10. Construction and compartmentation
Introduction
Every building must be designed and constructed in such a way that in the event of an outbreak of fire within the building, fire and smoke are inhibited from spreading beyond the compartment of origin.
Compartment wall
A compartment wall with a medium fire resistance duration should be provided between different hospital departments and hospital departments and protected zones.
Compartment
Every compartment in a hospital should have a maximum area of 1500m2.
Every upper storey and every basement storey should form a separate compartment.
Sub-compartment
Every compartment should be divided into at least 2 sub-compartments by a wall with short fire resistance duration, so that no sub-compartment is more than 750m2.
Where a compartment is under the maximum size of a sub-compartment, it need not be further sub-divided, except where it is the only compartment on a floor, then it should be sub-compartmented to provide the facility for progressive horizontal evacuation.
Minimum storey areas
Every storey in a hospital at a height of more than 7.5m containing departments to which patients have access should either comprise at least 4 compartments, each of which should have an area of at least 500m2 or have a hospital street and at least 3 other compartments.
In a hospital, every storey at a height of more than 18m containing departments to which patients have access should either comprise of at least 4 compartments, each of which should have an area of at least 500m2 or have a hospital street and at least 3 other compartments each of which should have an area of at least 500m2.
Wards occupied with very high dependency patients
Every ward occupied with very high dependency patients should be divided into at least 2 sub-compartments by a sub-compartment wall of short duration fire resistance.
[SHTM 81 part 1 – PDF page 15]
Every entrance to a ward occupied with very high dependency patients should be from a hospital street or through a lobby that is enclosed with short duration fire resistance.
Fire hazard rooms and fire hazard departments
In hospitals and in some instances other healthcare premises, certain rooms and departments that have an inherent fire risk, require an enhanced level of fire precautions.
These are termed fire hazard rooms or fire hazard departments and they should be enclosed in fire resisting construction so that fire is contained for a sufficient time to secure the safe evacuation of adjacent patient care areas.
The following fire hazard rooms and fire hazard departments should be enclosed with short duration fire resistant construction, including windows, vents, ducting and door sets:
wards and bedrooms designed for very high dependency patients and patients with severe mental health illness;
chemical stores;
domestic services rooms that are designed to allow storage of flammable materials, chemicals, or the charging of electrical devices/equipment;
day rooms (floor area over 20m2);
smoking rooms (where permitted);
disposal rooms;
laboratories;
lift motor rooms;
linen stores;
kitchens with full cooking facilities;
laundry rooms;
staff changing and locker rooms;
x-ray and record stores;
store rooms that are designed to allow storage of flammable materials, chemicals, or the charging of electrical devices/equipment;
rooms designed specifically for the charging of electrical devices/equipment;
flammable stores;
Any other room or department with a correspondingly high fire load.
The undernoted departments should not be located directly below or adjoin operating theatres, wards occupied with very high dependency patients or special care baby units (SCBUs).
[SHTM 81 part 1 – PDF page 16]
Where they are located below, or adjoin any other hospital department to which patients have access, they should have a fire suppression system installed.
boiler houses;
central stores;
commercial enterprises;
flammable stores;
laundries;
main electrical switchgear;
main kitchens;
refuse collection and incinerators;
any other department with a correspondingly high fire load.
The undernoted departments should have an automatic fire suppression system where they are located directly below, or adjoin operating theatres or wards occupied with very high dependency patients.
central staff changing facilities;
central sterile supplies;
hospital sterilising and disinfecting units;
health records departments;
pathology;
manufacturing pharmacies;
any other department with a correspondingly high fire load.
Combustibility
In a Hospital, compartments should have walls, floors and ceilings (attached to the roof structure), constructed of products that achieve European Classification A1 or A2 or it can be demonstrated that the fire performance of the completed structure achieves the intent of the building regulations. However sub-compartments may be constructed with products of European Classification B, C, D or E, provided the completed structure achieves short duration fire resistance.
Junction with external walls
Where a compartment wall or sub-compartment wall meets an external wall, there should be a 1m wide strip of the external wall which has the same level of fire resistance duration as the compartment wall or sub-compartment wall, to prevent lateral fire spread.
Where a lower roof abuts an external wall, the roof should provide a medium duration fire resistance for a distance of at least 3m from the wall.
[SHTM 81 part 1 – PDF page 17]
Cavity barriers
Cavity barriers need not be provided to divide a cavity above an operating theatre and its ancillary rooms.
Where cavity barriers are installed between a roof and a ceiling above an undivided space, the maximum limit of 20m should be applied.
Corridors
Corridor walls serving sleeping accommodation should be constructed of short duration fire resistance including windows, vents and ducting. Any door in the wall should have short duration fire resistance and be fitted with self-closing devices. Cupboard or storeroom doors should be of short duration fire resistance, but do not require self- closing devices provided they are kept locked shut when not in use.
Protected lobbies
Protected lobbies should not form part of a through route i.e. they should not be located across a corridor if the corridor continues beyond the protected lobby.
External wall systems
External wall systems, including cladding and insulation, on all hospitals with a total floor area of more than 200m2, should be constructed of products achieving European Classification A1 (non-combustible) or A2 (will not significantly contribute to fire load and fire growth).
See Scottish Advice Note: Determining the fire risk posed by external wall systems.
Car parks
Direct access from an enclosed car park to a hospital should be via a protected lobby.
Vertical access from an enclosed car park to a hospital should be via a protected lobby in the stair enclosure.