[HBN 00-09 – PDF page 8]

1.0 Policy and legislation

1.0 Policy and legislation

of this guidance can be applied to all healthcare facilities.

1.1 High standards of environmental hygiene and clinical practice in healthcare facilities have been identified as being important in minimising the risk of the transmission of infection. The design, planning, construction, refurbishment and ongoing maintenance of the healthcare facility also have an important role to play in the prevention and control of infection. The physical environment has to assist, not hinder, good practice.

1.5 The information outlined in this document follows the general principles given in the ‘The Health and Social Care Act 2008: Code of Practice on the prevention and control of infections and related guidance’ (the HCAI Code of Practice). This Code of Practice sets out criteria against which a registered provider will be judged on how it complies with the registration requirement for cleanliness and infection control. Not all criteria will apply to every regulated activity.

1.2 The Chief Medical Officer’s report on infections and the rise of antimicrobial resistance (Davis, 2013) stated that the design, construction and maintenance of healthcare facilities have a substantial bearing on the risk of developing a healthcare-associated infection.

1.3 It is important that infection prevention and control (IPC) is designed-in at the planning and design stages of a new-build or refurbishment project and that input continues up to the final build stage. Designed-in IPC means that designers, architects, engineers, facilities managers and planners work in collaborative partnership with IPC teams to deliver facilities in which IPC needs have been planned for, anticipated and met.

1.4 This guidance highlights IPC issues and risks that need to be addressed at each particular stage to achieve designed-in infection control. The principles

1.6 The law states that the HCAI Code of Practice must be taken into account by the Care Quality Commission when it makes decisions about registration against the cleanliness and infection control requirement. The regulations also say that providers must have regard to the Code when deciding how they will comply with registration requirements. Therefore, by following the Code, registered providers will be able to show that they meet the requirement set out in the regulations. However, the Code is not mandatory. A registered provider may be able to demonstrate that it meets the regulations in a different way (equivalent or better) from that described in this document. The Code aims to exemplify what providers need to do in order to comply with the regulations.

[HBN 00-09 – PDF page 9]

2.0 Understanding the planning process

c. recorded its findings in relation to the first

Important

two points;

d. implemented the steps identified; and

e. put appropriate methods in place to

The infection prevention and control (IPC) team should be consulted throughout every stage of a capital project and their views taken into account.

monitor the risks of infection to determine whether further steps are needed to reduce or control infection.

The planning process 2.5 This section explains the planning process, which comprises the following stages (see Figure 1):

Introduction 2.1 For IPC teams to effectively participate in the planning process for both new-build and refurbishment projects, it is essential for them to understand the process from its inception to completion and commissioning.

a. Preparation of a business case to support the

viability of the project.

b. Project funding.

c. Concept/feasibility study.

d. Design stage.

2.2 It is important that the IPC team and the chief executive officer sign-off each stage of the project. This will ensure that IPC is considered throughout. An example IPC checklist that can be adapted for use during the different stages of a capital project is shown in Appendix 2.

e. Contract.

f. Project monitoring/construction.

g. Pre-handover inspections (“snagging”).

h. Commissioning the facility.

i. Post-project evaluation.

2.3 IPC is a fundamental imperative in the planning and design stages of a healthcare facility, yet it is often overlooked or compromised throughout the lifecycle of the project. IPC teams should be involved throughout all phases of construction and renovation projects to reduce IPC risks. Failure to assess these risks properly can lead to expensive redesign later and expose the patient and healthcare worker to infection hazards.

2.6 The aim is to prompt those with overall responsibility for managing capital schemes to include IPC advice at the right time in order to prevent costly mistakes.

Stages of IPC input

2.4 To provide and maintain a clean and appropriate environment in premises that facilitate the prevention and control of infections, the HCAI Code of Practice states that a healthcare provider should ensure that it has:

a. made a suitable and sufficient assessment of

the risks to the person receiving care with respect to IPC;

Preparation of a business case to support the viability of the project 2.7 The preparation of a business case is the process that supports a healthcare organisation’s submission for funding of new capital projects.

b. identified the steps that need to be taken to

reduce or control those risks;

[HBN 00-09 – PDF page 10]

2.0 Understanding the planning process

Issues to consider:

• Alterations to agreed design • IPC risk assessments and control measures (fungal spores etc)

Impact of design on:

• Space/sizing • Decontamination • Specialist areas • Engineering services (such as ventilation and water systems)

Need to assess if design can support:

• Storage (linen, waste, patient equipment, cleaners’ equipment) • Ancillary areas • Changing facilities • Location of hand-hygiene facilities

Discuss finer details of:

• Location and type of fixtures and fittings • Equipment schedules • Airflows in theatres • Wastewater and sanitation • Medical gas vacuum systems

Areas needing inspection/testing to demonstrate compliance with IPC:

• Theatres • Special ventilated isolation rooms • Clean rooms

Control of legionella and aspergillus

Concept

Feasibility study

Sketch plans

Detail planning/design

Contract Issues to consider:

Monitoring/construction

Pre-handover inspection

Commissioning/equip

Post-project evaluation

Figure 1 The planning process

[HBN 00-09 – PDF page 11]

• hand-washing facilities;

• furnishings and fittings;

2.8 A business case should convincingly demonstrate that the project is economically sound, is financially viable (affordable to the providers and purchasers) and will be well-managed. Above all, a business case for any investment should show that it will benefit patients.

• appropriate finishes which permit efficient cleaning methods, equipment and safe chemicals to be used;

• types and numbers of isolation facilities;

• specific products with IPC implications and applicable regulations (for example, type of pipes, Legionella precautions).

2.9 The involvement and support of a wide range of managers and staff may be vital to the success of the business case, both to determine the requirement and scope of the investment and also to participate in subsequent stages of planning.

2.14 Specifically at this stage, the IPC team will need to:

• agree the requirements for IPC in the design and planning of the project;

2.10 It is important therefore at this stage to identify and involve key people who have a direct interest in the end product; this will include members of the IPC team along with other leading clinicians, nursing managers and departmental heads.

2.11 Normally the input from the project team should be managed by the project director, but for larger and more complex schemes a project manager, reporting to the project director, may be appointed to conduct the detailed work and manage the business case team.

• assess the progress of the building/ refurbishment project in relation to compliance with IPC specifications – any unexpected proposed deviations from the infection-control specification needs to be agreed with the IPC team at the earliest opportunity;

2.12 Specifically at this stage, the project team will:

• set the strategic context;

• ensure that the designers/planners recognise the benefits of not cutting corners on IPC issues.

• define objectives and benefit criteria;

• generate options;

• measure the benefits;

• identify/quantify costs;

Project roles and responsibilities 2.15 A comprehensive approach to planning will include consultation with the appropriate specialists from inception through to post-project evaluation.

• assess sensitivity to risk;

2.16 The project organisation (see Figure 2) should comprise (relative to the size of the project):

• identify the preferred option;

a. Internal organisation of the healthcare

• present the outline business case.

provider:

Issues to be addressed by the IPC team 2.13 Issues to be addressed by the IPC team at this stage will include:

–– Healthcare provider’s management board (should monitor cost and progress of all capital investment projects at regular meetings. If problems are identified, it needs to be satisfied that appropriate steps are being taken).

• storage (including waste collection points and delivery areas) and equipment cleaning areas;

• flooring;

–– Chief executive officer (given the project-specific role, title, and responsibility of project owner).

• dirty utilities;

• cleaners’ rooms;

[HBN 00-09 – PDF page 12]

2.0 Understanding the planning process

Health organisation

board

Chief executive Project board (IPC input here)

Project director User panel

Adviser

Quantity surveyor Project manager

Suppliers Contractors Designers

Figure 2 Project organisation

Project funding

–– Project board (comprising senior staff within the provider organisation who have an interest in the project and whose activities will be affected by the project, for example staff from clinical areas such as IPC).

–– Project director (responsible for project management).

Capital projects funded through private finance initiatives 2.17 The contract between the purchaser and the private sector supplier is critical and it is important that the service representatives/key stakeholders and particularly in this instance the IPC team are clear about the options available and the evidence to back up any decisions they advise on.

–– Professional adviser (experienced in construction and design, especially of healthcare facilities).

2.18 The IPC team will need to make sure that certain criteria are embedded into the contract in such a way that important decisions on design or build do not go ahead without being signed off by them. The team will need:

• access to all relevant and up-to-date plans and information on operational policies;

–– User panel (representatives of each of the relevant service departments, in each case authorised to define their department’s needs and to review and agree how those needs are to be met) along with patients and carers.

b. External resources:

• access to any meetings deemed relevant to them or timely minutes from those meetings that they cannot attend;

–– Project manager.

–– Other consultants.

• access to sites and departments as building work progresses at the appropriate time in the construction programme, for example environmental rounds with checklists based on project objectives;

[HBN 00-09 – PDF page 13]

• regular communication between the internal project manager and the project team;

• future maintenance requirements that minimise the potential risks to patients and allow for it to be effectively carried out.

• involvement in decision-making for any category of equipment the project team will purchase;

• involvement in any contracts for support services (such as catering, cleaning, linen, or sterile services) that the project team may be providing;

2.21 To assist with understanding and mitigating the risks associated with bacterial contamination of water distribution and supply systems, it is recommended that organisations should develop a water safety plan (WSP), which provides a risk- management approach to the microbiological safety of water and establishes good practice in local water distribution and supply. Those organisations with existing robust water management policies for Legionella will already have in place much of the integral requirements for developing a WSP.

• access to certain areas for any microbiological testing deemed necessary at commissioning and prior to handover, for example theatres, pharmacies and clean rooms in sterile services departments.

Note:

For further guidance, see:

• Health Technical Memorandum 04-01: ‘The control of Legionella, hygiene, “safe” hot water, cold water and drinking water systems’; and

Concept/feasibility study 2.19 The planning process starts with the identification of a “need” by the users. The development of this need will involve feasibility studies to enable a design brief or output specification to be developed.

• Health Technical Memorandum 04-01: ‘Addendum: Pseudomonas aeruginosa – advice for augmented care units’.

2.20 Where existing facilities are being modified or extended, the IPC team should review all operational policies and procedures, for example:

Design stage 2.22 The design brief or output specification should highlight the importance of design solutions for IPC.

• the effect the number of beds or departments will have on current policy and practice such as sterile services, catering, waste disposal and cleaning;

• contracts for support services such as catering, cleaning, linen, sterile services etc that the project team may be providing;

2.23 At this stage, the IPC team will need to follow up any input they have had in the initial design brief. Sketch plans should be available to the team to explain how the design brief fulfils their requirements at the 1:200 sketch design and 1:50 scale detail design stages of the project. Suggestions for improvement in operability are important at this stage.

• additional specialist areas that may require additional IPC and laboratory services (consideration should also be given to acquiring specialist advice from external agencies);

• location and relationships between departments;

• the number of surgical instruments and provision of decontamination facilities when planning extra theatres;

2.24 At the end of each part of the design stage, the project team and the IPC team will be required to sign-off the information issued and reviewed. This signifies that the design-brief requirements and changes agreed during discussions have been incorporated. Any subsequent changes made after sign-off should be made via a “change protocol”, which can have significant cost and programme implications for the project.

• impact of proposed design on ventilation and water systems;

[HBN 00-09 – PDF page 14]

2.0 Understanding the planning process

Detail planning/design (1:50 scale designs) – early period 2.26 At this point the 1:50 scale designs indicating equipment and furniture layouts and room data sheets will be available. There may be two or more stages to the consultation process.

Sketch plans (1:200 scale designs) 2.25 At this stage, 1:200 scale outline departmental layout drawings showing rooms outlined within departments will be available and discussions held with the design team. The IPC team needs to assess whether the facility is designed to support the prevention and control of infection. Examples include:

• confirming operational procedures;

• establishing baseline and future staffing profiles;

• establishing baseline and future revenue budgets;

Detail planning/design (1:50 scale designs) – later period 2.27 The IPC team will need to discuss finer details such as location and type of fixtures and fittings (for example, type and size of wash-hand basins and airflows in theatres). Room elevations of selected typical generic rooms should also be made available.

• establishing equipment requirements;

• strategy for equipping;

• procurement and selection of furnishings and equipment;

• missing rooms/facilities;

• appropriate placing and accessibility of hand-hygiene facilities;

2.28 Equipment schedules for groups 1, 2 and 3 (see next page) based on room data sheets/layouts are prepared at this stage. It is important that there is active involvement of the IPC team at this point, as it may have significant design implications. This will ensure that this equipment is compatible with IPC needs and also that proper inspection and testing can be agreed.

• single-bed rooms suitable for patient isolation and special ventilated isolation rooms;

2.29 A final review of room layouts, equipment, fittings and room data sheets should be carried out at the end of this stage, as this is where the final sign-off by the project team and the IPC team occurs.

• ventilation and air-conditioning systems including the level of filtration where specialised ventilation is required;

• water supply, heating and plumbing;

• storage for:

2.30 Any changes made during construction or after completion could have a significant adverse impact on costs and the building project.

–– personal protective equipment (PPE)

–– movable equipment

–– clean patient items

2.31 Items available for transfer from an existing facility should also be identified, which will allow schedules for new equipment to be prepared and costs identified.

–– clean linen

–– healthcare waste, including sharps, and used linen;

• surfaces: ceilings, walls, work surfaces, floor coverings and furnishings;

• utility rooms: dirty, clean, holding, workrooms, cleaners’ rooms;

• changing rooms;

• pneumatic delivery systems.

[HBN 00-09 – PDF page 15]

Group 1

Items that are supplied and fixed under the terms of a building/engineering contract and funded within the works cost. These are generally large items of plant/equipment that are permanently wired/installed, for example:

Contract 2.32 Tender documents sent to potential companies should include any statements the healthcare provider/project team may have about IPC that may affect any successful contractor’s employees. It should also comprise IPC requirements such as the control of Legionella and other microorganisms (for example, aspergillus).

• specialist equipment best suited to central purchasing arrangements;

• taps, sinks and wash-hand basins.

Project monitoring/construction

Excluded from this group will be items subject to late selection due to considerations of technical change, for example radiodiagnostic equipment.

Group 1 items are specified at the design stage.

Group 2

Construction 2.33 Monitoring will not normally be required by the IPC team until the works are at a stage when site visits can be arranged. At this point, the IPC team should visit the site so that that they can make a suitable ongoing assessment of the layout of the departments. This will facilitate the team to identify any differences/problems from the agreed design.

Items that have implications in respect of space/ construction/engineering services and are installed under the terms of building engineering contracts, but are purchased by the healthcare provider under a separate equipment budget, for example:

• paper towel dispensers;

• soap/scrub dispensers;

• cupboards;

• shelving;

• washer-disinfectors, including bedpan washer- disinfectors or macerators;

• washing machines;

Surveillance and monitoring during renovation or construction work adjacent to an existing facility 2.34 Where patients with increased susceptibility to infection may be placed at risk, it is important that an appropriate risk assessment is carried at an early stage in advance of any building works, including disturbance/alterations to the water system/building fabric/ventilation systems (see Appendix 3).

• worktops.

Group 3

2.35 Quality assurance of IPC interventions during building work should be based on a suitable and sufficient risk assessment of the precautions needed and frequent audit of the control measures in the risk assessment.

Items that have implications in respect of space and/or construction/engineering services and are purchased and delivered/installed directly by the healthcare provider, for example:

• small refrigerators;

• furniture;

• ventilators;

• monitors;

• trolleys.

2.36 Since airborne fungal spores can travel significant distances, this will apply generally to all works in the immediate vicinity or within the boundary of the healthcare facility. It is strongly advised that any recommendations informed by the risk assessment should be incorporated into the building (see Appendix 3) or engineering project so as to minimise risk both during construction and in future use.

Group 4

Items that may have storage implications but otherwise have no impact on space or engineering services, for example surgical instruments.

2.37 Where water systems are closed down, a Legionella risk assessment should be undertaken. This should include the risk bacterial overgrowth in dead-legs pose to adjacent water systems. Flushing

[HBN 00-09 – PDF page 16]

2.0 Understanding the planning process

and hyperchlorination should also be considered when the water system is reinstated.

2.42 By understanding the commissioning process, the IPC team should ensure that they are fully consulted and engaged in any working groups in which their expertise will have an impact or in which requirements to modify services may have repercussions on other aspects of IPC.

See Health Technical Memorandum 04-01 and Health Technical Memorandum 04-01: ‘Addendum: Pseudomonas aeruginosa – advice for augmented care units’.

2.43 The IPC team should also be involved in processes for:

• analysis of commissioning data;

• transfer of facilities;

• phased or staged occupation;

• storage and subsequent cleaning/disinfection of any furniture or equipment;

• approval of engineering commissioning data for operating theatres;

Pre-handover inspections 2.38 The IPC team should conduct periodic walk- round inspections (commonly referred to as “snagging” visits) during the construction works and also at the completion of the construction works prior to formal handover. They should raise any concerns and outstanding items with the project manager responsible for the capital scheme, with issues that constitute a high risk being appropriately prioritised. The project manager should then address these issues with the contractor and ensure the necessary works are completed prior to formal handover of the construction project.

• commissioning tests (for example, microbiological air-sampling for operating theatres, water testing);

• approval of engineering commissioning data for special ventilated isolation room(s);

• site visits;

• staff orientation and training;

• post-handover period;

Commissioning the facility 2.39 Upon completion of construction, the facility should be brought into use; depending on the complexity of the task involved, a commissioning manager and team may be needed. Senior managers, specialist teams and users should be fully involved in the process.

• decommissioning of redundant facilities;

• period of handover to operational management;

• confirming communication of procedures with internal and external agencies/users (for example, ambulance service and patient information leaflets).

2.40 Technical commissioning of the building, services and equipment should include any areas that require inspection and testing to demonstrate compliance with IPC standards (for example, theatres, hydrotherapy pools, special ventilated isolation rooms/suites and clean rooms in pharmacies and sterile services departments). Sufficient time should be built into the commissioning schedule to enable this and any rectification of identified problems.

2.41 The commissioning team should establish smaller working groups that:

Post-project evaluation 2.44 The purpose of the post-project evaluation is to improve project appraisal, design, management and implementation. It typically takes place 12 months post-handover and is a learning process that should not be seen as a means of allocating blame. There are three stages:

• identify policy issues for referral to the commissioning team or the construction project team;

a. project appraisal;

• identify staff training and orientation needs;

b. monitoring and evaluation of project;

c. review of project operations.

• establish the occupation programme for that user function, for inclusion into the overall commissioning master plan.

[HBN 00-09 – PDF page 17]

2.46 It is important that the project is evaluated in terms of its original objectives, not in the light of any new legislation or development. Performance indicators may be used if these can be measured retrospectively. Measurable objectives may include:

• activity data;

• patient satisfaction surveys etc;

2.45 It is at the third stage when it is useful for the IPC team to be included in the evaluation teams that are reviewing project objectives. The outcomes (activity and its consequences) of the project will not be amenable to evaluation until the facility has been in use for sometime. However, if the project is part of a phased refurbishment or new build, valuable lessons can be learned and implemented during ongoing project work.

• compliance with Legionella risk assessments.