Home › England (NHS England estates) › HTM 03-01 A › _Hlk36746534 / 1.0 Introduction / 2.0 The user requirements / 3.0 Legal requirements – applicable legislation / 4.0 The design and specification process – Project brief / 4.0 The design and specification process – Derogations and alternative design strategies / 4.0 The design and specification process – Resilience and diversity / 4.0 The design and specification process – Refurbishment of existing facilities and fitting out shell schemes / 4.0 The design and specification process – Computer-aided design (CAD) and building information modelling (BIM) / 4.0 The design and specification process – 5.0 Ventilation strategies / 6.0 Energy control strategies / 7.0 Environmental control / 8.0 Specific healthcare department requirements – General considerations / 8.0 Specific healthcare department requirements – Operating department / 8.0 Specific healthcare department requirements – Ultra-clean ventilation system / 8.0 Specific healthcare department requirements – Barn and semi-barn theatres / 8.0 Specific healthcare department requirements – Hybrid theatres / 8.0 Specific healthcare department requirements – Interventional imaging suites / 8.0 Specific healthcare department requirements – Other application-specific design guidance / 8.0 Specific healthcare department requirements – Hydrotherapy: general requirements / 8.0 Specific healthcare department requirements – Plantroom ventilation / 9.0 Equipment selection factors – General requirements / 9.0 Equipment selection factors – Supply AHUs and associated extract units (pages 95–102) / 9.0 Equipment selection factors – Supply AHUs and associated extract units (pages 103–110) / 9.0 Equipment selection factors – Supply AHUs and associated extract units (pages 111–112) / 9.0 Equipment selection factors – Distributed air-conditioning elements / 9.0 Equipment selection factors – AHUs: automatic control / 9.0 Equipment selection factors – Local exhaust ventilation (LEV) / 10.0 Installation standards / 11.0 Commissioning systems / 12.0 Acceptance testing: validation – Appointment of validator / 12.0 Acceptance testing: validation – Design proposal review / 12.0 Acceptance testing: validation – Permeability testing / 12.0 Acceptance testing: validation – UCV canopy leakage tests / 12.0 Acceptance testing: validation – Vertical flow UCV canopy air velocity tests / 12.0 Acceptance testing: validation – UCV canopy entrainment test / 12.0 Acceptance testing: validation – UCV terminal control system checks / 12.0 Acceptance testing: validation – UCV theatre microbiological tests / 12.0 Acceptance testing: validation – Radiopharmacy aseptic preparation facilities / 13.0 Information / Appendix 1: Typical AHU plant layouts / Appendix 2: Summary of design conditions / Appendix 3: Hierarchy of cleanliness / Appendix 4: Leakage flows in m3/s through closed door gaps / Appendix 5: Recommended airflow rates in m3/s through a doorway between rooms of different cleanliness to control cross-contamination / Appendix 6: Typical approximate pressures in an operating suite when a given door is open / Appendix 7: Operating suite design logic / Appendix 7: Operating suite design logic – Standard layout 1 – Two-corridor conventional operating suite with “lay-up” prep / Appendix 7: Operating suite design logic – Standard layout 2 – two-corridor UCV operating suite with SPS prep / Appendix 7: Operating suite design logic – Standard layout 3 – single-corridor conventional operating suite with “lay-up” prep / Appendix 7: Operating suite design logic – Standard layout 4 – single-corridor UCV operating suite with SPS prep / Appendix 7: Operating suite design logic – Standard layout 5 – (ex HTM 2025 Plan 1b): single-corridor conventional operating suite with “lay-up” prep / Appendix 7: Operating suite design logic – Standard layout 6 – (ex HTM 2025 Plan 1a): single-corridor UCV operating suite with SPS prep / Appendix 7: Operating suite design logic – Standard layout 7 – (ex HTM 2025 Plan 5b): two-corridor conventional operating suite with “lay-up” prep / Appendix 7: Operating suite design logic – Standard layout 8 – (ex HTM 2025 Plan 5a): two-corridor UCV operating suite with SPS prep / Appendix 7: Operating suite design logic – General / Appendix 7: Operating suite design logic – Peripheral room type / Appendix 7: Operating suite design logic – Air-movement control in peripheral rooms / Appendix 7: Operating suite design logic – Door opening / Appendix 7: Operating suite design logic – Door leakage flows / Appendix 7: Operating suite design logic – Relief of excess air from operating theatre when all doors are closed / Appendix 7: Operating suite design logic (pages 169–176) / Appendix 7: Operating suite design logic (pages 177–184) / Appendix 7: Operating suite design logic (pages 185–192) / Appendix 7: Operating suite design logic (pages 193–200) / Appendix 9: Design of air-movement control scheme for anaesthetic room

HTM 03-01 A: _Hlk36746534 / 1.0 Introduction / 2.0 The user requirements / 3.0 Legal requirements – applicable legislation / 4.0 The design and specification process – Project brief / 4.0 The design and specification process – Derogations and alternative design strategies / 4.0 The design and specification process – Resilience and diversity / 4.0 The design and specification process – Refurbishment of existing facilities and fitting out shell schemes / 4.0 The design and specification process – Computer-aided design (CAD) and building information modelling (BIM) / 4.0 The design and specification process – 5.0 Ventilation strategies / 6.0 Energy control strategies / 7.0 Environmental control / 8.0 Specific healthcare department requirements – General considerations / 8.0 Specific healthcare department requirements – Operating department / 8.0 Specific healthcare department requirements – Ultra-clean ventilation system / 8.0 Specific healthcare department requirements – Barn and semi-barn theatres / 8.0 Specific healthcare department requirements – Hybrid theatres / 8.0 Specific healthcare department requirements – Interventional imaging suites / 8.0 Specific healthcare department requirements – Other application-specific design guidance / 8.0 Specific healthcare department requirements – Hydrotherapy: general requirements / 8.0 Specific healthcare department requirements – Plantroom ventilation / 9.0 Equipment selection factors – General requirements / 9.0 Equipment selection factors – Supply AHUs and associated extract units (pages 95–102) / 9.0 Equipment selection factors – Supply AHUs and associated extract units (pages 103–110) / 9.0 Equipment selection factors – Supply AHUs and associated extract units (pages 111–112) / 9.0 Equipment selection factors – Distributed air-conditioning elements / 9.0 Equipment selection factors – AHUs: automatic control / 9.0 Equipment selection factors – Local exhaust ventilation (LEV) / 10.0 Installation standards / 11.0 Commissioning systems / 12.0 Acceptance testing: validation – Appointment of validator / 12.0 Acceptance testing: validation – Design proposal review / 12.0 Acceptance testing: validation – Permeability testing / 12.0 Acceptance testing: validation – UCV canopy leakage tests / 12.0 Acceptance testing: validation – Vertical flow UCV canopy air velocity tests / 12.0 Acceptance testing: validation – UCV canopy entrainment test / 12.0 Acceptance testing: validation – UCV terminal control system checks / 12.0 Acceptance testing: validation – UCV theatre microbiological tests / 12.0 Acceptance testing: validation – Radiopharmacy aseptic preparation facilities / 13.0 Information / Appendix 1: Typical AHU plant layouts / Appendix 2: Summary of design conditions / Appendix 3: Hierarchy of cleanliness / Appendix 4: Leakage flows in m3/s through closed door gaps / Appendix 5: Recommended airflow rates in m3/s through a doorway between rooms of different cleanliness to control cross-contamination / Appendix 6: Typical approximate pressures in an operating suite when a given door is open / Appendix 7: Operating suite design logic / Appendix 7: Operating suite design logic – Standard layout 1 – Two-corridor conventional operating suite with “lay-up” prep / Appendix 7: Operating suite design logic – Standard layout 2 – two-corridor UCV operating suite with SPS prep / Appendix 7: Operating suite design logic – Standard layout 3 – single-corridor conventional operating suite with “lay-up” prep / Appendix 7: Operating suite design logic – Standard layout 4 – single-corridor UCV operating suite with SPS prep / Appendix 7: Operating suite design logic – Standard layout 5 – (ex HTM 2025 Plan 1b): single-corridor conventional operating suite with “lay-up” prep / Appendix 7: Operating suite design logic – Standard layout 6 – (ex HTM 2025 Plan 1a): single-corridor UCV operating suite with SPS prep / Appendix 7: Operating suite design logic – Standard layout 7 – (ex HTM 2025 Plan 5b): two-corridor conventional operating suite with “lay-up” prep / Appendix 7: Operating suite design logic – Standard layout 8 – (ex HTM 2025 Plan 5a): two-corridor UCV operating suite with SPS prep / Appendix 7: Operating suite design logic – General / Appendix 7: Operating suite design logic – Peripheral room type / Appendix 7: Operating suite design logic – Air-movement control in peripheral rooms / Appendix 7: Operating suite design logic – Door opening / Appendix 7: Operating suite design logic – Door leakage flows / Appendix 7: Operating suite design logic – Relief of excess air from operating theatre when all doors are closed / Appendix 7: Operating suite design logic (pages 169–176) / Appendix 7: Operating suite design logic (pages 177–184) / Appendix 7: Operating suite design logic (pages 185–192) / Appendix 7: Operating suite design logic (pages 193–200) / Appendix 9: Design of air-movement control scheme for anaesthetic room

Specialised ventilation for healthcare premises Part A: The concept, design, specification, installation and acceptance testing of healthcare ventilation systems · PDF pages 203–205 of 213 · Source file: HTM0301-PartA-accessible-F6.pdf
Unofficial text extract. Tables and figures may be incomplete. Authoritative version: official PDF from NHS England.

[HTM 03-01 A – PDF page 203]

Appendix 10: Example cause-and-effect check-sheets

Appendix 10: Example cause-and- effect check-sheets

Example cause-and-effect check-sheet for general theatre or imaging suite

Site Date

Area served System ID

Test AHU Checks Y/N TCP Indication Y/N

AHU Off Supply and extract dampers closed Red

Supply damper open Extract damper open Red

Switch AHU “On”

Supply fan start and run Extract fan start and run Red

Prove airflow Green

Switch AHU to “Set Back” Supply fan slows Extract fan slows Red

Switch AHU to Operational speed

Supply fan speeds up Extract fan speeds up Green

Yellow display information

End of day 10 minute warning that system will switch to “Set Back” (Not all TCPs have this facility)

box

Do nothing System goes to “Set back” Red

Reset to full speed Green

Yellow display information

End of day 10 minute warning that system will switch to “Set Back” (Not all TCPs have this facility)

box

Press “Continue” System stays at full speed for 1 hour Green

Supply fan fail System shuts down Red

Reset system to normal Green

Yellow display information

Extract fan fails Warning on TCP and BMS. AHU locks out if fault not rectified by following day

box

Reset system to normal Green

Theatre/Imaging room temperature to be stable at 20°C at the start of this test.

Set temp:

Reduce set point temperature to lowest possible on TCP

Chiller battery valve opens fully Record min temp reached and time taken to stabilise.

oC Measured: oC Ind (TCP) oC Time taken mins

Set temp:

Increase set point temperature to highest possible on TCP

Heater battery valve opens fully. Record max temp reached and time taken to stabilise.

oC Measured: oC Ind (TCP) oC Time taken mins

Reset set point to 20oC Green

Red

Switch AHU “Off” Extract fan stops Supply fan stops Extract damper closes Supply damper closes

[HTM 03-01 A – PDF page 204]

Example cause-and-effect check-sheet for ultra-clean theatres

Site Date

Area served System ID

Test AHU/UCV Checks Y/N TCP Indication Y/N

AHU Off Supply and extract dampers closed Red

Supply damper open Extract damper open Red

Switch AHU “On”

Supply fan start and run Extract fan start and run Red

Prove airflow UCV "Off" Red

Switch AHU to “Set Back” Supply fan slows Extract fan slows Red

Switch AHU to Operational speed

Supply fan speeds up Extract fan speeds up –

AHU at operational speed Switch UCV on in “Low speed” Amber = “Conventional

Theatre mode”

Press “UCV mode” UCV goes to “Full speed” Green “UCV Theatre Mode”

UCV goes to “Low speed” Amber

Press ”Conventional Theatre mode”

Switch AHU to “Set Back” UCV goes to “Low speed” or “Off” Red

Reset system to normal UCV stays in “Low speed” Amber

Switch UCV “Off” UCV fans stop Red

Reset system to normal with UCV at full speed Green

Fail each UCV quadrant fan in turn and Coanda fans (4 + 2) Red

Reset system to normal with UCV at full speed Green

Trigger HEPA filter high pressure switch Green plus Blue light

Yellow display information

box

End of day 10 minute warning that system will switch to “Set Back” or “Off” (Not all Theatre Control Panels have this facility)

Do nothing AHU & UCV go to “Set back” or “Off” Red

Reset to full speed including UCV Green

Yellow display information

box

End of day 10 minute warning that system will switch to “Set Back” or ”Off” (Not all Theatre Control Panels have this facility)

Press “Continue” System stays at full speed for 1 hour Green

Supply fan fails System shuts down. UCV to “Low speed or Off” Red

Reset system to normal Green

Yellow display information

box

Extract fan fails Warning on TCP and BMS.AHU locks out if fault not rectified by following day

Reset system to normal and UCV to full speed Green

[HTM 03-01 A – PDF page 205]

Appendix 10: Example cause-and-effect check-sheets

Site Date

Area served System ID

Test AHU/UCV Checks Y/N TCP Indication Y/N

Theatre temperature to be stable at 20°C at the start of this test.

Chiller battery valve opens fully

Reduce set point temperature to lowest possible on TCP

Record min temp reached and time taken to stabilise

Set temp: oC Measured: oC Ind (TP) oC Time taken mins

Heater battery valve opens fully

Increase set point temperature to highest possible on TCP

Record max temp reached and time taken to stabilise

Set temp: oC Measured: oC Ind (TP) oC Time taken mins

Reset set point to 20ºC Green

Red

Switch AHU “Off” Extract fan stops Supply fan stops Extract damper closes Supply damper closes UCV drops to “Set back”

Note any additional tests or checks below