Preamble Health Building Note 00-09 supersedes and replaces all versions of Health Facilities Note 30 (HFN30).
Although the specific recommendations or processes it outlines may not necessarily be relevant to all types of healthcare facility or organisation, they may become more applicable as certain healthcare services and functions are decentralised.
The most important points raised by the document are the need:
• for an awareness of appropriate Health Building Notes and Health Technical Memoranda pertinent to new build or refurbishment projects;
• for timely, comprehensive and collaborative partnership between all parties to achieve IPC goals specific to each construction project;
• for all stakeholders to understand the basic principles of “designed-in” IPC;
Introduction The importance of a clean, safe environment for all aspects of healthcare should not be underestimated. It is important that healthcare buildings are designed with appropriate consultation, and the design facilitates good infection prevention and control (IPC) practices and has the quality and design of finishes and fittings that enable thorough access, cleaning and maintenance to take place. Good standards of basic hygiene, cleaning and regular planned maintenance will assist in preventing healthcare-associated infection (HCAI); only if the built environment reflects these needs are schedules more likely to be successful not only in being undertaken on a proactive and reactive basis but also in reducing contamination and risks to patients.
• to understand and assess the risks of infection relating to construction projects and the physical environment;
• for robust project management in relation to IPC considerations for all new-build and refurbishment projects;
Research and investigation have consistently confirmed that the healthcare environment can be a reservoir for organisms with the potential for infecting patients. For HCAIs to be reduced, it is imperative that IPC measures are “designed-in” at the very outset of the planning and design stages of a healthcare facility and that input continues up to, into and beyond the final building stage.
• for a system of signing-off plans and meeting notes to include all participating parties including the IPC team;
• for quality control throughout the duration of the construction project;
• to regularly consult with and update all relevant parties throughout the project;
Designed-in IPC means that designers, architects, engineers, facilities managers and planners work in collaborative partnership with IPC teams, healthcare staff and the users to deliver facilities in which IPC needs have been anticipated, planned for and met.
• to continually monitor developments.
Health Building Note 00-09 This guidance discusses the various stages of a capital build project from initial concept through to post- project evaluation and highlights the major IPC issues and risks that need to be addressed at each particular stage to achieve designed-in IPC.
Exclusions This document does not deal with the operational management of IPC issues (for example, dealing with outbreaks on a ward) or day-to-day standard IPC precautions. These issues will be dealt with locally via the healthcare organisation’s own policies and procedures on IPC.
This guidance does not apply to prison hospitals.
The principles of this guidance can be applied to all healthcare facilities (guidance on mental health settings is included in this revision – see Appendix 1).
Important It is essential that the IPC team are consulted throughout every stage of a capital project and their
expertise taken into account.
iv
[HBN 00-09 – PDF page 7]
Contents
Executive summary iv
Chapter 1 Policy and legislation
Chapter 2 Understanding the planning process Introduction The planning process Stages of IPC input
Chapter 3 Designing a healthcare facility: issues to consider Examples of design principles Sizing/space Isolation facilities Hand-hygiene facilities Ancillary areas Storage Interior finishes/fixtures and fittings Changing facilities Laundry and linen services Catering/food hygiene Healthcare waste Engineering services
Appendix 1 – Mental health and learning disability settings
Appendix 2 – Example of a typical IPC checklist
Appendix 3 – IPC risk assessment during construction/refurbishment of a healthcare facility
Appendix 4 – Microorganisms and infections: a guide for designers
Appendix 5 – Glossary
References