[SHFN 30 Part A – PDF page 9]

3. Procurement and construction process

Overview

The procurement and construction of a healthcare facility are highly complex processes and require input from a wide variety of sources.

Infection Prevention and Control advice is essential in relation to procurement at the design and planning stage of a project. There is a case for stipulating that Designers for healthcare projects should be able to demonstrate their knowledge and understanding of prevention and control of infection in relation to current guidance. The NHS Project Team needs to confirm this in the course of interviewing Design Teams prior to their appointment.

The specification of building materials, especially surface finishes, healthcare facility equipment etc. should take account of the input from the Project Team who are best placed to ensure that requirements are met, based on risk assessment.

Securing appropriate skills

HAI-SCRIBE aims to manage infection risks through the use of a prevention and control of infection questionnaire, as set out in the Implementation Strategy and Assessment Process section of this guidance. The system highlights the need for a multi-disciplinary team of specialists with appropriate skills to ensure its implementation. This is an essential requirement in terms of the evaluation of the site for development. Where issues such as contaminated land or suspected geological faults arise, specialist advice should be obtained.

[SHFN 30 Part A – PDF page 10]

4. The Planning Process

General overview

In general the stages of a typical healthcare building project are:

 establishing the ‘need to build’ and obtaining agreement from Scottish

Government Health and Social Care Department (SGHSCD) where required;

 appointment of a design team;

 preparing a project brief and carrying out feasibility studies;

 preparing a business case and securing funding;

 developing the design;

 appointment of a contractor;

 construction of the building works;

 handover;

 NHS commissioning of the building i.e. installing loose furnishings and

equipment and training staff;

 occupation.

Business Case process

The preparation of a business case is the process that supports NHS Board submissions for funding of new projects. A business case must convincingly demonstrate that there is a need for a new building, alteration or refurbishment to improve the delivery of healthcare services and that the project is economically sound, financially viable and will be properly managed by the NHS Board.

Details of the business case process can be found in the Scottish Capital Investment Manual which can be found on the Scottish Government Health and Social Care Directorate website at: www.scim.scot.nhs.uk/.

It is important at this stage to identify and involve key people who have a direct interest in the end product including members of the Project Team along with other specialists or departmental heads as required. Specifically at this stage, they need to:

 establish the goals of prevention and control of infection;

 agree the agenda for prevention and control of infection design and

planning;

 communicate prevention and control of infection imperatives throughout

the course of the project, but especially at the initial stages;

 work through conflicting issues to reach an optimum compromise;

[SHFN 30 Part A – PDF page 11]

 determine available resources that can be used and recognise the cost

benefits of not cutting corners on prevention and control of infection issues.

The brief/concept/feasibility study

The planning process starts with the identification of a ‘need’ by the users. The development of this need will involve feasibility studies to enable a design brief or output specification to be developed with consideration given to the following:

 the effect additional beds or departments will have on policies such as

waste management, linen and catering, etc.;

 the effect of extra theatres would have on decontamination services,

workflow, etc.;

 additional specialised areas that will probably require extra infection

prevention and control and laboratory input as well as specialist advice which may not be available in-house e.g. bed space and size of departments, etc., plus engineering services needs such as ultra-clean ventilation, showers, baths, etc.

Space planning

The planning of the building can contribute to reducing the risk of transmission of micro organisms. For example internal and external routes identified for removal of dirty laundry, segregated recyclates and residual wastes, need to be carefully planned.

The location of departments, theatres, wards and rooms needs to take account of good prevention and control of infection practice and ensure that workflows are designed to inhibit infection spread.

Similarly, the detailed design of the building elements can contribute to reducing the risk of transmission of micro organisms e.g. selection of finishing materials for floors, walls and ceilings; designing the ventilation system to inhibit the spread of contamination.

A number of design and layout issues could contribute to the risk of transmission of micro-organisms. For example, the ventilation system needs to inhibit contamination spread rather than contribute to it. Internal and external routes identified for removal of dirty laundry, waste food, healthcare waste, similarly need to be carefully planned.

Concept Design/ Developed Design

Drawings at a scale 1:200 will be available at this stage. They will assist the Project Team in determining clean and dirty traffic flow patterns and confirming room relationships and adjacencies. In addition to verifying compliance with the appropriate Scottish Health Planning Notes (SHPN) or Health Building Notes (HBN), the Project Team should be asked review

[SHFN 30 Part A – PDF page 12]

these plans to comment where their specialist knowledge may assist in the decision-taking process regarding issues such as:

 confirming operational procedures;

 setting out traffic flow patterns;

 establishing baseline and future staffing profiles;

 establishing baseline and future revenue budgets;

 establishing equipment requirements;

 providing equipment bays;

 strategy for equipping;

 procurement and selection of furnishings and equipment;

 missing rooms;

 appropriate placing and accessibility of hand hygiene facilities;

 ventilation systems including the level of filtration where specialised

ventilation is required;

 water supply, heating and plumbing;

 surface finishes: ceilings, walls, work surfaces, floor coverings and

furnishings;

 storage (including waste collection points and delivery areas) and DSRs

equipment cleaning areas;

 ancillary areas;

 single rooms;

 isolation rooms;

 changing facilities;

 providing flexibility of space: e.g. to allow for cohort nursing (a full

glossary of terms can be found in Appendix 2);

 lifts;

 pneumatic delivery systems.

Particular issues to be addressed by the Project Team

The Project Team must ensure that prevention and control of infection implications are not compromised by reducing standards set by NHS guidance or by overcrowding in clinical areas and they should communicate their views to the Project Manager for further action.

Technical design

Drawings at a scale of 1:50 will be available at this stage confirming more precise detail such as the number and location of sanitary fittings, equipment, furnishings, etc.

[SHFN 30 Part A – PDF page 13]

The Project Manager, with advice from the Project Team, will also need to consider the prevention and control of infection issues around:

 workflow;

 wash-hand basins: types, numbers and location;

 fixtures/fittings/flooring;

 waste water and sewage/body fluid disposal;

 ventilation;

 heating and lighting;

 water systems;

 suction/medical gases;

 storage systems;

 ward kitchens/pantry.

NHS guidance on the design and/or installation of the above can be found in planning notes and technical memoranda available on the HFS website.

To assist with understanding and mitigating risks associated with bacterial contamination of water distribution and supply systems, it is recommended that the NHS Board should have in place a Water Safety Plan (WSP) as outlined in SHTM 04-01 providing a risk management approach to the microbiological safety of water and establishing good practice in local water distribution and supply. Those organisations with robust water management policies for Legionella will already have in place much of the integral requirements for delivering a WSP.

Note: Refer to Health Protection Scotland Guidance for neonatal units (NNUs) (levels 1, 2 & 3), adult and paediatric intensive care units (ICUs) in Scotland to minimise the risk of Pseudomonas aeruginosa infection from water.

[SHFN 30 Part A – PDF page 14]

Planning process Time Period Issues to consider

Process and corresponding RIBA Plan of Work Stage

Waste Cleaning/disinfection/ sterilisation

1:Preparation and Brief 1 in 200 (some preliminary designs) 1:500

0:Strategic Definition Space Catering Specialist area Engineering facilities Laundry

1 in 200 draft activity data sheets equipment lists usually wish lists

2:Concept Design/3:Developed Design

Storage (linen, waste, patient equipment, domestic equipment) Ancillary areas Changing facilities

Design Stage

Lifts Pneumatic delivery systems Patient placement Single rooms Isolation rooms Outline business case

1 in 50: fixtures and fitting (fixed items Group 1)

3:Developed Design/ 4:Technical Design (Depending on Procurement Route)

Ventilation Heat/light Water systems Sewerage Vacuum

Wash-hand basins Storage systems Ward kitchens Workflow Fixture and fittings

Full business case

Tender

Procurement

5:Contract

Construction Equipment Space Specialist equipment

6:Handover & close-out

Delivery

7: In use Check for any changes made to original agreement/plan

Table 1: Project Development Chart

[SHFN 30 Part A – PDF page 15]

Typical Key Stages of Project Team Input

1. The Brief/Concept/Feasibility study: Project Team should contribute to the review of operational policies and procedures, such as:

 adding beds to ward area may require an additional sluice or single rooms;  adding extra theatres will need a review of decontamination services for instruments.  additional specialised areas will need extra prevention and control of infection input;  traffic flows. 2. Concept design/developed design: Sketch plans at 1:200 scale available at this stage, the Project Team needs to give a broad view of prevention and control of infection issues e.g. rooms missing, wards without ancillary areas such as disposal rooms or dirty utility.

3. Technical design: (1/50 designs – early period) There is a need to finalise locations of rooms for correct workflows/prevention and control of infection practice, i.e. wards, theatres.

4. Technical design: (1/50 designs – later period) Need to discuss finer details within rooms: location and type of fixtures and fittings, e.g. hand-wash basins/types of basins; airflows in theatres, flooring.

5. Construction: A designated individual should be appointed particularly if the new build is attached to an existing healthcare building, to ensure that control measures prevent risks to patients.

6. Equipment: decisions on equipment should be made as an ongoing process, but it is at this stage that it will be seen that previous equipment ‘wish-lists’ may not fit the rooms/departments or are now outdated. It is important that Project Teams also have input during this period (especially if it is a PFI/PPP build).

7. Commission/equipping: Project Teams must have input during this stage if costly and dangerous mistakes are to be avoided.

8. In use: this is an important stage in which lessons learnt can be highlighted for future projects, both within NHS Boards and throughout NHSScotland. Post-project evaluation is mandatory and results should be available to other NHS Boards.

Table 2: The Key Stages of the Planning Process and examples of Project Team input

[SHFN 30 Part A – PDF page 16]

Accommodation areas/internal

Examples: Key issues and areas to be considered

environment/general services

Accommodation areas

Bed areas: Single-bed rooms.

Placement of patients at high-risk. En-suite facilities. Doors on bays.

Dirty utility/clean utility. Standardisation of rooms/choice of equipment. Appropriate storage. Space.

Domestic services room. Space, adequate sinks and storage.

Workflow/layout. Standard ward area versus specialised area.

Bed planning. Elective. Emergency.

Linen services and facilities. Storage, transport and handling.

Catering/kitchen areas. Furnishing, fixtures and fittings plus workflow crucial for HACCP. Commercial systems e.g. cook-chill versus in-house systems.

Single rooms versus 4/6 bed bays.

Intensive care unit/High dependency unit (ITU/HDU).

Clinical wash-hand basins. Number dependent on room types. Correct wash hand basin specifications. Facilities to ensure compliance with hand hygiene. Located to encourage staff use.

Staff change areas/storage of uniforms. Type of uniform provided inline with national uniform policy.

Operational policy dictated by choice of decontamination strategy.

Decontamination facilities. Central Decontamination Unit/Local Decontamination Unit (CDU/LDU).

Purchase versus hire. Cleaning/disinfection-requirement. Enough equipment available.

Equipment. Bed/mattresses. Endoscopes/instruments. Patient specific. Area for Decontamination facilities.

Table 3: Infection control issues for the Project Team to consider in the Capital Planning Process.