HBN 00-09: Appendix 3 – IPC risk assessment during construction/refurbishment of a healthcare facility
[HBN 00-09 – PDF page 41]
Appendix 3 – IPC risk assessment during construction/refurbishment of a healthcare facility
1. Quality assurance in IPC associated with building work, fungal spore generation and susceptible patients should be centred on the three principles of:
a. identifying susceptible patient groups;
Help to reduce specific infection problems during construction 4. A planned contamination-control programme is essential when building work of any nature is planned.
b. where necessary, using methods of work that
reduce the dissemination of airborne fungal spores; and
c. protecting susceptible patients from those
airborne fungal spores that will be generated.
5. Early and sustained involvement of the IPC team in the planning process is essential and will lead to minimising of potential infection risks. Building dust control measures may not be sufficient for the control of fungal spore release; therefore, the following should be considered:
• Use floor-to-ceiling barriers that completely enclose the work area.
2. The first principle is one of clinical risk assessment. The second and third are deciding on actions and ensuring those actions are constantly applied for the duration of the risk. This could be achieved by:
• Seal windows in areas accommodating patients assessed as susceptible to minimise ingress of fungal spores generated by nearby building work.
• instruction of those working on the project, those in the estates team and clinical staff in affected areas;
• If vacuum cleaners are used, ensure they have high efficiency filters on exhausted air.
• routine monitoring of actions and precautions; and
• Use a vacuum cleaner with a HEPA filter to clean areas daily or more often if necessary.
• an efficient reporting and reaction system (should deficiencies be identified).
• Transport debris in sealed bags or containers with tightly fitting lids, or cover debris with a wet sheet.
• The removal of debris by chutes is liable to produce airborne fungal spores. The use and positioning of chutes should be carefully considered.
• Do not haul debris through patient-care areas but through an exit restricted to the construction crew.
3. Patients who are highly immunocompromised are thought to be a particular risk from infection by inhalation of fungal spores whose airborne concentrations are thought to increase in association with demolition, construction, maintenance and refurbishment (that is, building) works. The occurrence of clusters of fungal infection associated with building works has been observed on a number of occasions, which suggests the need to minimise the risk of spore dispersal during this time. Many of the recommendations in this appendix are based on consensus rather than scientific observation. The following measures are thought to reduce the dissemination of spores, including aspergillus.
[HBN 00-09 – PDF page 42]
Appendix 3 – IPC risk assessment during construction/refurbishment of a healthcare facility
• Commission additional hotel services with regard to cleaning during construction projects.
• Temporary storage for clinical equipment and clean linen should be clean and free of pests.
Monitoring 6. Demonstration that measures have reduced ingress of fungal spores into protected areas can be demonstrated by exposing settle plates in protected areas and comparing fungal deposition on these with equivalent settle plates exposed outside protected areas at the same time and for the same duration.
7. There is limited evidence that occasional active sampling for fungal spores demonstrates that protective measures are effective.
1. First, identify construction activity type from the table below.
Type A Inspection and non-invasive activities, includes, but not limited to: • removal of ceiling tiles for visual inspection on corridors and non-clinical areas; • painting and minimum preparation in corridors and non-clinical areas; • electrical trim work (all plugs, switches, light fixtures, smoke detectors, ventilation fans); • minor plumbing and activities that do not generate dust or require cutting of walls or access to ceilings other than for visual inspection.
Type B Small scale, short duration activities that create minimal dust. Includes:
• removal of a limited number of ceiling tiles in low risk clinical areas for inspection only; • installation of telephone and computer cabling; • access to chase spaces; • cutting of walls or ceiling where dust migration can be controlled in non-clinical areas.
Type C Any work of long/short duration which generates a moderate-to-high level of dust or requires minor building works, demolition or removal of any fixed building components or assemblies. Includes, but is not limited to: • sanding of walls for painting or wall covering; • removal of floor coverings, ceiling tiles, panelling, and wall-mounted shelving and cabinets; • new wall construction; • minor duct work or electrical work above ceilings; • major cabling activities.
Type D Major demolition and construction projects. Includes, but is not limited to new construction/machinery and equipment installations, rectifications and modifications
2. Then identify the infection control risk group by area.
) k sir h gih ( p u o r G ) k sir m ui d e m ( p u o r G ) k sir w ol( p u o r G
s m o o r y r e g r u s y a D s m o o r la cinilc E & A sr o dirr o c/ s a e r a e ciff O plant rooms/ service Radiology/magnetic resonance imaging All intensive care units
s e tiu s g nit a r e p o ll A stin u y r e v o c e r y r e g r u s la r e n e G st c u d
Ward A s ll high dependency units
stin u t n al p s n a rt & sis ylai D e nici d e m r a elc u N
Primary care/community treatment rooms
y g olo c n O stin u e g r a h c si d / s n ois si m d A
y g oloi d r a C y h p a r g oi d r a c o h c E Other departmental clinical areas Cardiac catheterisation suite
s m o o r n a elc y c a m r a h P t n e m tr a p e d t n eit a p -t u O
Bone marrow transplant units Sterile services departments
)la r e n e g ( y c a m r a h P Laboratories Endoscopy clinics Examination rooms
3. Now identify the “risk class” by correlating “construction type” with “risk group” (from 1 and 2 above) in the matrix below.
Construction activity type
Risk group Type A Type B Type C Type D
Group 1 Class 1 Class 2 Class 2 Class 3 Group 2 Class 1 Class 2 Class 3 Class 3 Group 3 Class 2 Class 3 Class 3 Class 4
[HBN 00-09 – PDF page 43]
4. After identifying the risk class from 3 above, follow the risk measures advised for each class.
Class 1 • Execute work by methods to minimise dust from construction • Immediately replace any ceiling tile displaced for visual inspection
Class 2 • Where appropriate, isolate HVAC (heating, ventilating, and air conditioning) system in areas where work is being performed • Provide active means to prevent airborne dust from dispersing into atmosphere if practicable, i.e. dust bag to machine • Water-mist work surfaces to control dust while cutting • Avoid pooling of water which may be prolonged • Seal unused doors with duct-tape • Block off and seal air-vents • Wipe work surfaces with detergent • Contain construction waste before transport in tightly covered containers • Wet-mop and vacuum with filtered vacuum cleaner before leaving work area • Place dust-attracting mat at entrance and exit of work area (tacky mat) • Remove isolation of HVAC system
Class 3 • Where appropriate, isolate HVAC system in area where work is being done to prevent contamination of duct system • Complete all critical barriers and implement dust control methods before construction begins • Maintain negative air pressure within work site. Use HEPA (high efficiency particulate air)-equipped air filtration unit if there be a risk that air will enter building • Do not remove barriers from work area until complete project is clinically clean • Vacuum with filtered vacuum cleaner during works • Wet-mop area during works • Remove barrier materials carefully to minimise spreading of dust and debris associated with construction • Contain construction waste before transport in tightly covered containers • Remove isolation of HVAC system in areas where work has been done and appropriate checks performed
Class 4 • Isolate HVAC system in area where work is being done to prevent contamination of duct system • Complete all critical barriers and implement dust control methods before construction begins • Maintain negative air pressure within work site using HEPA-equipped air filtration unit • Seal holes, pipes, conduits and punctures appropriately • Construct airlock and require all personnel to remove dirty apparel and clean down before leaving the work site. The use of cloth/paper disposable overalls/shoes, etc., may be required • Do not remove barriers from work area until completed project is thoroughly cleaned (as before) and repeat clinical clean after barrier removed • Vacuum work area with filtered vacuum cleaner • Wet-mop area with detergent during works • Remove barrier materials carefully to minimise spreading of dust and debris associated with construction • Contain construction waste before transport in tightly covered and sealed containers • Remove isolation of HVAC system in areas where work has been done and appropriate checks performed