HTM 03-01 A: _Hlk36746534 / 1.0 Introduction / 2.0 The user requirements / 3.0 Legal requirements – applicable legislation / 4.0 The design and specification process – Project brief / 4.0 The design and specification process – Derogations and alternative design strategies / 4.0 The design and specification process – Resilience and diversity / 4.0 The design and specification process – Refurbishment of existing facilities and fitting out shell schemes / 4.0 The design and specification process – Computer-aided design (CAD) and building information modelling (BIM) / 4.0 The design and specification process – 5.0 Ventilation strategies / 6.0 Energy control strategies / 7.0 Environmental control / 8.0 Specific healthcare department requirements – General considerations / 8.0 Specific healthcare department requirements – Operating department / 8.0 Specific healthcare department requirements – Ultra-clean ventilation system / 8.0 Specific healthcare department requirements – Barn and semi-barn theatres / 8.0 Specific healthcare department requirements – Hybrid theatres / 8.0 Specific healthcare department requirements – Interventional imaging suites / 8.0 Specific healthcare department requirements – Other application-specific design guidance / 8.0 Specific healthcare department requirements – Hydrotherapy: general requirements / 8.0 Specific healthcare department requirements – Plantroom ventilation / 9.0 Equipment selection factors – General requirements / 9.0 Equipment selection factors – Supply AHUs and associated extract units (pages 95–102) / 9.0 Equipment selection factors – Supply AHUs and associated extract units (pages 103–110) / 9.0 Equipment selection factors – Supply AHUs and associated extract units (pages 111–112) / 9.0 Equipment selection factors – Distributed air-conditioning elements / 9.0 Equipment selection factors – AHUs: automatic control / 9.0 Equipment selection factors – Local exhaust ventilation (LEV) / 10.0 Installation standards / 11.0 Commissioning systems / 12.0 Acceptance testing: validation – Appointment of validator / 12.0 Acceptance testing: validation – Design proposal review / 12.0 Acceptance testing: validation – Permeability testing / 12.0 Acceptance testing: validation – UCV canopy leakage tests / 12.0 Acceptance testing: validation – Vertical flow UCV canopy air velocity tests / 12.0 Acceptance testing: validation – UCV canopy entrainment test / 12.0 Acceptance testing: validation – UCV terminal control system checks / 12.0 Acceptance testing: validation – UCV theatre microbiological tests / 12.0 Acceptance testing: validation – Radiopharmacy aseptic preparation facilities / 13.0 Information / Appendix 1: Typical AHU plant layouts / Appendix 2: Summary of design conditions / Appendix 3: Hierarchy of cleanliness / Appendix 4: Leakage flows in m3/s through closed door gaps / Appendix 5: Recommended airflow rates in m3/s through a doorway between rooms of different cleanliness to control cross-contamination / Appendix 6: Typical approximate pressures in an operating suite when a given door is open / Appendix 7: Operating suite design logic / Appendix 7: Operating suite design logic – Standard layout 1 – Two-corridor conventional operating suite with “lay-up” prep / Appendix 7: Operating suite design logic – Standard layout 2 – two-corridor UCV operating suite with SPS prep / Appendix 7: Operating suite design logic – Standard layout 3 – single-corridor conventional operating suite with “lay-up” prep / Appendix 7: Operating suite design logic – Standard layout 4 – single-corridor UCV operating suite with SPS prep / Appendix 7: Operating suite design logic – Standard layout 5 – (ex HTM 2025 Plan 1b): single-corridor conventional operating suite with “lay-up” prep / Appendix 7: Operating suite design logic – Standard layout 6 – (ex HTM 2025 Plan 1a): single-corridor UCV operating suite with SPS prep / Appendix 7: Operating suite design logic – Standard layout 7 – (ex HTM 2025 Plan 5b): two-corridor conventional operating suite with “lay-up” prep / Appendix 7: Operating suite design logic – Standard layout 8 – (ex HTM 2025 Plan 5a): two-corridor UCV operating suite with SPS prep / Appendix 7: Operating suite design logic – General / Appendix 7: Operating suite design logic – Peripheral room type / Appendix 7: Operating suite design logic – Air-movement control in peripheral rooms / Appendix 7: Operating suite design logic – Door opening / Appendix 7: Operating suite design logic – Door leakage flows / Appendix 7: Operating suite design logic – Relief of excess air from operating theatre when all doors are closed / Appendix 7: Operating suite design logic (pages 169–176) / Appendix 7: Operating suite design logic (pages 177–184) / Appendix 7: Operating suite design logic (pages 185–192) / Appendix 7: Operating suite design logic (pages 193–200) / Appendix 9: Design of air-movement control scheme for anaesthetic room
[HTM 03-01 A – PDF page 203]
Appendix 10: Example cause-and-effect check-sheets
Appendix 10: Example cause-and- effect check-sheets
Example cause-and-effect check-sheet for general theatre or imaging suite
Site Date
Area served System ID
Test AHU Checks Y/N TCP Indication Y/N
AHU Off Supply and extract dampers closed Red
Supply damper open Extract damper open Red
Switch AHU “On”
Supply fan start and run Extract fan start and run Red
Prove airflow Green
Switch AHU to “Set Back” Supply fan slows Extract fan slows Red
Switch AHU to Operational speed
Supply fan speeds up Extract fan speeds up Green
Yellow display information
End of day 10 minute warning that system will switch to “Set Back” (Not all TCPs have this facility)
box
Do nothing System goes to “Set back” Red
Reset to full speed Green
Yellow display information
End of day 10 minute warning that system will switch to “Set Back” (Not all TCPs have this facility)
box
Press “Continue” System stays at full speed for 1 hour Green
Supply fan fail System shuts down Red
Reset system to normal Green
Yellow display information
Extract fan fails Warning on TCP and BMS. AHU locks out if fault not rectified by following day
box
Reset system to normal Green
Theatre/Imaging room temperature to be stable at 20°C at the start of this test.
Set temp:
Reduce set point temperature to lowest possible on TCP
Chiller battery valve opens fully Record min temp reached and time taken to stabilise.
oC Measured: oC Ind (TCP) oC Time taken mins
Set temp:
Increase set point temperature to highest possible on TCP
Heater battery valve opens fully. Record max temp reached and time taken to stabilise.
oC Measured: oC Ind (TCP) oC Time taken mins
Reset set point to 20oC Green
Red
Switch AHU “Off” Extract fan stops Supply fan stops Extract damper closes Supply damper closes
[HTM 03-01 A – PDF page 204]
Example cause-and-effect check-sheet for ultra-clean theatres
Site Date
Area served System ID
Test AHU/UCV Checks Y/N TCP Indication Y/N
AHU Off Supply and extract dampers closed Red
Supply damper open Extract damper open Red
Switch AHU “On”
Supply fan start and run Extract fan start and run Red
Prove airflow UCV "Off" Red
Switch AHU to “Set Back” Supply fan slows Extract fan slows Red
Switch AHU to Operational speed
Supply fan speeds up Extract fan speeds up –
AHU at operational speed Switch UCV on in “Low speed” Amber = “Conventional
Theatre mode”
Press “UCV mode” UCV goes to “Full speed” Green “UCV Theatre Mode”
UCV goes to “Low speed” Amber
Press ”Conventional Theatre mode”
Switch AHU to “Set Back” UCV goes to “Low speed” or “Off” Red
Reset system to normal UCV stays in “Low speed” Amber
Switch UCV “Off” UCV fans stop Red
Reset system to normal with UCV at full speed Green
Fail each UCV quadrant fan in turn and Coanda fans (4 + 2) Red
Reset system to normal with UCV at full speed Green
Trigger HEPA filter high pressure switch Green plus Blue light
Yellow display information
box
End of day 10 minute warning that system will switch to “Set Back” or “Off” (Not all Theatre Control Panels have this facility)
Do nothing AHU & UCV go to “Set back” or “Off” Red
Reset to full speed including UCV Green
Yellow display information
box
End of day 10 minute warning that system will switch to “Set Back” or ”Off” (Not all Theatre Control Panels have this facility)
Press “Continue” System stays at full speed for 1 hour Green
Supply fan fails System shuts down. UCV to “Low speed or Off” Red
Reset system to normal Green
Yellow display information
box
Extract fan fails Warning on TCP and BMS.AHU locks out if fault not rectified by following day
Reset system to normal and UCV to full speed Green
[HTM 03-01 A – PDF page 205]
Appendix 10: Example cause-and-effect check-sheets
Site Date
Area served System ID
Test AHU/UCV Checks Y/N TCP Indication Y/N
Theatre temperature to be stable at 20°C at the start of this test.
Chiller battery valve opens fully
Reduce set point temperature to lowest possible on TCP
Record min temp reached and time taken to stabilise
Set temp: oC Measured: oC Ind (TP) oC Time taken mins
Heater battery valve opens fully
Increase set point temperature to highest possible on TCP
Record max temp reached and time taken to stabilise
Set temp: oC Measured: oC Ind (TP) oC Time taken mins
Reset set point to 20ºC Green
Red
Switch AHU “Off” Extract fan stops Supply fan stops Extract damper closes Supply damper closes UCV drops to “Set back”
Note any additional tests or checks below