SHFN 30 Part A: Manual

Information for Design Teams, Construction

Teams, Estates & Facilities and Infection

Prevention & Control Teams

October 2014

[SHFN 30 Part A – PDF page 2]

Contents

page

Acknowledgements .......................................................................................... 4 1. Introduction and scope .......................................................................... 5 Questionsets and Pro-formas ................................................................... 5 2. Risk assessment .................................................................................... 7 Identifying risk .......................................................................................... 7 3. Procurement and construction process ............................................... 9 Overview .................................................................................................. 9 Securing appropriate skills ....................................................................... 9 4. The Planning Process .......................................................................... 10 General overview ................................................................................... 10 Business Case process .......................................................................... 10 The brief/concept/feasibility study .......................................................... 11 Space planning ....................................................................................... 11 4.10 Concept Design/ Developed Design ....................................................... 11 4.11 Particular issues to be addressed by the Project Team ......................... 12 4.15 Design Development stages ................................................................... 18 4.45 Sanitary fittings ....................................................................................... 23 4.84 Soft furnishings ....................................................................................... 28 4.90 Equipment .............................................................................................. 29 4.92 Procurement Stages ............................................................................... 29 4.105 Delivery/Commissioning Stage ............................................................... 32 4.107 Post Project Evaluation .......................................................................... 33 5. Typical rooms: purpose and content.................................................. 36 Generic rooms ........................................................................................ 36 6. Engineering services ........................................................................... 50 Heat emitters and temperature control ................................................... 50 Ventilation ............................................................................................... 51 6.15 Hot and cold water systems ................................................................... 52 6.30 Electrical services ................................................................................... 54 6.36 Wastewater and sanitation ..................................................................... 55 6.44 Medical gases and vacuum systems ...................................................... 55 6.45 Pneumatic air tube transport systems .................................................... 56

[SHFN 30 Part A – PDF page 3]

6.47 Computer equipment .............................................................................. 56 7. Importance of maintenance ................................................................. 57 Access for maintenance ......................................................................... 57 8. Demolition ............................................................................................. 58 Decontamination of buildings and equipment ......................................... 58 Effect upon adjacent healthcare premises.............................................. 58 Planning for demolition works ................................................................. 58 Appendix 1: Equipment groups ..................................................................... 60 Appendix 2: Glossary ..................................................................................... 61 Appendix 3: Infection control in Community Care facilities, Mental

Health units, custodial facilities and accommodation for patients with learning disabilities. ...................................................... 64 References....................................................................................................... 66

Disclaimer

The contents of this document are provided by way of general guidance

only at the time of its publication. Any party making any use thereof or placing any reliance thereon shall do so only upon exercise of that party’s

own judgement as to the adequacy of the contents in the particular circumstances of its use and application. No warranty is given as to the accuracy, relevance or completeness of the contents of this document and

Health Facilities Scotland, a Division of NHS National Services Scotland,

shall have no responsibility for any errors in or omissions therefrom, or

any use made of, or reliance placed upon, any of the contents of this

document.

[SHFN 30 Part A – PDF page 4]

Acknowledgements

Health Facilities Scotland would like to thank the SHFN30/HAI-SCRIBE Steering Group for their efforts in producing Part A of SHFN 30. Their input has been gratefully appreciated.

Thanks are also due to the Pilot Study Group for their assistance with trialling the process.

Finally, HFS would take this opportunity to express gratitude to everyone who contributed to the consultation phase of completing this document.

[SHFN 30 Part A – PDF page 5]

1. Introduction and scope

Note: The Project Team referred to throughout the document is the team of NHS staff assembled to fulfil the role of ‘The Client’ and to manage the delivery of the project. Through the various stages of the project it may include NHS Project Managers, Clinicians, Estates staff and Infection Prevention and Control specialists.

This guidance consists of two parts:

 SHFN 30 Part A: Manual: This provides Built Environment Infection

Prevention and Control information for Design Teams, Construction Teams, Infection Prevention and Control Teams and Estates & Facilities Teams;

 SHFN 30 Part B: HAI-SCRIBE: comprises the Implementation and

Assessment Process which describes the process for identifying, eliminating or managing built environment infection control risks. It also describes the key personnel involved in this process together with their roles and responsibilities and the fact that collaboration among all those involved in the process is pivotal to its success.

It is envisaged that participants will use the HAI-SCRIBE document (SHFN 30 Part B) to help them identify, manage and record built environment infection control risks. The same Group will use the Manual document (SHFN 30 Part A) for sourcing information to help in the decision making process so that identified risks can either be eliminated or successfully managed.

Questionsets and Pro-formas

Arrangements have been made to make available on the HFS Website, separately, the portfolio of Questionsets and Pro-formas for each stage of project development suitable for photocopying and application to individual projects as appropriate.

Additionally, compliance with these guidance documents can ensure that there are facilities in place to help fulfil the mandatory requirements outlined in the National Infection Prevention and Control Manual produced by Health Protection Scotland.

The Project Team members and contributors from various disciplines will take different advice from the guidance and it is the ensuing debate and analysis which will improve the quality of the delivered facility.

This Manual is intended to provide an insight to the key factors within the built environment which can impact on the prevention and control of infection and will also be useful as a guide for best practice in existing healthcare facilities.

[SHFN 30 Part A – PDF page 6]

In the future due to changing patient populations and changing healthcare needs there may be different factors to be considered when planning accommodation. These include the increase in the ageing population, caring for Bariatric patients, and more focus on community-based care.

The design of the built healthcare environment plays a fundamental role in infection prevention and control. The increasing threat of antimicrobial resistant organisms and other emerging pathogens in healthcare may present new and more difficult challenges in future healthcare facility design and planning efforts.

A system of recording projects, signing-off plans and meeting notes by all participating parties will be needed. The completion of questionsets in the ‘Implementation strategy and assessment process’ part of this guidance will fulfil most of this requirement. It is important that the Project Team sign-off each stage of the project having taken advice from Estates & Facilities, Infection Prevention & Control representatives and other appropriate disciplines.

Note: To manage or mitigate infection risks requires knowledge from many sources. Input from the Project Team will not only include Infection Prevention and Control Teams (IPCT). Estates and Facilities Teams and Design and Construction Teams also have important roles to play in managing or mitigating these risks. However, it is not expected that any single group will possess full knowledge or experience of another’s discipline. It is expected, therefore, that there will be an ongoing liaison during each stage of development where appropriate specialist knowledge from all sources of relevant expertise can be derived and incorporated into the design team appointments, project briefing, contract conditions, specification and quality control of construction and maintenance.

[SHFN 30 Part A – PDF page 7]

2. Risk assessment

Identifying risk

The time taken to plan or refurbish a healthcare facility can vary from a relatively short period in the case of urgent renovation, to as long as three or four years for a major capital build project. It is therefore important that all members of the Project Team are notified of capital bids at the earliest opportunity. The Infection Prevention and Control Team need to be involved in the first planning meetings. Most meetings thereafter will require some input from them.

To avoid mistakes and pitfalls the Project Team must consider issues including:

 how will the product, equipment, room or premises be used?

 what possible solutions are available?

 what are the budgetary limitations?

 which prevention and control of infection principles apply?

 which external regulations apply?

 what does the evidence suggest in relation to the specific context?

 what are the laws governing the project?

 what standards and guidelines apply from architectural and engineering

bodies, Health Facilities Scotland, local and national government departments and accrediting agencies?

 which product or design best balances the infection prevention and

control requirements with employee and patient safety and satisfaction, and cost constraints?

 what legal requirements are required under Health & Safety law?

Common pitfalls

Common pitfalls arise from a number of pressures, for example, the pressure to choose the cheapest products or design.

Note: The best products or designs may be more expensive initially but in the long term they will probably realise cost benefits as they may prevent outbreaks, or they may last longer and require less maintenance and be more durable.

Assessing risk

[SHFN 30 Part A – PDF page 8]

Designing premises that prevent the transmission of infectious agents to patients, healthcare workers and visitors is an important component of prevention and control of infection programme or plan. Outbreaks of infection have been related to the design, plan, layout, function and/or finish of the built environment. Thus, risk assessment is a fundamental imperative in the planning and design stages of a healthcare facility. It is often overlooked or compromised throughout the lifecycle of the project. It has not been unknown for the clinical outcome of a well- intentioned risk assessment to create other problems. There is therefore a need to verify that these outcomes are themselves risk assessed. Disseminating good specialist advice relating to Infection Prevention and Control throughout all phases of construction and renovation projects will reduce risks. There will be instances when it is not possible to achieve the ideal. This applies particularly to refurbishment projects within existing accommodation and is often related to spatial issues. In these circumstances the aim should be to make the best use of available facilities.

Note: Failure to assess properly risks affecting prevention and control of infection can lead to expensive redesign later and expose the patient and healthcare worker to unnecessary risks. It is important to bear in mind that any control measures put in place to prevent the spread of infection during a building stage and subsequent maintenance of any project take into account the effect that they would have on patients and staff in the surrounding areas.

Source

Building professionals must be aware of the risks associated with construction projects and that the environment can be a reservoir for potentially infectious agents. The source is the person, animal, object or substance from which an infectious agent is transmitted to a host. The immediate healthcare environment can be a potential reservoir of micro- organisms and source of infection or contamination, therefore, Designers and Planners need to consider eliminating potential sources of infection by practising good design, for example:

 adequate storage facilities;

 choice of materials, avoiding unnecessary surfaces that may become

reservoirs for infectious agents;

 ensuring materials and surfaces can be cleaned and maintained.