific information).

4.37 Plantroom noise level from fans when starting up or running should not be greater than 80 dB(A), and should be reduced where the plant is near to departments sensitive to noise.

4.31 In some inner-city areas the local airborne particulate level may be particularly high. In those special cases filters to ISO ePM1 ≥50% may be required to achieve the required indoor air quality. (See Defra’s website and the Specialised Ventilation for Healthcare Society’s (2018) SVHSoc.02 – ‘Change in air filter test and classification standards’.)

Humidity control requirements

4.38 Attention should be given to the reduction of tonal components. High tonal components from air diffusers etc can seriously disturb concentration over longer periods even when the overall noise level is low. Broadband noise causes less annoyance.

4.32 Close control of humidification was originally required for some healthcare applications (for example, operating theatres) in order to control the risk associated with the use of flammable anaesthetic gases. The use of such gases has now ceased.

4.39 The values recommended in Table 1 are for the total noise environment of space. In general, there will be noise transmitted into the space and noise generated within the space. The designer requires knowledge of the total hospital layout and operational policies, to assign acceptance magnitudes to all the possible noise sources, in order to arrive at the correct rating.

4.33 Providing humidification is expensive in terms of plant, running costs and maintenance, and therefore its use should be restricted to where it is necessary for physiological or operational reasons (see Chapter 8 and associated HBNs).

4.40 In Table 1 the overall noise level takes account of all internal and external noise sources. The noise level is the level measured with a sound-level meter in the unoccupied room, taking account of the external noise together with the noise generated by the ventilation system. The ventilation plant design noise level is that generated by the plant alone with no other noise source being considered. The levels suggested make recognised allowance for

4.34 In general terms the humidity within an occupied building or space will naturally float between 30% and 70% RH (relative humidity). Humidity should not be allowed to rise above 70% at any time but there is no need to maintain a background minimum level when the building or space is unoccupied.

[HTM 03-01 A – PDF page 34]

Table 1 Interior noise level

Area Room: overall noise level – dB(A) Ventilation design value – dB(A)

Operating department all rooms including preparation, anaesthetic, scrub and utility, interventional and diagnostic imaging departments – all rooms

UCV operating theatre and adjacent open- plan scrub only –

Treatment rooms Consulting rooms Sleeping areas/rooms Recovery rooms

Sanitary facilities

Aseptic preparation facility

Industrial areas

Circulation waiting areas

Plantrooms

the ingress of environmental noise which will have to be considered in the overall design, that is, in specifying the attenuation of walls, partitions, ceilings, etc.

4.44 CIBSE guide TM52 provides information and formulae for the calculation of air infiltration in buildings. In all cases the requirements of the appropriate section of the current Building Regulations Part L (airtightness minimum requirements) must be met.

Summertime temperatures

4.41 The recommended criterion is measured as the “A” weighted sound pressure level expressed in decibels, which should not be exceeded for more than 10% of the time. See Health Technical Memorandum 08-01 – ‘Acoustics’ for further information.

4.42 The designer should also consider noise escaping to the external environment and this should not be unacceptable to occupants of adjacent buildings.

Calculation of building loads

Air infiltration

4.45 To prevent overheating and avoid the future need for portable room air- conditioners, thermal modelling should be undertaken to ensure that internal temperatures in all areas do not exceed CIBSE Guide A guidance. Thermal modelling should be carried out whether the space is ventilated by natural, mixed mode or mechanical means. The modelling should be undertaken by a competent software user and take into account not only absolute values but also the time component.

4.46 Where thermal modelling indicates internal temperatures will exceed the recommended levels defined in CIBSE Guide A, additional measures should be explored to achieve compliance such as reducing solar and casual gains, improving building fabric performance, etc.

4.43 Air infiltration occurs due to a complex combination of wind pressure, thermal effects, location relative to other features and the construction standard of the building. The infiltration rate is governed by the size and number of doors and other openings in the building envelope and the complexity of internal air paths.

[HTM 03-01 A – PDF page 35]

4.0 The design and specification process

Peak heating load

• method of control of internal conditions;

• fluctuations in internal temperatures.

4.51 When the peak internal loads have been assessed and a suitable allowance made for non-coincidence, the supply temperature can be calculated.

4.47 Peak heating local calculations are necessary on all mechanical supply systems to establish the size of heater-batteries and subsequently the central plant. Note that with the introduction of the requirement to fit energy recovery set out in EU 1253, the heater-battery size will be reduced. If the energy-recovery value is ignored, the heater-battery and its control valve will be oversized and the system when put to use will be unstable and liable to hunt.

4.52 Once the lowest required supply temperature of the air handling unit has been established, and an allowance made for temperature rise through the fan and ductwork (usually 1 K for low pressure systems), the off-plant enthalpy can be established from a psychrometric chart or table.

4.53 The cooling loads for all plant on the chilled water system should be calculated at each of the individual peak times in order to accurately establish the required (diversified) capacity of the chiller.

4.48 Where ventilation systems provide tempered air to spaces which have supplementary low pressure hot water (LPHW) to offset the building fabric losses, the AHU heating load should be calculated based on the external winter design temperature, the design internal air temperature, and the calculated total air volume (including a suitable allowance for leakage).

4.49 Where the ventilation system is the only means of heating a space, an increase in load equivalent to the calculated fabric heat losses from the space should be added to the ventilation load. A check of supply temperature difference should be made. If it exceeds that recommended in paragraph 4.26 the ventilation supply volume should be increased to suit.

Note that as with heating, the introduction of the requirement to fit energy recovery set out in EU 1253 means that the cooling-coil size will be reduced. If the energy-recovery value is ignored, the cooling coil and its control valve will be oversized and the system when put to use will be unstable and liable to hunt.

Peak cooling load

Annual energy consumption

4.50 In addition to the base data of airflow rates and temperatures, when calculating cooling loads, the designer should take into account:

• solar cooling loads;

• surface conduction cooling loads;

4.54 The annual energy consumption of simple heating-only ventilation systems is simple to calculate, based on supply to external air temperature rise, and frequency of occurrence of external temperature data (see CIBSE Guide A).

• internal gain cooling loads;

• air infiltration cooling loads;

• cooling loads due to high limit humidity control;

4.55 Minimum air volumes are usually fixed by the room loads or fresh air requirements; however, the designer may increase airflow to some rooms or zones in order to balance loads, as detailed in paragraphs 4.63–4.68.

[HTM 03-01 A – PDF page 36]

4.56 The method of zoning and control can significantly influence energy consumption.

4.62 In intermittently heated buildings, it is necessary to consider the condensation risk at night set-back conditions as well as during normal operation. Calculation methods for this assessment are given in CIBSE Guide A.

Calculation of plant requirements

4.57 The nature of air-conditioning operation, that is, cooling and reheating for humidity or zonal temperature control, makes prediction of energy consumption very complex. It is imperative that these calculations are performed to ensure optimum energy efficiency.

Air supply volumes

4.63 The minimum air supply volume for a room is determined by the greatest of:

• the minimum fresh air requirement;

• the air required to achieve the room differential pressure and provide open door protection at the key door;

4.58 The concept of load and plant operation charts is outlined in the CIBSE Guide TM52. The method requires the designer to establish the minimum and maximum loads on all zones across the range of external temperatures between winter and summer design conditions. The total coil loads can be calculated taking account of the external air temperature and humidity plus the supply air conditions.

• the minimum supply volume for the room load as determined by the maximum heating or cooling supply temperature differential;

• the desired air-change rate;

• the make-up air for a local extract (for example, cooker hood or LEV system).

Plant sizing

4.64 Once the design airflow has been established, the cross-sectional area of the air-handling unit can be calculated based on values given in Commission Regulation EU 1253/2014.

4.59 When all temperatures/enthalpies for all zones are plotted on the plant operation chart, set points and resetting schedules can be established. From this information, the outputs of individual heaters, coolers and humidifiers can be established at any given external condition. When those loads are computed against annual frequency of occurrence of external conditions as given in CIBSE Guide TM52, the annual energy consumption of individual elements, and thus the air-conditioning system, can be established.

4.65 The fan duty should be calculated by adding the resistances of all elements that contribute to the pressure drop of the index circuit.

4.60 In order to prevent surface condensation occurring, it is necessary to provide enough ventilation to maintain the maximum and ambient dew-point temperature below the lowest surface temperature, the coldest usually being the glazing.

4.66 In order to establish the length of the AHU, it will be necessary to refer to manufacturers’ literature, ensuring all necessary access panels and components are included as detailed in Chapter 9.

4.61 Where this would require excessive ventilation levels, the designer should consider removal of the moisture at the source of the evaporation via an exhaust hood or similar device.

4.67 The designer should ensure that an allowance has been made for “dirty filter” conditions and confirm whether the fan