2. Scope of SHTM 81
Throughout this guidance, reference is made to healthcare premises owned or occupied by NHS Scotland; however, the standards apply equally to premises that are owned or managed by any other healthcare provider.
Designers should reference this document and other NHS Scotland SHTM Firecode documents, in conjunction with the Building Standards technical handbook non- domestic.
This guidance is specifically applicable to healthcare premises used for the treatment of patients. Buildings that do not have patient access such as offices, laboratories, and storage facilities, and are not physically connected to a patient treatment facility should be designed and constructed in accordance with the technical handbook non- domestic.
Many premises that do not have patient access are integral to the delivery of healthcare services e.g. warehouses and pharmacies. NHS Scotland Health Boards may wish to include particular aspects of this document, such as increased compartmentation or fire suppression systems, to protect the infrastructure and ensure business continuity.
Use by competent person
The guidance in this document has been prepared on the understanding that it can be interpreted and utilised by ‘competent persons’, who are appropriately qualified with sufficient technical knowledge relevant to the healthcare environment.
Consultation
NHS Scotland Bodies commissioning new healthcare premises and extensions or structural refurbishments to existing facilities should ensure that, at the earliest stage of the design process, there is close collaboration between all parties, including the Health Boards fire safety advisors regarding the fire safety provisions. This applies to all premises whether owned, leased, public private partnership or third party contract.
Scottish Government policy (CEL(2010)19) mandates NHS Scotland Bodies follow the built environment investment quality processes. These include the NHS Scotland Design Assessment Process (NDAP), and the NHS Scotland Assure processes (DL(2021)14).
It is essential that there is early consultation between the design team, the Health Boards subject matter experts, the Health Board fire safety advisor and clinical teams to ensure there is no conflict between patient care and fire safety requirements. It may also be appropriate to liaise with the client’s insurers and the Health Boards legal advisors.
[SHTM 81 part 1 – PDF page 7]
3. Fire safety during construction
The potential danger from fire is particularly severe on many construction sites, where high-risk activities, such as hot works are frequently combined with circumstances where fire can spread quickly, and escape may be difficult. If a worksite is within the curtilage of an existing healthcare facility, any fire incident has the potential to significantly impact on the occupied premises. Therefore, site activities of contractors should be supervised and controlled to ensure that a suitable means of escape remains available throughout the construction process, including handover and commissioning, from the occupied premises and construction site.
Construction sites are designated as ‘relevant premises’ for the purposes of Part 3 of the Fire (Scotland) Act. Therefore, where a construction site shares part of a site with an operational healthcare facility, the occupiers of the respective parts must co- operate to ensure there are adequate fire precautions to ensure the safety of all persons.
The Health Board should appoint a nominated person during the commissioning and handover phases to ensure that suitable fire safety precautions are put in place to compensate for any snagging work activity that impacts on the fire safety provision or fire safety systems being inoperative whilst testing takes place.
The Health Boards fire safety advisor should liaise closely with the nominated person.
If a construction site adjoins or is within the curtilage of an existing healthcare facility, the existing emergency fire action plan should be reviewed and revised to take account of the effect of works on the means of escape provision. The revised plan should take particular account of works that are close to an access or exit route, ambulance and other emergency vehicle arrival areas, supply delivery areas, medical gas cylinder handling areas and storage areas containing highly flammable materials.
The management arrangements must include a fire safety procedure for the site at all phases of construction, including commissioning and handover.
All persons working on or visiting the site should receive fire safety induction training regarding the work activity, the means for raising an alarm of fire and the evacuation procedures. Further information is available in HSE guidance: Fire safety in construction (HSG168).