SHTM 81 part 1: 23. Storage areas / 24. Photovoltaic panels (PV)
[SHTM 81 part 1 – PDF page 34]
23. Storage areas
The design and construction of healthcare premises should ensure that there are sufficient storage areas to prevent the potential for inappropriate storage that would compromise escape routes.
External collection and storage spaces should be sited at a safe distance from the building to ensure a fire in the storage area does not affect the occupied premises. Generally, a safe distance is considered as a minimum of three metres from the building. However, the final location should always be subject to completion of a Fire Risk Assessment that takes account of the following risk factors:
the type of external wall cladding;
the construction of any canopy to determine if it will contribute to fire spread if ignited;
the quantity of combustible material.
the likelihood and effect of smoke entering windows or other openings;
the means of identifying a fire in the storage area.
[SHTM 81 part 1 – PDF page 35]
24. Photovoltaic panels (PV)
Photovoltaic (PV) Panels should conform to BS EN 61215 or BS EN 61646 in conjunction with BS EN 61730-1.
PV panels should be installed in accordance with Microgeneration certification scheme (MCS) 2012 – ‘Guide to the Installation of Photovoltaic Systems and any specific guidance issued by manufacturers.
Photovoltaic (PV) panels should be provided with:
a switch in a prominent location, that is readily accessible to firefighters to isolate the DC side of the PV system, this switch should be provided with appropriate signage;
automatic smoke detection in the area inside the building in which the electrical control equipment for PV panels is located. This is particularly important in the case of a loft or other area that is normally unoccupied;
portable fire fighting location points adjacent to the control and switchgear;
a suitable mounting system so that they do not straddle heat expansion joints or fire compartment walls;
ground fault detection units to prevent short circuits.
Where roof mounted, there should be sufficient spacing between PV panels to allow effective firefighting and allow access for maintenance.
Secondary cells and batteries used for renewable energy storage should comply with BS EN 61427-1: Secondary cells and batteries for photovoltaic energy systems.