[HTM 05-02 – PDF page 103]

Appendix J: Qualitative Design Review

facilities managers and the fire safety advisor;

c. design team – architects and engineers;

d. fire service representative; and

e. building control or approved inspector.

Because of the complex and changing nature of healthcare and the often conflicting requirements between fire safety and nursing care etc, it is therefore essential that early consultation takes place between all relevant parties; ideally this consultation should form a Qualitative Design Review, as detailed in PD 7974-0:2002, ‘Application of fire safety engineering principles to the design of buildings — Part 0: Guide to design framework and fire safety engineering procedures’. The following information has been taken from the aforementioned PD 7974:0: 2002.

The QDR is a structured technique that allows the team to think of the possible ways in which a fire hazard might arise and establish a range of strategies to maintain the risk at an acceptable level. The fire safety design can then be evaluated quantitatively or qualitatively against the objectives and criteria set by the team. The QDR should be conducted in a systematic way to reduce the chance of a relevant item being missed.

The QDR is essentially a qualitative process that draws upon the experience and knowledge of the fire safety engineer and a team of others involved in the design and operation of the building.

Whilst the QDR is essentially a qualitative process, it can often be useful to carry out quick calculations to resolve a difference of opinion between team members or to establish the most significant scenarios for detailed quantification.

The main stages in the QDR are:

a. review architectural design and

For very large and complex projects, it is recommended that the QDR be carried out by a study team involving one or more fire safety engineers, other members of the design team and a member of operational management. It might also be appropriate to include representatives of approval bodies or the insurers to ensure that their views can be accounted for.

occupant characteristics;

b. establish fire safety objectives;

The QDR team on a major project might include the following:

c. identify fire hazards and possible

consequences;

a. fire safety engineer (chair);

d. establish trial fire safety designs;

b. client user group – generally involving

clinicians, nurses, managers, estates or

[HTM 05-02 – PDF page 104]

e. identify acceptance criteria and methods

of analysis;

electronic security locks), and fire-and- smoke dampers;

f. establish fire scenarios for analysis.

− − automatic fire detection systems, emergency communication systems, CCTV, fire safety signage, emergency lighting, fire extinguishers;

− − dry or wet risers and other fire-fighting equipment, other interior facilities for the fire-and-rescue service, emergency control rooms, location of hydrants outside the building, and other exterior facilities for the fire-and- rescue service;

All findings should be clearly recorded so that the underlying philosophy and assumptions that underpin the FSE study are explicit and can be readily checked by a third party. This information should be contained in the Fire Safety Strategy for the premises. Information provided to support Regulation 38 should include the following information. The reader should note that the information detailed below is only intended as guidance; however, the level of detail required will vary from building to building and should be considered on a case- by-case basis:

− − sprinkler system(s) design, including isolating valves and control equipment; and

• the fire safety strategy, including all assumptions in the design of the fire safety systems (such as fire load), and any risk assessments or risk analysis;

− − smoke-control system(s) (or HVAC system with a smoke-control function) design, including mode of operation and control systems;

• any high-risk areas (for example heating machinery) and particular hazards;

• all assumptions in the design of the fire safety arrangements regarding the management of the building;

• as-built plans of the building showing the locations of the above;

• escape routes (including stairs and lifts), escape strategy (for example simultaneous or phased) and muster points;

• details of all passive and active fire safety measures, including (but not exhaustively):

• specifications of any fire safety equipment provided, including operational details, operator manuals, software, system zoning, routine inspection, and testing and maintenance schedules. Records of any acceptance or commissioning tests;

• any other details appropriate for the specific building;

− − compartmentation (that is, location of fire-separating elements), cavity barriers, fire doors, self-closing fire doors and other doors equipped with relevant hardware (for example

• findings of the QDR consultation.